WWI Investor Presentation - Mining Indaba 2025 (amended)
Released
Released
Announcement PDF
ASX Announcement and Media Release
Monday, 10 February 2025
West Wits Mining Presentation
121 Mining Investment and Mining Indaba South Africa
(amended)
West Wits Mining Limited (ASX: WWI) (OTCQB: WMWWF) (“the Company”) releases the enclosed
amended presentation which amends the presentation released to ASX on 3 February 2025. The
amendment was requested by ASX and comprises recission of a graph from Slide 10 which ASX
determined was not compliant with Listing Rule 5.16.6. The information contained in the graph which
has been removed cannot be relied upon.
There are no other amendments to the enclosed presentation.
Approved for release by the Chairman.
Investor Relations
Keith Middleton
keith@middletoncorporate.com.au
General
info@westwitsmining.com
westwitsmining.com
linkedin.com/company/west-wits-mining
ABOUT WEST WITS MINING LIMITED
West Wits Mining Limited (ASX: WWI) (OTCQB: WMWWF) is focused on the exploration, development and
production of high-value precious and base metals for the benefit of shareholders, communities and
environments in which it operates. Witwatersrand Basin Project, located in the proven gold region of Central
Rand Goldfield of South Africa, boasts a 5.025Moz gold project at 4.66g/t2. The Witwatersrand Basin is a largely
underground geological formation which surfaces in the Witwatersrand. It holds the world's largest
known gold reserves and has produced over 1.5 billion ounces (over 40,000 metric tons), representing about 22%
of all the gold accounted for above the surface. In Western Australia, WWI is exploring gold and copper at the
Mt Cecilia Project in a district that supports several world-class projects such as Woodie Woodie manganese
mine, Nifty copper and Telfer gold/copper/silver mines.
1.
2.
The original report was “Updates to DFS Provide Improved Results for WBP”, which was issued with the consent of
Competent Persons, Mr. Andrew Pooley. The report was released to the ASX on 26 July 2023 and can be found on the
Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that
materially effects the information included in the relevant market announcement and, in the case of Mineral Resources
or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed. The form and context in which the
Competent Person’s findings are presented have not been materially modified.
The original report was “WBP Global MRE Increases with New Prospecting Right”, which was issued with the consent of
the Competent Person, Mr Hermanus Berhardus Swart. The report was released to the ASX on 16 December 2024 and
can be found on the Company’s website (https://westwitsmining.com/). Comprising 10.7MT at 4.60g/t for 1.595Moz
measured, 12.29MT at 4.19g/t for 1.70Moz Indicated, and 10.49MT at 5.10g/t for 1.73Moz inferred. The Company is not
aware of any new information or data that materially effects the information included in the relevant market
announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially
changed. The form and context in which the Competent Person’s findings are presented have not been materially
modified from the original market announcement.
page i
WEST WITS MINING
SOUTH AFRICA | NEAR TERM GOLD PRODUCER
CAPE TOWN INDABA| February 2025
ASX:WWI
ASX:WWI
COPYRIGHT ©2025 ALL RIGHTS RESERVED
Qala Shallows, Witwatersrand Basin Project, Gauteng
Mining District, Johannesburg, South Africa
DISCLAIMER
FORWARD-LOOKING STATEMENTS
COMPETENT PERSON STATEMENTS
This presentation includes “forward-looking statements” as that term within the meaning of securities laws of
applicable jurisdictions. Forward-looking statements involve known and unknown risks, uncertainties and other
factors that are in some cases beyond West Wits Mining Limited’s control. These forward-looking statements
include, but are not limited to, all statements other than statements of historical facts contained in this
presentation, including, without limitation, those regarding West Wits Mining Limited’s future expectations.
Readers can identify forward-looking statements by terminology such as “aim,” “anticipate,” “assume,”
“believe,” “continue,” “could,” “estimate,” “expect,” “forecast,” “intend,” “may,” “plan,” “potential,”
“predict,” “project,” “risk,” “should,” “will” or “would” and other similar expressions. Risks, uncertainties and
other factors may cause West Wits Mining Limited’s actual results, performance, production or achievements
to differ materially from those expressed or implied by the forward-looking statements (and from past results,
performance or achievements).
The original report was “Updates to Qala Shallows DFS provide improved results for Witwatersrand Basin
Project” which was issued with consent of the Competent Person, Mr. Jim Pooley. The report was released to
the ASX in July 2023 and can be found on the Company’s website (https://westwitsmining.com/). The
Company is not aware of any new information or data that materially effects the information included in the
relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement
continue to apply and have not materially changed. The form and context in which the Competent Person’s
findings are presented have not been materially modified from the original market announcement.
These factors include, but are not limited to, the failure to complete and commission the mine facilities and
related infrastructure in the time frame and within estimated costs currently planned; variations in global
demand and price for gold fluctuations in exchange rates between the U.S. Dollar, South African Rand and
the Australian Dollar; the failure of West Wits Mining Limited’s suppliers, service providers and partners to fulfil
their obligations under construction, supply and other agreements; unforeseen geological, physical or
meteorological conditions, natural disasters or cyclones; changes in the regulatory environment, industrial
disputes, labour shortages, political and other factors; the inability to obtain additional financing, if required,
on commercially suitable terms; and global and regional economic conditions. Readers are cautioned not to
place undue reliance on forward-looking statements. The information concerning possible production in this
announcement is not intended to be a forecast. They are internally generated goals set by the board of
directors of West Wits Mining Limited. The ability of the Company to achieve any targets will be largely
determined by the Company’s ability to secure adequate funding, implement mining plans, resolve logistical
issues associated with mining and enter into any necessary off take arrangements with reputable third parties.
Although West Wits Mining Limited believes that its expectations reflected in these forward-looking statements
are reasonable, such statements involve risks and uncertainties and no assurance can be given that actual
results will be consistent with these forward-looking statements.
ASX:WWI
The original report was “WBP Global MRE Increases with New Prospecting Right” which was issued with consent
of the Competent Person, Mr Hermanus Berhardus Swart. The report was released to the ASX on 16 December
2024 and can be found on the Company’s website (https://westwitsmining.com/). Comprising 10.7MT at
4.60g/t for 1.595Moz measured, 12.29MT at 4.19g/t for 1.70Moz Indicated and 10.49MT at 5.10g/t for 1.73Moz
inferred. The Company is not aware of any new information or data that materially effects the information
included in the relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all
material assumptions and technical parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed. The form and context in which the
Competent Person’s findings are presented have not been materially modified from the original market
announcement.
PAGE | 2
Why invest in West Wits
Significant gold resource in the
Witwatersrand Basin Project (WBP)
South Africa
WBP – Mineral Resource Estimate
5Moz Gold
(65% measured & indicated categories)1
WBP - Project 200 - significant growth
opportunity aimed to produce
200 000oz Gold per annum
Qala Shallows (Stage 1) – Robust DFS
17yr Life-of-mine for 924,000oz
70,000oz p/a steady-state production
for 9 years2
Qala Shallows - DFS
Post Tax IRR 72% & NPV US$366M
@ US$2,200/oz gold price2
Qala Shallows – Turn-key ready: fully
licensed, site infrastructure maintained; key
supplier contracts secured
Qala Shallows – Cost-effective toll treat
agreement with Ezulwini Mining
Company/ Sibanye-Stillwater subsidiary
Funding – South African banking
syndicate in final credit approval
process for 50-60% of project funding
Experienced international board and
management team
ASX: WWI | OTBCQB: WMWWF
CORPORATE SNAPSHOT
Transforming into mid-tier gold producer
CAPITAL STRUCTURE (ASX:WWI)
Shares on issue
2.56B
Market Capitalisation
A$41M
Unlisted Options (exercise price range 2.2c – 25c)
Performance Rights
Convertible Notes
@ 1.6c per share (on 29/01/2025)
141.5M
7.5M
50*
Cash - 31/12/2024
A$1.0M
Enterprise Value per Ounce
A$7.96/oz
JORC Mineral Resource Estimate1 (Gold)
5Moz
includes declared Ore Reserves
Commodity Exposure
Gold, Uranium
* Convertible Notes (CN) with a A$25,000 Face Value, convertible to WWI shares at
the lower of 2c or a 20% discount to the 15-day VWAP until the notes expire on
16/10/26. The CN are interest free and unsecured.
ASX:WWI
PAGE | 4
STRONG MANAGEMENT TEAM OVERSEEN
& SUPPORTED BY INTERNATIONAL BOARD
MICHAEL QUINERT
Chairman (AUS)
ASX-experienced
commercial lawyer with
extensive involvement in
assisting and advising
publicly listed mining
companies.
SIMON WHYTE
CFO / Company
Secretary (AUS)
ASX:WWI
RUDI DEYSEL
CEO (SA)
Mining Eng. with
Geophysics and MBA.
Previously experience
includes Anglo
American and Galiano
Gold
Chartered
Accountant with
extensive experience
in mining,
commodities and
logistics which
includes global
majors, Ernst & Young
and BP
TOZAMA KULATI
SIWISA
Exec Dir/Head of
Corp Affairs (SA)
BCom with MBA with
extensive experience
in ESG management.
Previously head of
stakeholder relations
at Lonmin
MARTIN
BEVENLANDER
Head of Geology
& Exploration (SA)
HULME SCHOLES
Non-Exec Dir (SA)
JAC VAN HEERDEN
Non-Exec Dir (SA)
WARWICK GRIGOR
Non-Exec Dir (AUS)
One of SA’s top legal
professionals
specialising in mining and
mineral law, having
represented Tier 1 mining
companies, including
Sibanye Stillwater and
DRDGold
Mining Engineer with MBA,
operations, and project
experience in South
Africa, DRC and
Zimbabwe.
Experienced mining
analyst who founded Far
East Capital Limited, a
specialist mining
company financier and
corporate adviser. Was
founding Executive
Chairman of Canaccord
Genuity Australia
Geologist with
expertise that spans
across the entire
mining cycle. Worked
in Indonesia, Papua
New Guinea, Australia,
and across Africa
KEITH MIDDLETON
Exec Manager
Commercial
Experienced Executive of
ASX listed companies
specialising in the resources
sector, financial analysis,
risk management, major
capital works expenditure.
Former Managing Director
of American Rare Earths
PAGE | 5
WBP – LOCATION & GROWTH POTENTIAL
SANDTON CBD
5. BIRD REEF
CENTRAL (BRC)
Gold & Uranium
JOHANNESBURG CBD
▪
2022 Scoping Study identified Five (5) distinct development
stages for the Witwatersrand Basin Project with Stages 1 – 4 Gold
Projects for a 27yr Life of Mine.6
▪
Qala Shallows is Stage 1 of the WBP which has been subject to a
DFS with a 17yr Life of Mine.2
▪
Prospecting Right (PR) adjacent to Qala Shallows granted
(yellow) and new PR application (red) which provides significant
organic growth opportunity.
▪
Stage 5 (BRC) is a potential standalone Gold & Uranium project.
Image: Mining Right (blue); Prospecting Right Granted (yellow)& New PR Application (red)
ASX:WWI
PAGE | 6
WWI – GOLD RESOURCES
GLOBAL MINERAL RESOURCE ESTIMATE (JORC 2012)1
Category
Tonnage (Mt)
Grade (g/t)
Content (oz)
Measured
10.07
4.60
1 595 000
Indicated
12.29
4.19
1 700 000
Measured &
Indicated
23.00
4.45
3 295 000
Inferred
10.49
5.10
1 730 000
Total
33.49
4.66
5 025 000
▪
Significant global Mineral Resource Estimate of 5Moz
Gold @ 4.66 g/t Au1
▪
High degree of confidence level with 65% of MRE in
Measured & Indicated categories.
▪
3 distinct reef horizons: Kimberley Reef; Bird Reef;
Main Reef (right image)
▪
Well understood geology, mineralisation & metallurgy
ASX:WWI
PAGE | 7
WBP - MRE & ORE RESERVE GROWTH
6
WWI has progressively grown
the MRE under the 2012 JORC
Code to over 5Moz @
4.66g/t.1
The Company has grown
declared Ore Reserves to
351koz.2
5
GOLD OUNCES (MILLION)
WBP tenement area
previously held by DRD Gold
which had a Historical MRE
declared (2000 ASX Report) of
12.8Moz at 4.6g/t Gold under
the previous JORC Code3.
0,35
0,29
4
-
3
1,21
2
1
-
0,30
0,57
0,35
Jan-16
JAN-16
Maiden MRE 400M depth3
1,24
0,81
Dec-17
DEC-17
Upgrade: 400 1,500m on
Kimberley
Reefs11
Inferred
ASX:WWI
0,28
0,60
1,42
1,50
1,37
1,44
1,00
1,26
Jul-18
JUL-18
Addition to
of K9B
Reef10
1,38
1,31
1,30
1,31
Sept-21
SEP-21
DFS with
declared
maiden Ore
Reserve9
Indicated
Dec-21
DEC-21
Bird Reef &
Main Reef
Upgrade to
1,000m depth7
Measured
1,73
Dec-24
DEC-24
Boost with New
Prospecting Right
Granted1
Ore Reserves
PAGE | 8
QALA SHALLOWS GOLD PROJECT
The Qala Shallows Gold Project (South Africa) comprises a low-risk, shallow underground mine
utilising contract mining with ore treated at an existing operational plant
HIGH TECHNICAL STANDARD
▪
Historic mine works with existing shafts & well understood rock engineering
▪
Successful “Proof of Mining Method” extraction and stockpiled in 2022
OPERATIONAL READINESS FOR RAPID PRODUCTION
▪
Robust DFS: Released to ASX July 2023
▪
Fully permitted: Mining Right; power; environmental; social; water; explosives
▪
Surface and underground infrastructure: Developed with quick accessibility & rapid production
▪
Small footprint: Minimal rehabilitation liability
▪
Production rate-based contract: Enhancing productivity & efficiency
▪
Cost-effective offtake treatment agreement: With nearby processing plant
STRONG ESG CREDENTIALS
▪
Black Economic Empowerment (BEE) ownership of 33.4% - higher than mandated 26%
▪
Local Economic Development Programme & Social Labour Plan
▪
Procurement from local Sowetan community
EXCEPTIONAL ECONOMICS DFS2
▪
924koz gold produced over 17yr LOM
▪
First gold produced in <12 months with steady state production of 70,000oz p/a (9 years)
▪
First quartile cost producer with AISC $977/oz (LoM) & US$871/oz (steady state)
▪
Payback period of 1.1yrs from completion of construction
ASX:WWI
PAGE | 9
QALA SHALLOWS - MINING INVENTORY & ORE RESERVE2
RUN OF MINE INVENTORY
▪
>1Moz Gold at 3.04g/t, inclusive of Ore Reserves
▪
Ore Reserves - 4Mt at 2.71g/t for 351,400 oz gold,
comprises 35% of the mining inventory
▪
During the first 6 years of production, reserves
comprise >75% of mining inventory
▪
An underground drilling program will be
implemented to convert resources to reserves as
decline development progresses to maintain a
minimum level of reserves
▪
Mineral Resource Estimate Cut-off at 2g/t is
calculated using a gold price of US$1,500/oz and
ZAR 15.00/1 US$
▪
Significant upside to Mine Inventory at current gold
price (approx. US$ 2,700/oz) and Exchange rate
(approx. ZAR 17.50/1 US$)
ASX:WWI
RUN OF MINE INVENTORY (INCLUSIVE OF ORE RESERVES) 2
Mineral Resource
Estimate Category
Tonnage
(Mt)
Grade
(g/t)
Content
(kg)
Content
(oz)
Measured
1.01
2.93
2 949
95 000
Indicated
3.49
2.62
9 135
294 000
Inferred
5.78
3.32
19 156
616 000
Grand Total
10.28
3.04
31 240
1 004 000
PAGE | 10
QALA SHALLOWS MINING PLAN
Trackless development with conventional stoping
– tried and tested
▪
Ore body is accessed from surface via a decline system developed
from the existing Qala adit box cut
▪
The decline is located centrally in the mining area and the K9B
footwall
▪
Stopes will be accessed via strike drives developed on the K9B reef
horizon
▪
Development of the strike drives and decline will be by mechanised
method with drill rigs, LHDs and ADTs deployed for drilling, face
cleaning and hauling of blasted rock to the tips respectively
▪
Mining in the stope blocks will be using standard conventional
mining techniques widely used in region with the deployment of
handheld drills and cleaning using a scraper and winch
combination
▪
Most of the mining will take place in a large unmined block of
ground to the east of the property
▪
Stoping will commence from 35m below surface to a maximum
depth of 850m
▪
A small amount of waste rock will be stockpiled on site
▪
Once on surface, ore will be trucked approximately 40km to an
existing processing plant under a Toll Processing agreement with
Sibanye Stillwater.
ASX:WWI
Stage 3
Stage 2
Stage 1 - DFS
Stage 4
PAGE | 11
QALA SHALLOWS PERMANENT SURFACE LAYOUT2
▪ Critical infrastructure
completed
▪ Contract terms finalised with
key suppliers
▪ Mining Right &
Environmental Authorisation
granted
MINE EXTENSION
Scoping Study
Stage
2 – Main Reef
▪ 7.5MVA power
allocation
Stage 3 – Bird Reef East
received withStage
primary
4 – Qala power
Deeps
substation completed with
backup diesel generators
▪ Water Use License granted &
established water supply
infrastructure installed
▪ Explosives License granted
ASX:WWI
PAGE | 12
QALA SHALLOWS PRODUCTION SCHEDULE
MINING SCHEDULE & GRADE
DFS completed in July 2023 by Bara Consulting2
▪
DFS completed on first stage of development to
deliver 924,000oz gold at AISC of US$977/oz
▪
From the project start date, there is a 6 - 8 week
period to mobilise contractors and purchase initial
equipment
▪
Initial production will provide a robust 30,000 tonne
ore stockpile to facilitate delivery of 15,000 tonnes per
month to Sibanye-Stillwater’s plant which ramps up to
steady state of around 60,000 tonnes per month
▪
Targeting achievement of the stockpile & delivery
within 6 to 8 months from start of production
▪
Gradual mine build-up towards a steady-state
production of 5,700 ounces of gold per month at an
AISC of US$871/oz
ASX:WWI
GOLD PRODUCTION
PAGE | 13
QALA SHALLOWS DFS FINANCIAL MODEL & FUNDING
KEY FINANCIAL METRICS – DFS Base Case US$1,850/oz
DFS - Financial Evaluation2
DEFINITIVE FEASIBILITY STUDY2
GOLD PRICE
US$1,850/oz
GOLD PRICE
US$2,200/oz
▪
Post-Tax Free Cashflow of US$522m over Life-of-Mine
Peak Funding
US$54m
US$43m
▪
AISC cost in lowest quartile at US$977/oz (LoM)
Payback Period
(from commencement)
4.1 years
3.6 years
▪
Post-Tax - NPV7.5 US$255m and IRR 53%
Pre-Tax NPV (7.5%)
US$367m
$531m
(A$583m)
(A$843M)
US$255m
$366m
(A$405m)
(A$581M)
53%
72%
PEAK FUNDING REQUIREMENT
▪
US$54m (DFS) with 13 months payback from completion of construction
▪
Peak funding substantially reduced at prevailing Gold Price due to higher revenues
from production during the 3-year mine development phase
▪
At a Gold Price (US$2,200/oz), peak funding reduces to US$43M
PROJECT FUNDING INITIATIVES
▪
▪
Due Diligence completed, SA commercial bank has obtained credit approval and
a South African Development Finance Institution (DFI) is in the final credit approval
process and to participate in a syndicated senior debt loan to fund 50 - 60% of
development funding requirements
Having a substantial portion of the funding requirement provided for by a
syndicated bank debt facility would provide a strong platform for finalising
arrangements for the required balance. The Company continues to engage and
negotiate with several other potential sources to complete all required funding for
the project
ASX:WWI
Post-Tax NPV (7.5%)
Post-Tax Internal Rate of Return
DFS - Financial Evaluation2
GOLD PRICE US$1,850/oz
Total Revenue
US$1.7b
Total Free Cashflow
US$522m
LOM C1 Cost
US$818/oz
AISC – Life of Mine
US$977/oz
AISC – Steady State
US$871/oz
Pre-Tax Internal Rate of Return
61%
* USD converted to AUD at 1.5873 PAGE | 14
TARGETING FIRST GOLD POUR Q4 2025
2024
2025E
H1
H2
2026E
H1
2027E
2027E
H2
H1
H2
H1
LVL 2
LVL 3
LVL 4
LVL 5
H2
2028E
H1
H2
Due Diligence completed on Sr Debt Facility
Project Finance package with 50% - 60% Sr Debt
Mobilise mining contractors & execute first blast
Build 30,000t stockpile & start deliveries to Sibanye
First gold pour
EPCM contract works – major surface infrastructure
UG level access via decline development
LVL 1
Ongoing UG sampling to grow Ore Reserves
Ramp up gold production to 70,000oz pa Steady-State2
ASX:WWI
PAGE | 15
KEY MILESTONES DRIVING VALUE
2021
Milestones
Catalysts
✓ Mining Right granted with 3.5Moz gold MRE8
❖ Complete Project Finance package
✓ Stage 1 DFS confirms 278koz Ore Reserve & AISC US$1,144/oz1
❖ Commission UG mine development
✓ MRE increased to 4.3Moz Gold7
❖ First ore production via completed early works development
✓ Revised Scoping Study on Stages 1 – 46
❖ Deliveries to Sibanye plant & First Gold Pour
✓ Early Works - surface infrastructure & UG access established
❖ Steady production ramp up via decline development
✓ Toll Processing Agreement secured with Sibanye Stillwater
✓ Updated DFS boosts Ore Reserves to 351koz & AISC US$977/oz2
✓ Contracts negotiated with key suppliers
✓ Project finance due diligence successfully completed
✓ MRE increased to 5Moz Gold1
✓ Credit Approval received from 1 out of 2 senior lenders
2024
ASX:WWI
PAGE | 16
WBP BIRD REEF CENTRAL: URANIUM & GOLD OPPORTUNITY
Presence of uranium mineralisation within the Bird Reef sequence provides
significant opportunity for the BRC to become a joint gold and uranium
operation.
URANIUM EXPLORATION TARGET4
BRC Uranium Project has the potential to become a standalone mine with
separate infrastructure accessed through the existing Circular Shaft site.
Range
Low
High
Tonnes (M)
10
22
Declared JORC Gold Mineral Resource: 1.38Mt Ore at 2.66g/t for 118,000oz3
Grade (ppm) U3O8
300
550
URANIUM EXPLORATION PROGRAM
Content (Mlb) U3O8
12
16
▪
Phase 1 2008 Exploration results4 confirmed consistent uranium
mineralisation over approx. 3.3km with more than 7km of strike identified
along the targeted Bird Reef section within the WBP’s mining right area
▪
BRC Uranium Exploration Program outlined and aimed at converting the
significant Uranium Exploration Target to a JORC compliant Mineral
Resource Estimate (MRE) within the Bird Reef Sequence of the WBP
▪
Uranium Exploration Target is confined to the western margin of the WBP’s
mining right area and remains open for the approx. 3.75km strike length
extension to the east
▪
2022 Diamond Drilling results5 highlighted by:
o Middle Reef (PH1B) - 1.59m depth @ 835ppm U & 1.46g/t Au (85.11m),
including 0.96m @ 1,321ppm U & 2.30g/t Au from 85.74m)
o White Reef (PH1B) - 1.20m depth @ 108ppm U & 5.45g/t Au (104.61m)
Notes: The potential quantity and grade are conceptual in nature. There has
been insufficient exploration and evaluation of historical information to
estimate a Mineral Resource. It is uncertain if further exploration will result in the
estimation of a Mineral Resource.
URANIUM EXPLORATION PROGRAM TIMELINE
Phase 1 – 2008
Completed
30 drillholes
6,688m3
Initial Exploration Program to
confirm uranium mineralisation
Phase 2 – 2022
Completed
3 drillholes
291m5
Execution of Phase 2
exploration drilling (BRC Project)
Phase 3
Planned
10 drillholes
2,640m
Convert Exploration Target to
JORC MRE
Phase 4
Planned
2 drillholes
1,600m
Target depth extension of MRE
o Middle Reef (PH1C) - 1.26m depth @ 221ppm U & 0.38g/t Au (77m)
ASX:WWI
PAGE | 17
WBP ENVIRONMENTAL, SOCIAL & GOVERNANCE (ESG)
ENVIRONMENTAL STEWARDSHIP & BIODIVERSITY CONSERVATION
▪
Complete underground operation: low noise and dust levels
▪
Small footprint & surface infrastructure: low rehabilitation liability &
minimal impact on surrounding environment
▪
Efficient water use model: Minimal water usage & zero effluent
discharge into local tributaries
SOCIAL POSITIVE IMPACT OF HOST COMMUNITIES
▪
Local Economic Development Programme: Community wards forum in
collaboration with City of Joburg
▪
Local procurement: Sourced from growing BEE database
▪
Social & Labour Plan: Includes Beneficiary Learnership Programme
GOVERNANCE RESPONSIBLE PRODUCTION PRACTICES
▪
Corporate Governance Framework: Complies with changing legal
& regulatory requirements
▪
Company Mine Health & Safety: Conforms to Mine Health & Safety Act
29 of 1996
▪
Health & Safety: Zero harm approach
▪
Stakeholder Engagement: Transparent reporting
ASX:WWI
PAGE | 18
Qala Shallows Box Cut
CHIEF EXECUTIVE OFFICER
INVESTOR RELATIONS
SOUTH AFRICA
AUSTRALIA
Rudi Deysel
Keith Middleton
rdeysel@westwitsmining.com
keith@middletoncorporate.com.au
Unit 8A, Sifon Industrial Park
279 Sifon Street, Robertville
Roodepoort
1709
Level 6, 400 Collins Street
Melbourne, Victoria
Australia
3000
westwitsmining.com | info@westwitsmining.com
COPYRIGHT ©2023 ALL RIGHTS RESERVED
ASX:WWI
PAGE | 19
Appendix 1: Ore Reserve & Mineral Resource Estimate Statements
Table 1: WBP (JORC) Ore Reserve2
Declared ore reserve of 4.03MT at 2.71g/t for 351,424oz Gold2
Ore Reserve Notes:
1. No Inferred Mineral Resources are included in the Ore Reserves.
2. The evaluation used a gold price US$1,850 per ounce and a rate of exchange of R17.5 / US$ 1.
ORE RESERVE STATEMENT FOR QALA SHALLOWS (JORC 2012)
ORE Reserve
Category
Tonnage
(Mt)
Grade
(g/t)
Content
(kg)
WBP’s Global Mineral Resource is made up of several gold bearing reefs across the mining right
area, a breakdown by reef and MRE category is detailed in Table 21.
Content
(oz)
Proved
0.96
2.96
2 847
91 536
Probable
3.07
2.64
8 083
259 887
Total
4.03
2.71
10 930
351 424
MRE Notes:
1. Global MRE set at a 2.0g/t Au cut-off. Reported in accordance with the JORC Code of 2012.
2. Number differences may occur due to rounding errors.
3. Mineral Resources are reported as inclusive of Ore Reserves.
4. The Inferred Mineral Resources have a high degree of uncertainty, and it should not be assumed that
all or a portion thereof will be converted to Ore Reserves.
REFER TO SLIDE 9 FOR QALA SHALLOWS MINE INVENORY TABLE – 1Moz
Note: errors may occur due to rounding differences
Table 2: WBP (JORC) Mineral Resource Estimate – by Reef (2g/t cut-off)1
Measured
Indicated
Inferred
Total
Reef
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Bird – Central & West
0.04
3.73
0.00
0.89
2.51
0.07
0.44
2.86
0.04
1.38
2.66
0.12
Bird – East
2.22
4.30
0.31
2.00
4.74
0.30
0.42
4.48
0.06
4.63
4.51
0.67
K9B KRC
0.00
2.98
0.00
0.10
3.87
0.01
0.18
4.22
0.02
0.28
4.08
0.04
K9B KRE
1.93
4.37
0.27
6.21
4.14
0.83
2.35
5.51
0.42
10.50
4.49
1.52
K9A KRE
2.10
4.54
0.31
1.82
4.20
0.25
4.20
5.14
0.69
8.11
4.77
1.25
K9B KRE (PR 10730)
0.31
5.18
0.05
0.54
5.92
0.10
1.46
5.18
0.24
2.31
5.35
0.40
K9A KRE (PR 10730)
0.59
4.95
0.09
0.50
5.01
0.08
1.05
5.27
0.18
2.14
5.12
0.35
Main Reef Leader
0.72
5.81
0.14
0.15
8.34
0.04
0.09
7.54
0.02
0.96
6.36
0.20
Main
2.79
4.73
0.42
0.09
5.15
0.01
0.31
5.27
0.05
3.19
4.79
0.49
Total
ASX:
WWI | OTBCQB: WMWWF10.70
4.60
1.59
12.29
4.19
1.70
10.49
5.10
1.73
33.49
4.66
5.03
Note: errors may occur due to rounding differences
APPENDIX 2 - REFERENCES
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
The original report was “WBP Global MRE Increases with New Prospecting Right” which was issued with consent of the Competent Person, Mr Hermanus Berhardus Swart. The report was released to the ASX on 16 December
2024 and can be found on the Company’s website (https://westwitsmining.com/). Comprising 10.7MT at 4.60g/t for 1.595Moz measured, 12.29MT at 4.19g/t for 1.70Moz Indicated and 10.49MT at 5.10g/t for 1.73Moz inferred.
The Company is not aware of any new information or data that materially effects the information included in the relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The form and context in which the Competent Person’s
findings are presented have not been materially modified from the original market announcement.
The original report was “Updates to Qala Shallows DFS provide improved results for Witwatersrand Basin Project” which was issued with consent of the Competent Person, Mr. Andrew Pooley. The report was released to the
ASX on 27 July 2023 and can be found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the information included in the relevant
market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply
and have not materially changed. The form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
The original report was “Updated Mineral Resource Estimate for the Soweto Cluster” which was issued with consent of competent persons Mr. Herma