Investor Presentation - RIU Explorers Conference
Released
Released
Announcement PDF
page i
ASX Announcement and Media Release
Tuesday, 17 February 2026
West Wits Mining Presentation
RIU Explorers Conference, Fremantle WA 2026
West Wits Mining Limited (ASX: WWI) advises that Board representatives will be attending the RIU
Explorers Conference in Fremantle, WA from 17 - 19 February 2026.
Chairman, Mr Michael Quinert, will be presenting at the RIU Explorers Conference, where he and Board
members will meet with investors and stakeholders to discuss the Company’s strategy and progress.
A copy of the Investor Presentation is attached to this announcement.
Approved for release by the Company Secretary, Simon Whyte
For further information, contact our Investor Relations:
Jessica Fertig
ir@westwitsmining.com
General
info@westwitsmining.com
westwitsmining.com
linkedin.com/company/west-wits-mining
ABOUT WEST WITS MINING LIMITED
West Wits Mining Limited (ASX: WWI) (OTCQB: WMWWF) is focused on the exploration, development and
production of high-value precious and base metals for the benefit of shareholders, communities and
environments in which it operates. Witwatersrand Basin Project, located in the proven gold region of Central
Rand Goldfield of South Africa, boasts a 7.24Moz gold project at 4.00g/t1
. The Witwatersrand Basin is a largely
underground geological formation which surfaces in the Witwatersrand. It holds the world's largest known gold
reserves and has produced over 1.5 billion ounces (over 40,000 metric tons), representing about 22% of all the
gold accounted for above the surface. In Western Australia, WWI is exploring gold and copper at the Mt Cecilia
Project in a district that supports several world-class projects such as Woodie Woodie manganese mine, Nifty
copper and Telfer gold/copper/silver mines.
1. The original report was “2.2Moz Increase to WBP Global Resource Estimate to 7.24Moz” which was issued
with consent of the Competent Person, Mr Hermanus Berhardus Swart. The report was released to the
ASX on 02 February 2026 and can be found on the Company’s website (https://westwitsmining.com/).
Comprising 14.08MT at 4.40g/t for 1.99Moz Measured, 15.55MT at 4.04g/t for 2.02Moz Indicated and
26.81MT at 3.75g/t for 3.23Moz Inferred. The Company is not aware of any new information or data that
materially effects the information included in the relevant market announcement and, in the case of
Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning
the estimates in the relevant market announcement continue to apply and have not materially changed.
The form and context in which the Competent Person’s findings are presented have not been materially
modified from the original market announcement.
Qala Shallows, Witwatersrand Basin Project, Gauteng
Mining District, Johannesburg, South Africa
COPYRIGHT ©2026 ALL RIGHTS RESERVED
RIU Explorers Conference
February 2026
ASX:WWI
Unlocking Long-Life
Gold Production in the
Witwatersrand Basin
Building the next
South African Gold Producer
PAGE | 2
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Forward-looking Statements
This presentation includes “forward-looking statements” as that term within the meaning of securities laws of
applicable jurisdictions. Forward-looking statements involve known and unknown risks, uncertainties and other
factors that are in some cases beyond West Wits Mining Limited’s control. These forward-looking statements
include, but are not limited to, all statements other than statements of historical facts contained in this
presentation, including, without limitation, those regarding West Wits Mining Limited’s future expectations.
Readers can identify forward-looking statements by terminology such as “aim,” “anticipate,” “assume,”
“believe,” “continue,” “could,” “estimate,” “expect,” “forecast,” “intend,” “may,” “plan,” “potential,”
“predict,” “project,” “risk,” “should,” “will” or “would” and other similar expressions. Risks, uncertainties and
other factors may cause West Wits Mining Limited’s actual results, performance, production or achievements to
differ materially from those expressed or implied by the forward-looking statements (and from past results,
performance or achievements).
These factors include, but are not limited to, the failure to complete and commission the mine facilities and
related infrastructure in the time frame and within estimated costs currently planned; variations in global
demand and price for gold fluctuations in exchange rates between the U.S. Dollar, South African Rand and the
Australian Dollar; the failure of West Wits Mining Limited’s suppliers, service providers and partners to fulfil their
obligations under construction, supply and other agreements; unforeseen geological, physical or
meteorological conditions, natural disasters or cyclones; changes in the regulatory environment, industrial
disputes, labour shortages, political and other factors; the inability to obtain additional financing, if required, on
commercially suitable terms; and global and regional economic conditions. Readers are cautioned not to
place undue reliance on forward-looking statements. The information concerning possible production in this
announcement is not intended to be a forecast. They are internally generated goals set by the board of
directors of West Wits Mining Limited. The ability of the Company to achieve any targets will be largely
determined by the Company’s ability to secure adequate funding, implement mining plans, resolve logistical
issues associated with mining and enter into any necessary off take arrangements with reputable third parties.
Although West Wits Mining Limited believes that its expectations reflected in these forward-looking statements
are reasonable, such statements involve risks and uncertainties and no assurance can be given that actual
results will be consistent with these forward-looking statements.
The production target and financial forecasting reported under the Qala Shallows Definitive Feasibility Study
(DFS) contain inferred mineral resources. The directors confirm that it is reasonable to include these inferred
mineral resources having regard to the location and geology of the project in the well understood and
researched structure of the Witwatersrand Basin and the views provided to WWI by independent geological
expert consultants.
Competent Person Statements
The original report was “Updates to DFS provide Improved Results for WBP” which was issued with consent of the
Competent Person, Mr. Jim Pooley. The report was released to the ASX in July 2025 and can be found on the
Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data
that materially effects the information included in the relevant market announcement and, in the case of
Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the
estimates in the relevant market announcement continue to apply and have not materially changed. The form
and context in which the Competent Person’s findings are presented have not been materially modified from
the original market announcement.
The original report was “WBP Global MRE Increases with New Prospecting Right” which was issued with consent
of the Competent Person, Mr Hermanus Berhardus Swart. The latest report was released to the ASX on 2
February 2026 and can be found on the Company’s website (https://westwitsmining.com/). Comprising
14.08MT at 4.40g/t for 1.99Moz Measured, 15.55MT at 4.04g/t for 2.02Moz Indicated and 26.81MT at 3.75g/t for
3.23Moz Inferred. The Company is not aware of any new information or data that materially effects the
information included in the relevant market announcement and, in the case of Mineral Resources or Ore
Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed. The form and context in which
the Competent Person’s findings are presented have not been materially modified from the original market
announcement.
Disclaimer
PAGE | 3
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Why invest in West Wits
Witwatersrand Basin Project (WBP) − South Africa
Investment Highlights: Why West Wits
Near-Term Gold Production: Qala Shallows in underground development, first ore
delivered (Oct 2025) and first gold targeted for March 2026
Fully Funded: A$51M Cash Balance & Executed Senior Debt Facilities fully
funding the project to steady-state production
Tier-One Asset Base: South Africa’s first new underground gold mine in 15
years and Stage 1 of the scalable Witwatersrand Basin Project
Resource Growth Upside: New Prospecting Right granted and an increase
in MRE base to 7.24Moz @ 4.00g/t Au11
Institutional Support & Optionality: Placement anchored by Tribeca (A$10m),
providing capital flexibility for growth, exploration and uranium upside (BRC)
Experienced Leadership & ESG Alignment: Strong management, community
partnerships and sustainability-driven programs
PAGE | 4
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Company Snapshot
Metric Detail
Primary Project Witwatersrand Basin Project (WBP), Gauteng, South Africa
Ownership 74% West Wits MLI (Pty) Ltd (26% BEE Partner)
Resource Base 7.24 Moz @ 4.0g/t11
Mine Type Underground gold mine
Processing Toll treatment agreement with Sibanye-Stillwater’s Ezulwini Plant
First Gold Production On track (Q1 March 2026); funding secured
Secondary Assets Mt Cecelia in the Paterson Province, Western Australia
PAGE | 5
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Corporate Snapshot
Transforming into mid-tier gold producer
Capital Structure (ASX:WWI)
Shares on issue
Listed Options (exercise price 3.85c, expiring 05/09/2027)
Unlisted Options (exercise price 11c, expiring 27/01/2029)
Various Unlisted Options (exercise price range 2.2c – 25c)*
Performance Rights
4.32B
320M
221M
338M
5M
Market Capitalisation
@ 8.5c per share (on 04/02/2026)
A$367M
Cash – 02/02/2026 A$50.7 M
Enterprise Value per MRE Ounce A$43.7/oz
JORC Mineral Resource Estimate1 (Gold)
includes declared Ore Reserves
7.24Moz @ 4.0g/t
0m
10m
20m
30m
40m
50m
60m
70m
80m
90m
100m
$0.00
$0.01
$0.02
$0.03
$0.04
$0.05
$0.06
$0.07
$0.08
$0.09
$0.10
Feb 25 Mar 25 Apr 25 May 25 Jun 25 Jul 25 Aug 25 Sep 25 Oct 25 Nov 25 Dec 25 Jan 26 Feb 26
Volume (RHS) Close (LHS)
PAGE | 6
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Board & Executive Team
Experienced analyst who founded Far
East Capital Limited, a specialist
company financier and corporate
adviser in the mining sector. Was the
founding Executive Chairman of
Canaccord Genuity Australia
Mining Engineer with MBA, operations
and project experience in SA, DRC and
Zimbabwe. Surface and underground
mine management expertise in base
and precious metals. Strong
background in mine technical services
and executive management
ASX-experienced commercial lawyer with extensive
involvement in assisting and advising publicly listed
mining companies globally. Non-Executive Director of
ASX-listed companies and serves on the boards of
several unlisted companies
Michael Quinert
Chairman (AUS)
Jac van Heerden
Non-Exec Dir
(SA)
Warwick Grigor
Non-Exec Dir
(AUS)
Simon Whyte
CFO / Company Secretary (AUS)
Chartered Accountant and Associate Member of the
Governance Institute of Australia with experience in
mining, commodities and logistics, including global majors,
Ernst & Young and BP Australia. Expertise in managing
business transformation and integration projects
Rudi Deysel
CEO (SA) / MD
Mining Eng. with Geophysics and MBA. Production
experience in conventional narrow tabular
underground, open-cast mining and various
commodities including Gold, PGMs, Copper and
Cobalt. Previous experience includes Anglo American
and Galiano Gold
Tozama Kulati
Siwisa
Exec Dir/Head of
Corp Affairs (SA)
BCom with an MBA with extensive
experience in ESG management and
leading transformation projects from
development to execution. Previously
head of stakeholder relations at
Lonmin. 2025 AAMEG Rising Star Award
winner
Keith Middleton
Non-Exec Dir
(AUS)
Company director with significant
experience in capital markets, strategy
and mining operations in Australia, North
America and South Africa. Previously
founding MD of American Rare Earths
and NED in ASX listed resource
companies Redbank Copper and
Advance Metals
PAGE | 7
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
The Witwatersrand Basin Opportunity
South Africa’s Witwatersrand Basin − responsible for ~22% of global historic gold production
▪ Located in one of
the world’s richest
and most productive
gold regions
▪ Historic output: >1.5
billion ounces
(40,000 tonnes)
▪ Established mining
jurisdiction with
modern
infrastructure and
skilled labour
▪ West Wits controls a
strategic position in
the Central Rand
Goldfield, adjacent
operating mines
PAGE | 8
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Funding Secured for Growth
Fully funded to steady-state gold production
▪ AUD50.7M Cash Balance at 02/02/2026 (including $10M Tribecca cornerstone
investment, providing institutional validation)
▪ USD12.5M Nebari Loan Facility (part of a scalable US$35M package)
▪ Executed Senior Debt syndicated loan facility of up to ZAR875 million (~USD50
million) with two leading South African financial institutions
▪ 2Moz increase to Global MRE to 7.24Moz in February
West Wits now has complete funding pathway to achieve sustainable gold
production and operational ramp-up
2025 2026
2026/
2027
From
2028
Jul Aug Sep Oct Jan Feb Mar
Updated Qala Shallows DFS - US$500M Post-Tax NPV7.5 ; 384koz Reserves & AISC US$1289/oz2
✓
Project Finance package secured ✓
Qala Shallows site Mobilisation complete ✓
First ore production via completed early works development ✓
2.2Moz Gold Increase to Global JORC MRE to 7.4Moz @ 4.0g/t11
✓
First Gold Pour from Sibanye’s Ezulwini Plant ●
Production ramp up via decline development ●
Steady-state production: 70,000/oz pa for 12 years2
●
PAGE | 9
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Fully mobilised
Qala Shallows: The Foundation for Growth
Ore production commenced from underground
workings
Commissioned site infrastructure: power,
ventilation, water, LHDs and drill rigs operational
Building 30,000t ore stockpile to commence
processing at Ezulwini Plant from Mar-26
Designed for long-life, low-cost gold production
with scalability
PAGE | 10
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Gold Production
Qala Shallows − Strong Project Economics
Updated DFS completed in July 2025 by
Bara Consulting2
Base Case Financials (at US$2,850/oz):
▪ Revenue: US$2.7 billion
▪ Free Cash Flow: US$983 million
▪ NPV (Post-Tax, 7.5%): US$500 million
▪ IRR (Post-Tax): 81%
▪ Payback: 8 months from end of funding
period
▪ LOM: 17 years
▪ Robust at all gold prices:
Even at US$1,850/oz, the project delivers
a 35% IRR, demonstrating strong
resilience.
Note: the DFS and any production target under the DFS contain inferred
mineral resources. The directors confirm that it is reasonable to include these
inferred mineral resources in the well-understood and researched structure
of the Witwatersrand Basin and the views provided to WWI by independent
geological expert consultants, given the project’s location and geology.
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
0
200
400
600
800
1,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Recovered
Gold
(OZ)
Ore
Tonnes
'000s
Project Year
ORE Tonnes − 2025 Update Recovered Gold
Mining Schedule & Grade
-
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
-
200
400
600
800
1,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
ROM
Grade
(g/t)
Ore/Waste
Tonnes
(KT)
Project Year
Ore Tonnes Waste Tonnes ROM Grade
PAGE | 11
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Qala Shallows − Mining Inventory and Ore Reserve2
Run of mine inventory
▪ 1.03Moz Gold at 3.0g/t, inclusive of Ore
Reserves
▪ Ore Reserves – 4.6Mt at 2.60g/t for
384,000 oz gold, (37% of the mining
inventory)
▪ First 7 years of production: Reserves
comprise >75% of mining inventory
▪ Ongoing underground drilling to
convert Resources to Reserves as
decline development progresses
▪ Mine Plan cut-off grade at 1.31g/t is
calculated using a gold price of
US$2,850/oz and ZAR18.00/1 US$
Note: the DFS and any production target under the DFS contain inferred
mineral resources. The directors confirm that it is reasonable to include these
inferred mineral resources in the well-understood and researched structure
of the Witwatersrand Basin and the views provided to WWI by independent
geological expert consultants, given the project’s location and geology.
Run of Mine Inventory (Inclusive Of Ore Reserves) 2
Mineral Resource
Estimate Category
Tonnage
(Mt)
Grade
(g/t)
Content
(kg)
Content
(oz)
Measured 1.4 2.78 3 167 102 000
Indicated 3.7 2.54 9 487 305 000
Inferred 5.8 3.30 19 268 619 000
Grand Total 10.7 2.98 31 922 1 026 000
Mining schedule by Ore Reserve/Mineral Resource category
-
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
RoM
Ounces
'000s
Year
Measured and indicated Inferred Proven and probable
PAGE | 12
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
WWI − Gold Resources11
WBP – Global JORC Mineral Resource Estimate as of 01 February 2026
Category Tonnes (M) Grade (g/t AU) Ounces
Measured 15.61 4.40 1 991 000
Indicated 26.81 4.03 2 020 000
Measured & Indicated 42.42 4.21 4 012 000
Inferred 56.51 3.75 3 232 000
Total 56.51 4.00 7 240 000
▪ Global JORC MRE to 7.24Moz @ 4.0g/t Au.
▪ 4Moz Au (55%) classified as Measured & Indicated, providing high
degree of confidence for mine development
▪ High-grade profile with average grade of 4.0g/t Au.
▪ Feb-26 MRE Update included:
➢ New Prospecting Right adds 1.2Moz @ 4.38g/t Au, providing
a natural depth extension to the Qala Shallows gold mine.
➢ Lower cut-off grade using USD 2,850/oz gold price, unlocks
an additional 1Moz Au, supported by current gold prices
▪ 3 distinct reef horizons: Kimberley Reef; Bird Reef; Main Reef (right
image)
Expansion Potential: Proven Mineralisation and Metallurgy
PAGE | 13
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
0.35
0.81
1.26 1.30 1.31
1.73 1.73
3.32
0.57
1.24
1.00
1.38 1.31
1.44 1.42
2.02
0.30
1.21
1.42 0.60
1.37
1.51 1.49
1.99
0.28
0.29
0.35 0.38
0.38
0
1
2
3
4
5
6
7
8
9
Jan-16 Dec-17 Jul-18 Sep-21 Dec-21 Dec-24 Jul-25 Jan-26
▪ WBP tenement area
previously held by
DRD Gold which
had a Historical MRE
declared (2000 ASX
Report) of 12.8Moz
at 4.6g/t Gold under
the previous JORC
Code3.
▪ WWI has
progressively grown
the MRE under the
2012 JORC Code to
over 7.24Moz @
4.22g/t.11
▪ The Company has
grown declared Ore
Reserves to 384koz.2
Inferred Indicated Measured Ore Reserves
WBP − MRE and Ore Reserve Growth
Gold Ounces (Million)
Addition to of
K9B Reef8
DFS with
declared
maiden Ore
Reserve7
Bird Reef &
Main Reef
Upgrade to
1,000m
depth5
Boost
with New
Prospecting
Right
Granted1
Maiden MRE -
400M depth3
Upgrade: 400
-1,500m on
Kimberley
Reefs9
DFS updated
with
US$2,850/oz
gold price &
ZAR18:$1 FX
rate2
MRE
increases to
7.24Moz @
4.0g/t Au11
PAGE | 14
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
WBP − Location and Growth Potential
2022 Scoping Study: 4 Development stages;
Stages 1 – 4 Gold Projects (27-year LoM)4
Stage 1 (Qala Shallows): DFS complete (17-
year LoM)2
Recently granted PR 10839 adds 1.2Moz @
4.38g/t Au11
, providing a natural depth
extension to the Qala Shallows gold mine.
Stage 5 (BRC): potential standalone Gold &
Uranium project
Image: Mining Right – MR10073 (orange); Prospecting Right – PR10730 (red) & Prospecting Right -
PR 10839 (Yellow)
Project 200 planning underway which aims to
increase production capacity of the WBP to
aspirational rate of 200,000oz per annum
PAGE | 15
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Emerging Witwatersrand Basin Uranium-Gold Opportunity
Bird Reef Central (BRC) Project
Funded exploration program enabled by
recent institutional capital raise, targeting a
declared Uranium Mineral Resource Estimate
BRC demonstrates potential as standalone
uranium–gold projects within the
Witwatersrand Basin
Dual-commodity exposure: uranium upside
with meaningful gold credits
Located within West Wits’ Witwatersrand
Basin Project, leveraging existing geological
knowledge, infrastructure & Mining Right
Image: Plan View of the Bird Reef Central and West Exploration Area, within the WBP’s Mining Right
Boundary
PAGE | 16
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Project 200 – Defining a Pathway to ~200koz p.a.
Transforming WBP into a scalable , Long-Life Gold Platform
Scoping Study Underway
▪ Independent Scoping Study commenced to assess expansion to ~200,000oz p.a.
▪ Bara Consulting appointed (building on Phase 1 trade-off analysis)
▪ Completion targeted June 2026
Foundation For Scale
▪ 7.24Moz JORC Mineral Resource11
supports staged, long-life growth
▪ Multiple targets across Mining Right + 2 Prospecting Rights
Dual-track Growth Strategy
▪ First gold at Qala Shallows on-track for March 2026
▪ Project 200 targets a step-change toward mid-tier scale production
Balance Sheet Support
▪ Recent institutional placement strengthens funding capacity for:
▪ Production ramp-up
▪ Expansion study advancement
Image: CEO and MD, Rudi Deysel onsite
PAGE | 17
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Growth Program
Unlocking Resource Potential
Q1'26 Q2'26 Q3'26 Q4'26 Q1'27 Q2'27 Q3'27 Q4'27 Q1'28 Q2'28 Q3'28
Project 200
Shallow Targets
• Scoping Study
• Data Collection
• Feasibility Study
Deep Targets
• Scoping Study
• Data Collection
• Feasibility Studies
Central Bird Reef
• Drilling Programme
• Data Collection
• Scoping Study
• Feasibility Study
PAGE | 18
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Qala Shallows Operational Build-Out
PAGE | 19
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
WBP Environmental, Social & Governance (ESG)
Local Enterprise Development: Partnering with community vendors for site catering and logistics
Learnership Program: Skills development for local youth
Transparency and Inclusion: Active engagement with Wards 40, 41, 42, 43, 44, 45, 49, 70 and 127 through
Local Economic Development (LED) Forums
Sustainability Focus: Safe operations, local procurement and community-driven impact
PAGE | 20
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
AUSTRALIA
Level 6, 400 Collins Street
Melbourne, Victoria
Australia
3000
INVESTOR RELATIONS
Jessica Fertig
ir@westwitsmining.com
SOUTH AFRICA
Unit 8A, Sifon Industrial Park
279 Sifon Street, Robertville
Roodepoort
1709
westwitsmining.com | info@westwitsmining.com
PAGE | 21
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Table 1: WBP (JORC) Ore Reserve2
Declared Ore Reserve of 4.6MT at 2.6g/t for 383,934oz Gold2
Ore Reserve Notes:
1. No Inferred Mineral Resources are included in the Ore Reserves.
2. The evaluation used a gold price US$2,850 per ounce and a rate of exchange of R18.0 / US$ 1.
WBP’s Global Mineral Resource is made up of several gold bearing reefs across the mining right area, a breakdown
by reef and MRE category is detailed in Table 21.
MRE Notes:
1. Global MRE set at a 2.0g/t Au cut-off. Reported in accordance with the JORC Code of 2012.
2. 1.24g/t Cut-off values are reported applying a gold price of $ 2 850/oz and ZAR 18/1 US$.
3. 2.0g/t Cut-off values are reported applying a gold price of $ 1 500/oz and ZAR 15.00/1 US$.
4. Number differences may occur due to rounding errors.
5. Mineral Resources are reported as inclusive of Ore Reserves.
6. The Inferred Mineral Resources have a high degree of uncertainty, and it should not be assumed that all or a
portion thereof will be converted to Ore Reserves.
Refer to slide 10 for Qala Shallows Mine inventory table – 1moz
Table 2: WBP (JORC) Mineral Resource Estimate – by Reef (2g/t cut-off)11
Ore Reserve Statement For Qala Shallows (JORC 2012)
ORE Reserve Category
Tonnage
(Mt)
Grade
(g/t)
Content
(kg)
Content
(oz)
Proved 1.1 2.79 3 086 99 205
Probable 3.49 2.54 8 856 284 730
Total 4.6 2.60 11 942 383 934
Note: errors may occur due to rounding differences
Note: errors may occur due to rounding differences
Appendix 1:
Ore Reserve & Mineral Resource Estimate Statements
Reef & Area
Measured Indicated Inferred Total
Au Cut-off
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Bird - Central 0.04 3.73 0.00 0.89 2.51 0.07 0.44 2.86 0.04 1.38 2.66 0.12 2 g/t
Bird - East 2.22 4.30 0.31 2.00 4.74 0.30 0.42 4.48 0.06 4.63 4.51 0.67 2 g/t
K9B KRC 0.00 2.98 0.00 0.10 3.87 0.01 0.18 4.22 0.02 0.28 4.08 0.04 2 g/t
K9B Qala 2.19 4.05 0.28 6.88 4.01 0.89 3.51 4.69 0.53 12.58 4.21 1.70 1.24 g/t
K9A Qala 2.85 3.84 0.35 2.67 3.59 0.31 7.94 3.01 0.77 13.45 3.30 1.43 1.24 g/t
K9B PR10730 2.04 4.95 0.33 1.74 4.07 0.23 1.40 3.54 0.16 5.18 4.28 0.71 1.24 g/t
K9A PR10730 1.23 4.03 0.16 0.80 4.67 0.12 4.28 3.02 0.42 6.31 3.42 0.69 1.24 g/t
K9B PR 10839 0.23 4.42 0.03 4.87 4.81 0.75 5.10 4.79 0.79 1.24 g/t
K9A PR 10839 0.01 2.07 0.00 3.39 3.77 0.41 3.39 3.77 0.41 1.24 g/t
Main Reef Leader 0.72 5.81 0.14 0.15 8.34 0.04 0.09 7.54 0.02 0.96 6.36 0.20 2 g/t
Main 2.79 4.73 0.42 0.09 5.15 0.01 0.31 5.27 0.05 3.19 4.79 0.49 2 g/t
Total 14.08 4.40 1.99 15.55 4.04 2.02 26.81 3.75 3.23 56.44 4.00 7.24
PAGE | 22
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Lindiwe Magidimisa
Projects & Business Development Manager
(SA)
BSc Chemical Engineering, PGDip Industrial Engineering, and
MBA. Experience spans multiple business functions, including
Capital Assurance, Capital Projects, Business Improvement, and
serving as Chief of Staff in CEO’s office at De Beers
Experienced Management Team
Martin Bevenlander
Head of Geology & Exploration
(SA)
Arnoldus Ludick
General Manager Finance and Admin
(SA)
Geologist with expertise that spans across the entire mining cycle
from greenfield exploration, and project development to
production. Worked in Indonesia, Papua New Guinea, Australia
and across Africa
CGMA, ACMA, AMDP with BCom (Hons) in Management and
Financial Accounting. Financial strategist with track record in cost
transformation and operational efficiency. Previous experience
includes Petra Diamonds and Anglo American
PAGE | 23
ASX:WWI COPYRIGHT © 2026 ALL RIGHTS RESERVED
Appendix 2
References (1/2)
1. The original report was “WBP Global MRE Increases with New Prospecting Right” which was issued with consent of the Competent Person, Mr Hermanus Berhardus Swart. The report
was released to the ASX on 16 December 2024 and can be found on the Company’s website (https://westwitsmining.com/). Comprising 10.7MT at 4.60g/t for 1.595Moz measured,
12.29MT at 4.19g/t for 1.70Moz Indicated and 10.49MT at 5.10g/t for 1.73Moz inferred. The Company is not aware of any new in formation or data that materially effects the
information included in the relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters
underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The form an d context in which the Competent Person’s
findings are presented have not been materially modified from the original market announcement.
2. The original report was “Updates to DFS provide Improved Results for WBP” which was issued with consent of the Competent Person, Mr. Andrew Pooley. The report was released to
the ASX on 23 July 2025 and can be found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially
effects the information included in the relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters
underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The form an d context in which the Competent Person’s
findings are presented have not been materially modified from the original market announcement. The DFS and any production target under the DFS contain inferred mineral
resources. The directors confirm that it is reasonable to include these inferred mineral resources in the well-understood and researched structure of the Witwatersrand Basin and the
views provided to WWI by independent geological expert consultants, given the project’s location and geology.
3. The original report was “Updated Mineral Resource Estimate for the Soweto Cluster” which was issued with consent of competent persons Mr. Hermanus Berhardus Swart, it was
released to the ASX on 22 January 2016 and can be found on the Company’s website (https://westwitsmining.com/). The company is not aware of any new information or data that
materially effects the information included in the relevant market announcement. The form & context in which the Competent Persons’ findings are presented have not been
materially modified.
4. The original report was “Wits Basin Scoping Study” which was issued with consent of the Competent Person, Mr. Andrew Pooley. The report was released to the ASX on 09/03/2022 and
can be found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the information included in
the relevant market announcement. The form and context in which the Competent Person’s findings are presented have not been materially modified from the original market
announcement.
5. The original report was “WBP’s Global JORC Mineral Resource Expands by 724,000oz to 4.28MOZ at 4.58 g/t Gold” which was issue d with consent of the Competent Person, Mrs Cecilia
Hattingh. The report was released to the ASX on 3 December 2021 and can be found on the Company’s website (https://westwitsmining.com/). Comprising 8.8MT at 4.60g/t for
1.449Moz measured, 11.3MT at 4.19g/t for 1.517Moz Indicated and 8MT at 5.10g/t for 1.309Moz inferred. The Company is not aware of any new information or data that materially
effects the information included in the relevant market announcement and, in the case of Mineral Resources or Ore Reserves,
Share your feedback
Discover