Completion of Qala Shallows Finance Package
Released
Released
Announcement PDF
Page | i
ASX Announcement and Media Release
Friday, 19 June 2026
WEST WITS EXECUTES DEFINITIVE LOAN AGREEMENTS TO
COMPLETE QALA SHALLOWS FINANCE PACKAGE
HIGHLIGHTS
➢ West Wits executes definitive loan agreements for the project finance package for the
Qala Shallows Gold Project — completing the Company's funding pathway to steady-state
gold production.
➢ The Absa Bank and Nedbank CIB finance package comprises the following facilities: (1) a
ZAR 875 million Senior Loan Facility; (2) a ZAR 150 million Working Capital Facility (WCF);
and (3) a ZAR 90 million Cost Overrun Debt Facility (CODF).
➢ The completion of all three facilities removes a key execution risk and positions West Wits
to accelerate the Qala Shallows ramp-up toward the targeted steady-state production rate
of ~70,000oz Au per annum from Q4 20282.
➢ West Wits is the first new underground gold mine to be developed in South Africa in over
15 years, backed by a DFS-confirmed USD 500 million post-tax NPV at USD 2,850/oz gold
price2 and a Global JORC Mineral Resource Estimate of 7.24Moz @ 4.0g/t Au1.
West Wits CEO and Managing Director, Rudi Deysel said:
"The execution of all three facility agreements marks the completion of our project finance
package and a significant step forward in the delivery of Qala Shallows. The Senior Loan
Facility, announced in May-26, provides the core capital backbone. The Working Capital
Facility and Cost Overrun Debt Facility now provide the commercial flexibility any operating
mine requires — ensuring we can efficiently manage our working capital cycle and maintain
financial resilience through the ramp-up phase. With our funding structure complete and gold
production already underway, the focus is entirely on disciplined operational delivery —
advancing underground development, increasing ore delivery rates to the Ezulwini processing
plant, and building toward steady-state production."
COMPLETION OF FULL PROJECT FINANCE PACKAGE
West Wits Mining Limited (ASX:WWI) (OTCQB:WMWWF) (“West Wits” or “the Company”) is
pleased to announce execution of definitive loan agreements for its project finance package
which fully funds the Qala Shallows Gold Project, the first stage of the Company's
Witwatersrand Basin Project ("WBP").
Page | ii
The full package comprises three complementary facilities, all provided collectively by Absa
Bank Limited (“Absa Bank”) and Nedbank Limited (acting through its Nedbank Corporate and
Investment Banking division) (“Nedbank CIB”) (together, the "Lenders"):
• ZAR 875 million Senior Loan Facility — the primary project finance facility, previously
announced following execution of a binding term sheet on 21 May 2026 (refer ASX
announcement dated 21 May 2026). Further details are set out in that announcement.
• ZAR 150 million Working Capital Facility (WCF) — a revolving credit facility to fund
production working capital cycle at a lower cost of debt.
• ZAR 90 million Cost Overrun Debt Facility (CODF) — a contingency facility providing
financial resilience through the construction and ramp-up period.
Credit approval for the Senior Loan Facility, WCF and CODF has been received from the
Lenders and definitive legal agreements for all three facilities have been executed. As noted
in the 21 May 2026 announcement, Absa Bank and Nedbank CIB offer a broader suite of
commercial banking products than the structure they replaced — the WCF and CODF are
tangible examples of that capability, directly tailored to the operational and risk profile of Qala
Shallows.
DETAILS OF THE WORKING CAPITAL FACILITY
The Working Capital Facility (WCF) is a short-term revolving credit line that provides
immediate liquidity relief during the production ramp-up, bridging the gap between ore
delivery and cash collection from gold sales.
Investment significance: The WCF directly addresses a common constraint for emerging gold
producers — the timing mismatch between incurring operational costs and receiving gold sale
proceeds. By drawing against verified sales invoices issued to Sibanye-Stillwater and self-
liquidating upon invoice settlement, the facility efficiently recycles working capital without
diluting equity or straining the Senior Debt Facility.
Working Capital Facility — Key Terms
Lenders Absa Bank Limited and Nedbank CIB
Borrower West Wits MLI (Pty) Ltd (South African subsidiary of West
Wits Mining Limited)
Facility Amount Up to ZAR 150,000,000
Interest Rate Variable rate linked to South African Prime Lending Rate
Drawdown Mechanism Drawdowns made against verified sales invoices issued by
West Wits to Sibanye-Stillwater Limited for gold sales
Repayment Automatic repayment upon settlement of the underlying
sales invoices
Purpose Fund the working capital cycle during production ramp-up
Page | iii
DETAILS OF THE COST OVERRUN DEBT FACILITY
The Cost Overrun Debt Facility (CODF) provides a dedicated contingency capital reserve,
ensuring Qala Shallows has access to additional funding in the event that project costs exceed
initial estimates during the drawdown period of the Senior Debt Facility.
Investment significance: Cost overrun facilities are a standard feature of commercial finance
structures. Their presence signals that the Lenders — two of South Africa's most experienced
mining finance institutions — have undertaken rigorous independent assessment of the
project and are comfortable providing contingency cover. For investors, the CODF reduces the
risk of unplanned equity dilution arising from project variability during the ramp-up phase.
The CODF is structured to activate only after: (i) full drawdown of the ZAR 875 million Senior
Debt Facility, and (ii) full expenditure of the ZAR 57 million Equity Cost Overrun Facility that
has already been funded by the Company. If drawn, repayment is from a cash sweep of excess
operating cashflow, aligning the facility's repayment profile with production performance.
Cost Overrun Debt Facility — Key Terms
Lenders Absa Bank Limited and Nedbank CIB
Borrower West Wits MLI (Pty) Ltd (South African subsidiary of West
Wits Mining Limited)
Facility Amount Up to ZAR 90,000,000
Interest Rate Variable rate linked to the South African Rand Overnight
Index Average (ZARONIA)
Drawdown Conditions Available after full drawdown of the Senior Debt Facility and
after expenditure of the ZAR 57 million equity-funded Cost
Overrun Reserve
Purpose Fund project cost overruns during the construction and ramp-
up period
Repayment Cash sweep of excess operating cashflow
Page | iv
COMPLETE FINANCE PACKAGE SUMMARY
Facility Amount (ZAR) Purpose Interest Rate Lender(s)
Senior Loan Facility 875,000,000 Project
development, ramp-
up & production at
Qala Shallows
Variable
(ZARONIA-
linked)
Absa Bank /
Nedbank CIB
Working Capital
Facility
150,000,000 Fund production
working capital
cycle via invoice
drawdowns
Variable
(Prime-linked)
Absa Bank /
Nedbank CIB
Cost Overrun Debt
Facility
90,000,000 Contingency funding
for cost overruns
after Senior Facility
drawdown
Variable
(ZARONIA-
linked)
Absa Bank /
Nedbank CIB
TOTAL PACKAGE 1,115,000,000
PROJECT CONTEXT AND PATH TO PRODUCTION
Qala Shallows represents Stage 1 of the WBP, which hosts a Global JORC Mineral Resource
Estimate of 7.24Moz @ 4.0g/t Au¹ within the Witwatersrand Basin — one of the world's most
prolific gold districts.
West Wits achieved first gold production from Qala Shallows in March 2026, with an inaugural
gold pour completed at Sibanye-Stillwater's Ezulwini processing plant on 17 March 2026. The
Company is now in its production ramp-up phase, with underground development advancing
and ore delivery rates progressively increasing.
The execution of all three facility agreements completes the Company's project finance
structure and removes key execution risk as development and production continue to ramp-
up. West Wits remains on track to reach steady-state production of approximately 70,000oz
per annum targeted from Q4 2028, supported by a DFS-confirmed post-tax NPV7.5 of USD 500
million at USD 2,850/oz gold price over a 16.8-year mine life.²
Key near-term milestones include:
• Continued underground development to unlock additional mining areas
• Progressive increase in ore delivery rates to the Ezulwini processing plant
• Establishment of grid power connection (targeted Q4 2026) to improve operational cost
efficiency
• Advancement of Project 200 Scoping Study, targeting a materially higher production
profile of ~200,000oz per annum
Page | v
West Wits acknowledges the continued support and commitment of Absa Bank and Nedbank
CIB in completing the full finance package. Their expertise in structuring mining project finance
solutions tailored to the requirements of Qala Shallows has been integral to advancing the
project to this stage.
Approved for release by the Managing Director and CEO, Rudi Deysel.
For further information contact:
Jessica Fertig, Investor Relations
IR@westwitsmining.com
General info@westwitsmining.com
www.westwitsmining.com
ABOUT WEST WITS MINING LIMITED
West Wits Mining Limited (ASX: WWI) (OTCQB: WMWWF) is focused on the exploration,
development and production of high-value precious and base metals for the benefit of
shareholders, communities and environments in which it operates. Witwatersrand Basin
Project, located in the proven gold region of Central Rand Goldfield of South Africa, boasts a
7.24Moz gold project at 4.0g/t1. The Witwatersrand Basin is a largely underground geological
formation which surfaces in the Witwatersrand. It holds the world's largest known gold
reserves and has produced over 1.5 billion ounces (over 40,000 metric tons), representing
about 22% of all the gold accounted for above the surface.
1. The original report was “2.2Moz Increase to WBP Global Resource Estimate to 7.24Moz ” which was issued with consent
of the Competent Person, Mr Hermanus Berhardus Swart. The report was released to the ASX on 02 February 2026 and
can be found on the Company’s website (https://westwitsmining.com/). Comprising 14.08MT at 4.40g/t for 1.99Moz
Measured, 15.55MT at 4.04g/t for 2.02Moz Indicated and 26.81MT at 3.75g/t for 3.23Moz Inferred. The Company is not
aware of any new information or data that materially effects the information included in the relevant market
announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially
changed. The form and context in which the Competent Person’s findings are presented have not been materially
modified from the original market announcement.
2. The original report was “Updates to DFS provide Improved Results for WBP” which was issued with consent of the
Competent Person, Mr. Andrew Pooley. The report was released to the ASX on 23 July 2025 and can be found on the
Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that
materially effects the information included in the relevant market announcement and, in the case of Mineral Resources
or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed. The form and context in which the Competent
Person’s findings are presented have not been materially modified from the original market announcement. The DFS and
any production target under the DFS contain inferred mineral resources. The directors confirm that it is reasonable to
include these inferred mineral resources in the well-understood and researched structure of the Witwatersrand Basin and