First Underground Ore Production at Qala Shallows
Released
Released
Announcement PDF
Page | i
ASX Announcement and Media Release
Wednesday, 15 October 2025
First Underground Ore Production at Qala Shallows
West Wits Mining Limited (ASX:WWI) (OTCQB:WMWWF) (West Wits, WWI or the Company)
is pleased to announce a major operational milestone with the first underground ore
production delivered to the stockpile overnight from the Qala Shallows gold project, marking
commencement of underground ore production within South Africa’s Witwatersrand Basin.
This achievement signifies the Company’s successful transition from mobilisation and
preparatory development works to underground ore extraction — a critical step toward
establishing a long-life, steady-state gold operation at the one of the world’s most historically
productive gold regions.
HIGHLIGHTS
First Underground Ore Delivered:
• Ore from Qala Shallows successfully stockpiled on surface following commissioning of
critical underground infrastructure.
• A full-length engineered concrete haul road and formal water management systems
completed to support continuous ore movement and safe operations.
Underground Mining Capability Commissioned:
• The first underground double boom drill rig has been delivered, commissioned and is
now operational underground.
• Operational ramp-up underway with full staffing of key technical roles and
commencement of night-shift operations to accelerate production.
Infrastructure & Safety Milestones Achieved:
• Cover drilling completed, underground communications commissioned and decline
lighting installed.
• The newly installed Proximity Detection System and fire suppression on the drill rig
reinforce WWI’s commitment to best-practice safety and compliance.
Production Outlook:
• Targeting a 30,000-tonne ore stockpile by end-of-Q1 2026, with first gold processing
expected in Q1 2026.
• Processing to commence through the Sibanye-Stillwater Limited’s Ezulwini
Processing Plant under a toll-treatment agreement.
Robust Funding Position:
• West Wits remains well capitalised with A$17.7m raised in Sep-25 and separate
agreements for a US$12.5m Nebari loan facility and a ~US$50m syndicated loan
facility in place, subject to fulfilment of conditions precedents, to fully support the
transition into production and ramp-up.
Page | ii
Commenting on this strong progress, Rudi Deysel CEO stated:
“This marks a transformational step for West Wits — the beginning of true underground
mining at Qala Shallows. With our first ore delivered to surface and on-reef development now
underway, we’ve crossed the threshold into production, demonstrating the strength of our
execution and the commitment of our team.
The progress achieved by our team since mobilisation in July is exceptional. Supported by a
strong funding position and robust infrastructure, we are firmly on track to establish a long-
life gold operation within the renowned Witwatersrand Basin.”
Overview
West Wits has achieved substantial progress at the Qala Shallows Project, underpinned by a
strong funding base comprising of the A$17.7 million Sep-25 equity placement and separate
agreements in place for a US$12.5 million Nebari loan facility and a ~US$50 million syndicated
loan facility with drawdown subject to fulfilment of conditions precedents. This robust
financial position has enabled the Company to rapidly deliver critical infrastructure, advancing
Qala Shallows toward sustained underground production.
Over recent months, underground development has progressed on schedule, with key
milestones achieved:
• Cover drilling completed
• Underground communications commissioned
• Decline lighting installed
• Concrete haul road completed
IMAGE 1: UNDERGROUND INFRASTRUCTURE AND ROADWAY DEVELOPMENT PREPARED BY
THE PRODUCTION TEAM LAYING THE FOUNDATION FOR SAFE ACCESS AND ORE TRANSPORT
Page | iii
These installations have established a safe, fully connected and modern underground
environment, providing the foundation for efficient mining operations.
The transition to underground production represents a pivotal milestone in the Qala Shallows
development. Delivering first ore to surface and commissioning the site’s first -double boom
drill rig for underground operations required extensive preparatory works, including the
construction of a full-length engineered concrete roadway through the box-cut capable of
supporting heavy haulage and the integration of formal drainage systems to manage water
flow. Construction began on 8 September 2025, with the first concrete pour in early October
2025 and the haul road reaching operational strength, enabling the first ore haulage from the
decline portal this week.
IMAGE 2: DRILL RIG DELIVERED TO QALA SHALLOWS
The double boom underground drill rig delivered following successful commissioning at GST
SA, has now commenced drilling. The rig was fitted with Level 9 (collision avoidance),
proximity detection and fire detection and suppression systems, ensuring compliance with
South African mining safety standards and reinforcing West Wits’ commitment to a safe, high-
integrity operation.
Operational ramp-up is well underway, supported by the implementation of night-shift
operations and the appointment of key technical personnel across production, engineering,
and safety disciplines. These additions — including a Production Manager, General
Engineering Supervisor, Safety Officers, Shift Supervisors, Miners, Boilermakers and
Electricians — bring the expertise required to sustain safe and efficient underground
development.
Page | iv
IMAGE 3: DRILL RIG OPERATIONAL UNDERGROUND
Drilling operations have now commenced, with support drilling active along the 1 West and
Main Declines, and face drilling initiated at the 1 East Decline. These activities mark the start
of full-scale underground development, transitioning Qala Shallows from early-stage
handheld operations to mechanised production.
The Company is targeting a 30,000-tonne ore stockpile by the end of Q1 2026 to establish a
consistent ore supply to the Ezulwini Processing Plant, operated under an exclusive toll-
treatment agreement with Sibanye-Stillwater. Stockpiling is already underway at a dedicated
storage pad within the Ezulwini facility. Processing is expected to commence in Q1 2026,
culminating in the first gold pour, which will mark the transition to revenues from gold sales.
IMAGE 4: LHD DROPS FIRST ORE AS PRODUCTION ACTIVITY BEGINS TO RAMP UP ON SITE
Page | v
IMAGE 5: LHD EXITING QALA SHALLOWS CONCRETED BOX-CUT ROADWAY
WITH THE FIRST LOAD OF ORE
Stage One of the WBP project - Qala Shallows
Definitive Feasibility Study (DFS) (ASX release July 2025)1,2
• Confirms an Ore Reserve of 4.6Mt at 2.60g/t for 383,934oz Au
• Supporting a ~17-year Life-of-Mine with a total production of 944,000oz Au
• Steady-State Production Planned ramp-up to 70,000oz per annum over 12 years
• Production commences at an initial rate of 15,000–20,000t ore per month from Q1
2026, reaching 65,000t per month within three years.
IMAGE 6: QALA SHALLOWS IS FULLY MOBILISED AND ORE PRODUCTION HAS COMMENCED
Page | vi
Approved for release by the Company’s Managing Director, Rudi Deysel.
For further information contact:
Keith Middleton
keith@middletoncorporate.com.au
General info@westwitsmining.com
www.westwitsmining.com
ABOUT WEST WITS MINING LIMITED
West Wits Mining Limited (ASX: WWI) (OTCQB: WMWWF) is focused on the exploration, development and
production of high-value precious and base metals for the benefit of shareholders, communities and
environments in which it operates. Witwatersrand Basin Project, located in the proven gold region of Central
Rand Goldfield of South Africa, boasts a 5.025Moz gold project at 4.66g/t3
. The Witwatersrand Basin is a largely
underground geological formation which surfaces in the Witwatersrand. It holds the world's largest
known gold reserves and has produced over 1.5 billion ounces (over 40,000 metric tons), representing about 22%
of all the gold accounted for above the surface. In Western Australia, WWI is exploring gold and copper at the
Mt Cecilia Project in a district that supports several world-class projects such as Woodie Woodie manganese
mine, Nifty copper and Telfer gold/copper/silver mines.
1. The original report was “Updates to DFS provide Improved Results for WBP” which was issued with consent of the
Competent Person, Mr. Andrew Pooley. The report was released to the ASX on 23 July 2025 and can be found on the
Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that
materially effects the information included in the relevant market announcement and, in the case of Mineral Resources
or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed. The form and context in which the
Competent Person’s findings are presented have not been materially modified from the original market announcement.
The directors confirm that it is reasonable to include these inferred mineral resources in the well understood and
researched structure of the Witwatersrand Basin and the views provided to WWI by independent geological expert
consultants, given the project’s location and geology.
2. The DFS and any production target under the DFS contain inferred mineral resources. The directors confirm that it is
reasonable to include these inferred mineral resources in the well-understood and researched structure of the
Witwatersrand Basin and the views provided to WWI by independent geological expert consultants, given the project’s
location and geology.
3. The original report was “WBP Global MRE Increases with New Prospecting Right” which was issued with consent of the
Competent Person, Mr Hermanus Berhardus Swart. The report was released to the ASX on 16 December 2024 and can
be found on the Company’s website (https://westwitsmining.com/). Comprising 10.7MT at 4.60g/t for 1.595Moz
measured, 12.29MT at 4.19g/t for 1.70Moz Indicated and 10.49MT at 5.10g/t for 1.73Moz inferred. The Company is not
aware of any new information or data that materially effects the information included in the relevant market
announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially
changed. The form and context in which the Competent Person’s findings are presented have not been materially
modified from the original market announcement.