Quarterly Activity Report
Reporting Period 1 April – 30 June 2026
HIGHLIGHTS
Qala Shallows Operations
➢ Development Milestone: 1 West Decline breakthrough achieved at Qala Shallows, unlocking access to
historically pre-developed stoping areas on 2 Level and higher-grade production zones, requiring only
minor modifications to accommodate modern trackless mining vehicles and accelerate production.
➢ Underground Development: 544m of underground development to 30 June 2026, including 375m on-reef
development and 168m waste development.
➢ Early Production: deliveries of on-reef development ore to Sibanye Stillwater Ltd’s Ezulwini Plant during
the quarter delivered 4.6kg (148oz) of gold with YTD production 7.05kg (227oz).
➢ Surface Infrastructure on track with 45% of all works now complete: EPCM critical infrastructure roll-out
accelerating which includes permanent warehouse completed & operational, new haulage road 90%
completed and in use, storm water management system and excavation of the pollution control dam
completed.
➢ Fleet Expansion: new critical underground equipment with two 10-tonne LHD’s and a 3rd
Jumbo drill rig
delivered to expand underground fleet capacity and mining flexibility.
➢ Scoping Study – Expanded Scope to assess multiple development and processing pathways across the
WBP, including construction of a standalone processing plant, third-party processing partnerships and
integration of additional ore sources; results expected to be received from the consultant by end July and
be available for public release early August 2026.
➢ Bird Reef Central (BRC) Uranium / Gold Project: drawdown of Senior Loan Facility enables allocation
surplus capital towards growth projects with the Company finalising plans for implementing the
exploration programme targeting a declared Uranium JORC Mineral Resource Estimate.
Corporate
➢ Fully Funded Project: Cash as at 30 June 2026 was ~A$32M
➢ Finance Package Complete & First Drawdown: Full project finance package executed: ZAR 875 million
Senior Loan Facility + ZAR 150 million Working Capital Facility + ZAR 90 million Cost Overrun Debt Facility,
with Absa Bank and Nedbank CIB, two of South Africa’s leading corporate and investment banks.
➢ Nebari Repaid: Nebari Loan Facility (USD 12.5 million) repaid in full, concluding the Sep-25 bridge funding
initiative to advance Qala Shallows development until first drawdown of the Senior Loan Facility.
➢ Portfolio Rationalisation: Execution of sale agreement to divest Mt Cecelia Project to Aventine Resources
Limited (“Aventine”) under a value-accretive structure comprising $2.0 million in Aventine equity, a 1%
NSR and $1.0 million in milestone consideration on definition of a 500,000oz Au JORC Resource.
➢ Capital Consolidation: Capital consolidation completed on a 10-for-1 basis, reducing shares on issue to
434,647,512 ordinary shares and improving capital structure ahead of the institutional finance close.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27
July 2026
westwitsmining.com | ir@westwitsmining.com page 2
CEO and Managing Director, Rudi Deysel:
“The June quarter marks a step-change in the operations of West Wits. The 1 West Decline breakthrough
is the moment we have been building toward — it transitions Qala Shallows from early on-reef
development ore into pre-existing higher-grade stopes and provides access to a significant inventory that
requires reduced preparation work.
With the full project Absa / Nedbank finance package now executed and Nebari repaid, our funding
structure is complete. The proposed divestment of Mt Cecelia to a West Australian focused explorer
rationalises West Wits asset portfolio whilst retaining exposure to Mt Cecelia’s upside at zero ongoing cost.
The operational priority for the next quarter is clear: advance development rates, ramp up production, and
execute the Scoping Study to define the pathway to 200,000oz per annum. Finalising the project finance
also enables the Company to finalise exploration plans for the standalone BRC Uranium / Gold Project
which is viewed as an organic strategic growth project.”
IMAGE 1: AERIAL VIEW OF QALA SHALLOWS WITH DEVELOPMENT OF SURFACE INFRASTRUCTURE ON-TRACK
WITH WORKS 45% COMPLETE WHILST MAINTAINING FULL UNDERGOUND MINING OPERATIONS
The Qala Shallows Project continued to make significant progress during the quarter, with further
advances across the site supporting the ongoing development of the operation. A key milestone was the
completion of the new tarred access road, providing direct access from the main public road into the mine
and significantly improving logistics, traffic flow and site accessibility. Surface development also advanced
substantially, with the operations precinct now well established and comprising offices, workshops, stores,
security and access control facilities, and other key operational buildings. These milestones strengthen the
operational capability of the site and support the continued ramp-up of mining activities as the Project
progresses towards steady-state production.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27
July 2026
westwitsmining.com | ir@westwitsmining.com page 3
OPERATIONS AND PROJECT DEVELOPMENT
WITWATERSRAND BASIN PROJECT (“WBP”), GAUTENG, SOUTH AFRICA
The June 2026 quarter was defined by a decisive operational breakthrough, the completion of the Company’s
project finance package, and significant portfolio rationalisation. West Wits Mining Limited (ASX: WWI;
OTCQB: WMWWF) (“West Wits” or “the Company”) is advancing its transition to a sustainable gold producer,
with underground development at Qala Shallows progressing to unlock higher-grade production areas and
achieving first drawdown of the Senior Loan Facility for the fully funded project.
1 West Decline Breakthrough — A Major Production Milestone
West Wits achieved the breakthrough of its 1 West Decline into the 2 Level mining horizon at Qala Shallows
at the end of May 2026. This is a major operational milestone for the project, transitioning the operation from
initial diluted development ore into areas of historically pre-developed underground workings containing
established, unmined stoping areas.
The breakthrough was the result of the Definitive Feasibility Study’s(“DFS”) mine plan optimisation specifically
designed to accelerate payback, improve capital efficiency and strengthen the overall project business case. 2
Level development leverages existing underground infrastructure from historical mining operations, requiring
only minor modifications to accommodate modern trackless mining vehicles to access previously exposed
stoping areas.
As previously disclosed, the availability of these historical working areas is estimated to save approximately
one year of additional development work that would otherwise have been required to establish equivalent
access to new stopes. Rather than continuing to mine lower grade on-reef development ore, the operation
can now begin including, higher-grade production areas to improve mine grades and cash generation during
the ramp-up phase, accelerating progress toward the DFS-modelled steady-state production profile of
approximately 70,000oz per annum2
.
IMAGE 2: 1 WEST DECLINE BREAKTHROUGH ACHIEVED AT QALA SHALLOWS
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27
July 2026
westwitsmining.com | ir@westwitsmining.com page 4
Underground Operations and Ramp-Up Progress
During the quarter, the Company continued to advance underground development and production:
• Installation of support structures completed in June 2026 in the weathered zone of a known geological
feature of the main decline near surface. The main decline entered competent ground in July, requiring
standard roof bolting only and thereby resulting in increased advance rates.
• 544m of underground development to 30 June 2026, including 375m on-reef development and 168m
waste development. Decline developments include:
o Main Decline: 63m
o 1 East Decline: 53m
o 1 West Decline: 132m
• Ore production ramp-up progressing from underground workings with ore delivery to Sibanye-
Stillwater’s Ezulwini processing plant increasing progressively with 7.05kg (227oz) of gold produced from
on-reef development ore to 30 June 2026.
• Additional operational flexibility established within the mine plan as the 1 West Decline breakthrough
opens access to the near-term stoping inventory in the western section of 2 Level.
These results were pleasing in the context of delays occasioned through having to work through
considerable weathered zone material in the shallow area where the Main Decline commences and also
the mandatory pause in operations required to investigate the unfortunate mud rush event of 10 June.
FIGURE 1: QALA SHALLOWS UNDERGROUND DEVELOPMENT WITH EXISTING WESTERN STOPING AREAS
NOW ACCESSIBLE FOLLOWING 2 LEVEL BREAKTHROUGH VIA 1 WEST (1W) DECLINE
Surface Infrastructure and Energy Supply
Surface infrastructure development program under the EPCM contractor is on track with 45% of all works
completed at period end. Primary assets advanced during the period include:
• Haulage road construction approximately 90% complete, with haulage trucks already utilising the new
dedicated entrance and route.
• New Main Store facility construction completed, providing secure and organised storage for critical
spares, consumables and consignments and improving inventory management.
• Site access control transitioned from a manual process to a fully integrated electronic access control
system, improving site security as operations expand.
• Installation of storm water management system and excavation of the pollution control dam completed.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27
July 2026
westwitsmining.com | ir@westwitsmining.com page 5
• The Company’s fuel supply arrangements remain sufficient to support planned mining and development
activities without disrupting production. Upon connection to grid power, estimated for early 2027, the
Company expects a material reduction in diesel consumption, with diesel generators transitioning to a
backup role which will reduce operating costs and exposure to fuel price volatility.
IMAGE 3: OPERATIONAL INFRASTRUCTURE UPGRADES AND UNDERGROUND FLEET
EXPANSION ACTIVITIES AT QALA SHALLOWS
Underground Fleet Expansion
To support the next phase of the underground production ramp-up and increase operational capacity, West
Wits strengthened its underground fleet during the quarter:
• New 10-tonne Load-Haul-Dump (“LHD”) unit delivered to site, increasing ore-handling capacity and
flexibility within the mine workings.
• An additional jumbo drill rig delivered, enhancing drilling capacity for stope and development advance.
People and Safety
Key appointment of Sephela Makete Thema (“Makete”) as Head of Operations in May 2026, further
strengthening the Company's executive leadership team. Prior to joining West Wits, Makete led Fraser
Alexander's Tailings and Remining Division across South Africa and Namibia, overseeing a workforce of more
than 2,000 employees. His previous leadership roles at Sibanye-Stillwater included Relieving Vice President
and Head of Operations, Mine Manager and Mine Overseer, where he successfully delivered improvements in
production, safety and operational performance. He holds a Bachelor of Science in Mining Engineering and a
Master of Science in Engineering from the University of the Witwatersrand, as well as a Postgraduate Diploma
in Business Administration from the University of Pretoria. Makete has quickly integrated as a vital leader of
the operations team.
Local workforce recruitment to support project development continues with a total labour contingent of 431
on 30 June 2026, including 64 personnel on West Wits’ Owners Team and 367 Contractors, which is on-track
towards total labour requirement at steady-state operations of approximately 1,100 personnel.
The Company was saddened to report the mud rush incident at Qala Shallows on 10 June 2026 which resulted
in the fatality of a contractor’s employee. The Company has extended its deepest condolences to the workers
family, friends and colleagues. The incident was formally notified to the South African Department of Mineral
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27
July 2026
westwitsmining.com | ir@westwitsmining.com page 6
and Petroleum Resources (“DMPR”) in accordance with regulatory protocols. The Company cooperated fully
with the DMPR’s formal investigation which was completed with all operational restrictions lifted and no
adverse findings against West Wits
Sustainability and Community Partnerships
West Wits continues to advance its Enterprise and Supplier Development initiatives alongside the
development of the Qala Shallows Project.
During the quarter, the Company officially launched its Food Vendor Project, creating sustainable local
enterprise opportunities directly linked to mining operations. Successful vendors received professionally fitted
facilities, with supporting water and electricity infrastructure.
The initiative forms part of the Company's broader commitment to promoting local economic participation
and supporting the growth of sustainable community businesses.
IMAGE 4: FOOD VENDOR PROJECT LAUNCHED TO CREATE SUSTAINABLE LOCAL ENTERPRISE OPPORTUNITIES
West Wits facilitated a Terms of Reference Workshop with the Local Economic Development (“LED”) Forum,
representing local government Wards 40, 41, 42, 43, 44, 45, 49, 70 and 127. These wards comprise the
Company's Social and Labour Plan host and affected communities, where the company is committed to
delivering sustainable socio-economic development initiatives.
The workshop established a shared governance framework that defines the Forum's purpose, roles,
responsibilities and decision-making processes, providing a transparent platform for ongoing engagement
between West Wits and community representatives.
IMAGE 5: MEMBERS OF THE LOCAL ECONOMIC DEVELOPMENT (LED) FORUM DURING THE TERMS OF
REFERENCE WORKSHOP
Executive Director and Head of Corporate Affairs, Tozama Kulati Siwisa, received the Most Visionary Architect
of Sustainable Mining and Social Transformation 2026 award at The Global Icons of Impact 2026. The award
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27
July 2026
westwitsmining.com | ir@westwitsmining.com page 7
recognises her leadership in advancing sustainable mining practices and integrating meaningful social impact
into West Wits' growth strategy. Once again Tozama’s leadership and professionalism have been recognised
at industry level. Congratulations to Tozama on another well-earned accolade.
IMAGE 6: EXECUTIVE DIRECTOR AND HEAD OF CORPORATE AFFAIRS, TOZAMA KULATI SIWISA, RECOGNISED
FOR LEADERSHIP IN SUSTAINABLE MINING
FINANCIAL POSITION AND FUNDING
Completion of Full Project Finance Package
The June 2026 quarter saw West Wits complete its full project finance package, a landmark achievement that
further mitigates risk on the pathway to steady-state production. The package, provided by Absa Bank Limited
and Nedbank Limited (acting through its Nedbank Corporate and Investment Banking division) (“Nedbank
CIB”), comprises three complementary facilities:
Facility Amount (ZAR) Purpose Rate Lender(s)
Senior Loan Facility 875,000,000 Project development, ramp-
up & production at Qala
Shallows
ZARONIA-
linked
Absa /
Nedbank CIB
Working Capital Facility (WCF) 150,000,000 Fund production working
capital cycle via invoice
drawdowns
Prime-linked Absa /
Nedbank CIB
Cost Overrun Debt Facility
(CODF)
90,000,000 Contingency funding for cost
overruns after Senior Facility
drawdown
ZARONIA-
linked
Absa /
Nedbank CIB
TOTAL PACKAGE 1,115,000,000
The completion of all three facilities by two of South Africa’s leading mining finance institutions represents a
strong institutional endorsement of the Qala Shallows Project’s technical credentials and commercial viability.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27
July 2026
westwitsmining.com | ir@westwitsmining.com page 8
The Working Capital Facility (“WCF”) directly addresses the timing mismatch between incurring operating
costs and receiving gold sale proceeds by drawing against verified Sibanye-Stillwater sales invoices, efficiently
recycling capital without diluting equity. The Cost Overrun Debt Facility (“CODF”) provides a final-line
contingency buffer that protects shareholders from unplanned dilution arising from project variability during
the ramp-up phase. Notably, the hedging structure — protecting 50% of planned gold sales through
construction via a Put Option programme — ensures the project maintains full upside exposure to gold prices,
which at current levels above USD 3,500/oz represent meaningful incremental value beyond the DFS base case
of USD 2,850/oz.
Nebari Loan Repaid — Financial Close of SA Senior Loan Imminent
On 26 June 2026, West Wits announced the full repayment of the USD 12.5 million Tranche 1 loan facility to
the Nebari Natural Resources Credit Fund II LP (“Nebari”), drawn down in November 2025. Repayment of the
Nebari Facility released all associated obligations and security as part of satisfying the final conditions
precedent for financial close of the ZAR 875 million SA Senior Loan Facility with Absa Bank and Nedbank CIB.
The Company acknowledges the pivotal role that Nebari played in the development of Qala Shallows.
Drawdown of the USD 12.5 million Tranche 1 in November 2025, as part of a scalable USD 35 million package,
provided critical capital that directly enabled the ramp-up of underground operations, the purchase of critical
plant and equipment, and the continued delivery of ore to the Ezulwini processing plant.
With the Nebari Facility fully repaid and the SA Senior Loan at financial close, the Company transitions to a
lower-cost, longer-tenure institutional finance structure purpose-built for a producing mine. This replaces a
bridge facility with a full project finance framework, materially reducing the Company’s financing costs during
ramp-up and providing the capital certainty needed to execute the mine plan through to steady-state
production.
Capital Consolidation
Following approval by shareholders at the 8 April 2026 general meeting held, West Wits' issued capital was
consolidated on a 10-for-1 basis. Updated holding statements were dispatched on 16 April 2026. The post-
consolidation capital structure is as follows:
Class of Security Pre-Consolidation Post-Consolidation
WWI (Ordinary Shares) 4,346,465,221 434,647,512
WWIO (Listed Options) 302,551,631 30,255,205
WWIAC (Unlisted Options) 386,963,596 38,696,376
WWIAD (Performance Rights) 2,500,000 250,000
WWIAG (Warrants) 166,933,764 16,693,377
The consolidation reduces the share count from approximately 4.3 billion to 434.6 million shares, simplifying
the capital structure and improving the Company’s positioning ahead of institutional engagement and the
formal close of the SA Senior Loan Facility.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27
July 2026
westwitsmining.com | ir@westwitsmining.com page 9
CORPORATE ACTIVITY
Divestment of Mt Cecelia Project — Crystallising Value, Retaining Upside
On 29 April 2026, West Wits announced the proposed divestment of its Mt Cecelia Project in Western Australia
by selling 100% of the issued capital of Northern Reserves Pty Ltd to Aventine Resources Limited, a gold-copper
exploration company focused on the highly prospective Paterson Province.
The transaction is structured to deliver immediate and potential future value while eliminating all ongoing
capital obligations in respect of the Mt Cecelia Project:
• $2.0 million in Aventine equity (calculated at the IPO public offering price, equating to 10,000,000
Aventine fully paid ordinary shares) providing leverage to exploration success.
• 1% Net Smelter Royalty (“NSR”) over all future production (subject to potential buy-back of 50% of the
royalty by Aventine for $2 million).
• Deferred consideration of up to $1.0 million (cash or shares at Aventine’s election) upon
announcement of a JORC-compliant Inferred or greater Mineral Resource Estimate of at least
500,000oz gold at a minimum cut-off of 0.5g/t, achievable within 5 years of completion.
The transaction would eliminate all ongoing capital requirements in respect of Mt Cecelia while retaining
meaningful exposure to its exploration upside through equity, a royalty and milestone consideration. By
transferring the asset to a dedicated, funded explorer in Aventine — which is targeting an ASX listing in Q32026
in the Paterson Province, proximate to Telfer, Havieron, Winu and Minyari Dome — West Wits shareholders
would gain leveraged exposure to one of Australia’s most active discovery districts with no ongoing financial
obligation. The divestment would also free management attention and capital to focus exclusively on the Qala
Shallows production ramp-up and the Project 200 growth strategy.
The transaction remains subject to Aventine’s proposed ASX listing and capital raising being completed , and
receipt of all necessary regulatory approvals.
Investor Engagement
West Wits maintained an active investor engagement programme during the quarter, participating in leading
mining and investment conferences across Asia, Australia and South Africa.
In Hong Kong, Non-Executive Director Warwick Grigor met with institutional investors, fund managers and
family offices during the Ignite Partners Investment Summit and Resourcing Tomorrow conference. The
meetings reflected growing interest from Asian investors seeking exposure to a well-funded, near-term gold
producer operating in the world-renowned Witwatersrand Basin.
The Company also participated in the RIU Sydney Resources Round-up, where CEO and Managing Director
Rudi Deysel presented West Wits' production ramp-up strategy at Qala Shallows.
In South Africa, Chief Financial Officer Simon Whyte represented the Company at Junior Indaba 2026,
providing delegates with an update on the Company's execution milestones and growth strategy.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27
July 2026
westwitsmining.com | ir@westwitsmining.com page 10
IMAGE 7: WEST WITS SENIOR LEADERSHIP ENGAGES INVESTORS AT RIU SYDNEY RESOURCES ROUND-UP 2026
EXPLORATION AND RESOURCE DEVELOPMENT
WBP Mineral Resource Estimate — 7.24Moz @ 4.0g/t Au1
The Company’s Global JORC Mineral Resource Estimate for the Witwatersrand Basin Project, announced on 2
February 2026, remains at 7.24Moz @ 4.0g/t Au1
. The MRE is underpinned by three distinct gold-bearing reef
horizons — the Kimberley Reef, Bird Reef and Main Reef — and is structured as follows:
TABLE 1: WBP GLOBAL JORC MINERAL RESOURCE ESTIMATE AS AT 1 FEBRUARY 2026¹
Category Tonnes (M) Grade (g/t Au) Ounces Au Cut-off
Measured 14.08 4.40 1,991,000 Various
Indicated 15.55 4.04 2,020,000 Various
Measured & Indicated 29.63 4.21 4,012,000
Inferred 26.81 3.75 3,232,000
Total 56.44 4.00 7,244,000
Notes: Mineral Resources are reported in accordance with the JORC Code (2012 Edition). The MRE is reported at a blended cut-off of 2.0g/t
Au for Bird Reef and Main Reef areas and 1.24g/t Au for Kimberley Reef areas. Mineral Resources are reported as inclusive of Ore Reserves.
With 4.0Moz (55%) classified as Measured and Indicated — the highest confidence JORC categories — the
WBP resource base provides a robust foundation for mine development and bank finance. The high average
grade of 4.0g/t Au reflects the Witwatersrand Basin’s exceptional geological endowment.
Project 200 Scoping Study — Expanded Scope
During the quarter, West Wits announced an expanded scope for its Project 200 Scoping Study, with
completion revised to end-July 2026 with results expected to be available for release in early August 2026.
The revision reflects a strategic decision to broaden the analysis and assess multiple development and
processing pathways across the broader WBP, rather than limiting the study to a single expansion scenario.
The expanded study, being undertaken by independent consultants Bara Consulting (Pty) Ltd, is expected to
evaluate three to four potential development scenarios including:
• Construction of a standalone processing plant at the WBP.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27
July 2026
westwitsmining.com | ir@westwitsmining.com page 11
• Utilisation of third-party processing infrastructure through strategic partnerships with established South
African gold producers and processing groups.
• The potential integration of additional ore sources and future mining areas beyond the current Qala
Shallows mine plan, leveraging the broader WBP’s 7.24Moz Mineral Resource1
base and additional
prospecting rights.
Engagement with established South African gold producers and processing groups reflects the growing
recognition of WBP’s scale and strategic location in the Central Rand Goldfield. A study outcome that aims to
identify a viable pathway to approximately 200,000oz per annum — compared to the current Stage 1 DFS
target of approximately 70,000oz per annum — would represent a step-change in the Company’s production
and cash flow profile, potentially reshaping the investment case to a mid-tier gold producer.
Bird Reef Central (BRC) Uranium-Gold Opportunity
The BRC Project, located within the WBP Mining Right, continues to be assessed for its potential as a
standalone uranium-gold project within the Witwatersrand Basin. With the Senior Loan Facility now drawn,
the Company is finalising plans for implementing the exploration programme targeting a declared Uranium
JORC Mineral Resource Estimate. The BRC Project provides dual-commodity exposure for shareholders —
uranium upside with meaningful gold credits — leveraging the Company’s existing geological knowledge,
infrastructure and Mining Right position.
Approved for release by the Board of West Wits Mining Limited.
For Investor Relations contact:
Jessica Fertig, Investor Relations — ir@westwitsmining.com
General:
info@westwitsmining.com
westwitsmining.com
ABOUT WEST WITS MINING LIMITED
West Wits Mining Limited (ASX: WWI) (OTCQB: WMWWF) is focused on the exploration, development and production
of high-value precious and base metals for the benefit of shareholders, communities and environments in which it
operates. Witwatersrand Basin Project, located in the proven gold region of Central Rand Goldfield of South Africa,
boasts a 7.24Moz gold project at 4.0g/t1
. The Witwatersrand Basin is a largely underground geological formation which
surfaces in the Witwatersrand. It holds the world’s largest known gold reserves and has produced over 1.5 billion
ounces (over 40,000 metric tons), representing about 22% of all the gold accounted for above the surface.
1. The original report was “2.2Moz Increase to WBP Global Resource Estimate to 7.24Moz” which was issued with consent of the Competent
Person, Mr Hermanus Berhardus Swart. The report was released to the ASX on 02 February 2026. Comprising 14.08MT at 4.40g/t for
1.99Moz Measured, 15.55MT at 4.04g/t for 2.02Moz Indicated and 26.81MT at 3.75g/t for 3.23Moz Inferred. The Company is not aware of
any new information or data that materially affects the information included in the relevant market announcement and, in the case of
Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates continue to apply
and have not materially changed.
2. The original report was “Updates to DFS provide Improved Results for WBP” which was issued with consent of the Competent Person, Mr.
Andrew Pooley. The report was released to the ASX on 23 July 2025 and can be found on the Company’s website
(https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the information included
in the relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The
form and context in which the Competent Person’s findings are presented have not been materially modified from the original market
announcement. The DFS and any production target under the DFS contain inferred mineral resources. The directors confirm that it is
reasonable to include these inferred mineral resources in the well-understood and researched structure of the Witwatersrand Basin and the
views provided to WWI by independent geological expert consultants, given the project’s location and geology.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27
July 2026
westwitsmining.com | ir@westwitsmining.com page 12
SUMMARY OF EXPENDITURE
Summary of expenditure on substantive exploration, development and production activities during the quarter ended 30
June 2026:
• Approximately $11.1M for Qala Shallows surface infrastructure, underground mine development (including 1
West Decline), operations and maintenance.
• Approximately $2.8M for plant and equipment, including the new 10-tonne LHD, Jumbo drill rig and associated
underground fleet additions.
Related Party Payments
• $185k for director fees, salaries and related costs paid to Messrs Quinert, Deysel, Grigor and Middleton.
• $53k QR Lawyers Pty Ltd & Brickwick Pty Ltd, related entities of Mr Quinert, for office rent, company secretarial
and legal services.
INTERESTS IN MINING TENEMENTS
Tenements Location Held