Quarterly Activities and Cashflow Report
Released
Released
Announcement PDF
ASX Announcement and Media Release
Friday, 30 October 2015
Fast Facts
Capital Structure
Shares on issue
Options
Market Cap
Cash in Bank
Debt
Enterprise Value (EV)
*Assumes completion of
current placement
@ 30 Oct 2015
456 million *
62.15 million
A$13.95 million*
A$2.0million*
Nil
A$13.95million*
Quarterly Activities Report
Review of Operations
West Wits Mining Limited (ASX:WWI) (“the Company” or “West Wits”) experienced
its best quarter for a number of years with meaningful progress made at both its
Derewo River Gold Project, Papua Province, Indonesia (“Derewo”) and its Soweto
Company Directors & Management
Michael Quinert
Chairman
Vin Savage
Executive Director
Neil Pretorius
Non-Exec Director
Hulme Scholes
Non-Exec Director
Top Shareholders ≈
Twynam Ag
DRD Gold Ltd
QMM Pty Ltd
Trevor Neale
Top 40 Shareholders
ASX: WWI
www.westwitsmining.com
Cluster Gold Project, Johannesburg, South Africa (“Soweto Cluster”).
Indonesia
Alluvial Gold Project, Papua Province (WWI:50%)
19.9%
11%
8%
6%
74%
Post the quarter end, West Wits announced that its Indonesian subsidiary PT.
Madinah Qurrata’ain (“PTMQ”) had commenced operations at Derewo. This was a
significant step forward for the Company and something that it has been striving to
Company Highlights
• Indonesia
o
High grade placer deposit
o
Project show early stage
similarities with discoveries inc;
Porgera, Edie Creek, Wau
o
Independent geologists believe
source of nuggets likely to be local,
based on the size and shape of the
nuggets discovered
achieve for some time. Whilst challenges remain, including the removal of the illegal
mining population, the Company has been able to conduct operations to date
without interference.
Construction of the alluvial circuit is progressing as planned. Following the temporary
diversion of the 81 Creek the sluice boxes are now being set up and adjusted for
optimal performance. The Company will shortly commence test runs of material over
the sluice boxes in preparation for the gradual commissioning of the circuit.
Commissioning of the alluvial circuit will be staged, with full operation of this first
circuit planned to be achieved within 4 to 6 weeks.
The commencement of operations has been made possible as a result of extensive
•
South Africa
o
near surface and underground
targets
o
1-2.2m oz Exploration Target down
to 400m
o
Historic estimate of 12.8m oz at
4.6g/t
o
31.8m ozs Au produced historically
work and negotiations undertaken with local and regional authorities by the
Company’s new partner for the Indonesian venture PT Intan Angkasa Aviation
(“PTIA”). In particular, PTIA’s representatives, led by retired Chief Police Inspector,
General of Police for Indonesia Rudiard M.L. Tampubolon, have provided the
leadership and experience necessary to successfully navigate a pathway to the
Contact Details
West Wits Mining Limited
ACN 124 894 060
Suite 1, 1233 High Street
Armadale VIC 3143
T: +61 3 8692 9049
F: +61 3 8692 9040
E: info@westwitsmining.com
W: www.westwitsmining.com
commencement of operations.
West Wits is confident of commissioning the alluvial circuit during the current
quarter and will provide further updates as work progresses.
Whilst operations have proceeded thus far without interruption an artisanal mining population is still present at site.
Their presence continues to constitute a risk to operations. The Company is confident that the ultimate removal of the
artisanal miners can be achieved within the next few months.
Exploration Project, Papua Province (WWI:80%)
Exploration plans continue to be held in abeyance pending commissioning of the alluvial circuit. On establishment of an
alluvial circuit and generation of cashflow, management will reassess its initial exploration programs which were designed
the previous year with a view to recommencing that project.
Figure 1. Highlight of demagnetised target zones
The program(s) were designed to evaluate Wopogi and Sena which are highlighted in Figure 1 and present as demagnetised zones. It is envisaged an initial sampling program of approx. 300-500 samples would be implemented to
confirm the anomalism established through the Freeport datasets in the Wopogi area and to map the basic geological
units and alteration types encountered.
South Africa
Soweto Cluster Gold Project, Central Rand (WWI: 76%)
As part of a technical review of the historical data completed by West Wits, the Company released a 12.8 million oz Au
historic estimate to the ASX which was estimated by the previous lease holder DRD Gold Limited.
Category
Tonnes Millions
Grade g/t
Ounces Au
Measured
27.1
5.03
4,380,000
Indicated
29.4
3.88
3,670,000
Inferred
31.4
4.72
4,770,000
Total
87.9
4.6
12,820,000
Table 1. Historical Mineral Estimate for the Company’s Soweto Cluster Project (ASX: 28/8/15). The supporting material
concerning the above historical estimate provided in the announcement of 28 August 2015 continues to apply and has
not materially changed. The historical estimate is not reported in accordance with the JORC Code (2012). At this point a
Competent Person has not done sufficient work to classify this historical estimate under the JORC Code (2012).
Based on that historic estimate, West Wits formulated and released, on 22 September 2015, a new Exploration Target
under JORC 2012 which was based on specific targets which formed part of the historical estimate. The Exploration Target
includes only the top 400m below surface which is considered potentially viable for exploitation from open pit and or
shallow underground mining. The Exploration Target range established was
Consolidated Exploration Target for the Soweto Cluster
Category
Tonnes Millions
Grade g/t
Ounces Au
Low range
9
3.5
1,000,000
Upper Range
15
4.5
2,200,000
Table 2: The consolidated Exploration Target is stated above as ranges of potential tonnes and grades. Number
differences may occur due to rounding errors. The potential quantity and grade is conceptual in nature, there has been
insufficient exploration and evaluation of historical information to estimate a Mineral Resource. It is uncertain if further
exploration will result in the estimation of a Mineral Resource.
The delineation of these targets will define the Company’s next exploration programs which are being designed to
enhance the geological understanding and potentially upgrade this Exploration Target into higher categories under the
JORC code. The first of these projects is known as the ‘Number 11 Shaft Project’, which is located on the “Bird Reef”.
Number 11 Shaft Project
The Number 11 Shaft Project is a significant unmined portion of the Bird Reef that is centred around the existing
underground infrastructure of a disused shaft on the old Rand Leases area at the Eastern portion of the Soweto Cluster.
This opportunity is approx. 800m in strike length and focusses on where the Bird Reef outcrops at surface. This target
was left unmined as a crown pillar to accommodate significant surface infrastructure that was present at the time but
has since been removed or made redundant. The Number 11 Shaft was closed at the end of 1998 (DRD Annual Report
1999) and no further production has taken place from this shaft.
No. 11 Shaft
Figure 2. Location main auriferous lodes within the Soweto Cluster. The white boundary marks the extent of the WWI
tenements in the area. The approximate location of the Number 11 Shaft is also shown by the yellow star.
A detailed evaluation of historical underground mining and sampling plans from the production history along the Bird
Reef in this area has resulted in the formulation of an Exploration Target for ore remaining in the Number 11 Shaft pillar.
The evaluation took into consideration underground and surface areas that have been previously mined as well as a
database which included approx. 6000 samples of the Bird Reef taken from underground production headings, stopes
and open pits as well as reconciled mined tonnes and grade versus actual gold production from the Bird Reef.
Exploration Target for the Number 11 Shaft Project
Category
Tonnes Thousands
Grade g/t
Ounces Au
Low range
600
4.5
85,000
Upper Range
700
6.0
140,000
Table 3: The Exploration Target is stated as ranges of potential tonnes and grades. Number differences may occur due to
rounding errors. The potential quantity and grade is conceptual in nature, there has been insufficient exploration and
evaluation of historical information to estimate a Mineral Resource. It is uncertain if further exploration will result in the
estimation of a Mineral Resource.
Potential Open Pit
Potential Underground
Figure 3. Two plan views of the Bird Reef sample data projected to surface. The Bird Reef in this area dips approximately
30 degrees to the southwest. The sample data are from surface and underground workings on the Bird Reef collected by
DRD during mining. The plan on the left shows sample points coloured by gold grades and illustrates the intensive level of
sampling undertaken along development drives and in stopes. The plot on the right is a contour map of the sample
grades and clearly illustrates the linear nature of the “pay shoots” (higher grade areas = reds and yellows) within the Bird
reef and also shows the area immediately beneath the unmined crown pillar as higher grade and as a potential “pay
shoot” zone extending into the crown pillar. Also shown on both maps are the approximate areas for the estimation of
the Exploration Target including the potential open pit zone in purple and potential underground zone in red.
The next phase of work on the Number 11 Shaft Project will involve three important phases the first two of which can be
run in parallel
1. Validation of historical data
a. QAQC database involving comparisons between electronic data and hardcopy data which program is due
to commence shortly
b. QAQC of sampling data documenting laboratory methods and performance of standards and blanks
c. Examination of mine to mill reconciliation factors
2. Collection of new geological data
a. Trenching across strike to accurately identify position of Bird Reef at surface
b. Trenching along the outcrop of Bird reef to collect samples for gold assay
c. Drilling to intersect Bird Reef approximately mid-way between surface and underground development.
The drill program involves approximately 14 angled holes for a total program of approximately 500m. This
program is scheduled to commence within the next week.
3. Estimation of Resources in compliance with the JORC Code of 2012. At this stage there has been insufficient
exploration and evaluation of historical data and estimates to estimate a Mineral Resource. It is uncertain if
further exploration will result in the estimation of a Mineral Resource.
Corporate
Towards the end of the quarter the Company announced a 1 for 4 rights issue at 1.4 cents per share to raise
approximately $1m. The re-emergence of the Company’s Soweto Cluster asset as a promising project generated strong
interest in the market. This support encouraged Far East Capital Limited to fully underwrite the issue. Post quarter end
the board resolved to capitalise on strong market interest by undertaking a placement to raise a further approximately
$1m through an issue of shares at 1.8 cents each. The placement was undertaken again by Far East Capital Limited which
provided a firm commitment to place the stock. The Placement has been strongly supported. These capital raisings are
currently in the process of completing and will deliver approximately $2m in net funds. These funds will enable the
Company to accelerate its project developments in both Indonesia and South Africa.
For And On Behalf Of The Board
Michael Quinert
Chairman
West Wits Mining Limited
Interests in Mining Tenements
Tenements
GP183PR
Location
Held at end of
Acquired during the
Disposed during the
Quarter
quarter
quarter
76%*
-
-
Paniai Regency, Indonesia
50%*
-
-
Paniai , Indonesia
80%*
-
-
Intan Jaya, Indonesia
80%*
-
-
Nabire, Indonesia
80%*
-
-
Underground rights - Soweto Cluster, West
Rand, South Africa **
Production IUP – NO.
47/2010
Exploration IUP – NO.
76/2010
Exploration IUP –
NO.31/2010
Exploration IUP – NO.
543/142/SET
*Minority positions are held by local parties in compliance with local legislation in relation to foreign ownership and
mineral and production rights.
** Rights are subject to an appeal for reinstatement
Competent Person Statement
The review of the Geological data and historical estimates was undertaken by Dr. Andrew Tunks and represents an
accurate representation of the available data. Dr. Tunks (Member Australian Institute Geoscientists) is a consultant to
the Company and has sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the
‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Dr Tunks consents to the
inclusion in the report of the matters based on his information in the form and context in which it appears.’
Dr Andrew J. Tunks MAIG
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Rule 5.5
Appendix 5B
Mining exploration entity and oil and gas exploration entity
quarterly report
Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013
Name of entity
WEST WITS MINING LIMITED (ASX: WWI)
ABN
Quarter ended (“current quarter”)
89 124 894 060
30 September 2015
Consolidated statement of cash flows
Cash flows related to operating activities
1.1
Receipts from product sales and related debtors
1.2
Payments for
1.3
1.4
Dividends received
Interest and other items of a similar nature
received
Interest and other costs of finance paid
Income taxes paid
Other (provide details if material)
1.5
1.6
1.7
(a) exploration & evaluation
(b) development
(c) production
(d) administration
Net Operating Cash Flows
1.8
1.9
1.10
1.11
1.12
1.13
Cash flows related to investing activities
Payment for purchases of: (a) prospects
(b) equity investments
(c) other fixed assets
Proceeds from sale of:
(a) prospects
(b) equity investments
(c) other fixed assets
Loans to other entities
Loans repaid by other entities
Prospect sale proceeds to BEE partner
Net investing cash flows
Total operating and investing cash flows
(carried forward)
+ See chapter 19 for defined terms.
01/05/2013 Appendix 5B Page 1 of 6
Current quarter
$A’000
Year to date
(3 months)
$A’000
-
-
(136)
(109)
(136)
(109)
-
-
-
-
-
-
(245)
(245)
-
-
(245)
(245)
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Current quarter
$A’000
1.13
1.14
1.15
1.16
1.17
1.18
1.19
Total operating and investing cash flows
(brought forward)
Cash flows related to financing activities
Proceeds from issues of shares, options, etc.
Proceeds from sale of forfeited shares
Proceeds from borrowings
Repayment of borrowings
Dividends paid
Other (provide details if material)
Net financing cash flows
(245)
Year to date
(3 months)
$A’000
(245)
82
82
82
82
(163)
(163)
345
(3)
179
345
(3)
179
Net increase (decrease) in cash held
1.20
1.21
Cash at beginning of quarter/year to date
Exchange rate adjustments to item 1.20
1.22
Cash at end of quarter
Payments to directors of the entity, associates of the directors, related
entities of the entity and associates of the related entities
Current quarter
$A'000
1.23
Aggregate amount of payments to the parties included in item 1.2
32
1.24
Aggregate amount of loans to the parties included in item 1.10
-
1.25
Explanation necessary for an understanding of the transactions
Salaries, directors’ fees, corporate advisory and consulting fees at normal commercial rates
Non-cash financing and investing activities
2.1
Details of financing and investing transactions which have had a material effect on consolidated
assets and liabilities but did not involve cash flows
2.2
Details of outlays made by other entities to establish or increase their share in projects in which the
reporting entity has an interest
+ See chapter 19 for defined terms.
Appendix 5B Page 2 of 6
01/05/2013
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Financing facilities available
Add notes as necessary for an understanding of the position.
3.1
Loan facilities
3.2
Credit standby arrangements
Amount available
$A’000
Amount used
$A’000
-
-
-
-
Estimated cash outflows for next quarter
$A’000
4.1
Exploration and evaluation
4.2
Development
4.3
Production
4.4
Administration
150
100
150
400
Total
Reconciliation of cash
Reconciliation of cash at the end of the quarter (as shown
in the consolidated statement of cash flows) to the related
items in the accounts is as follows.
Current quarter
$A’000
Previous quarter
$A’000
5.1
Cash on hand and at bank
179
345
5.2
Deposits at call
-
-
5.3
Bank overdraft
-
-
5.4
Other (provide details)
-
-
Total: cash at end of quarter (item 1.22)
179
345
+ See chapter 19 for defined terms.
01/05/2013 Appendix 5B Page 3 of 6
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Changes in interests in mining tenements and petroleum tenements
Tenement
reference
and
location
6.1
6.2
Interests in mining
tenements and petroleum
tenements relinquished,
reduced or lapsed
Interests in mining
tenements and petroleum
tenements acquired or
increased
Nature of interest
(note (2))
Interest at
beginning
of quarter
Interest at
end of
quarter
Nil
Nil
+ See chapter 19 for defined terms.
Appendix 5B Page 4 of 6
01/05/2013
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Issued and quoted securities at end of current quarter
Description includes rate of interest and any redemption or conversion rights together with prices and dates.
Total number
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
7.11
7.12
Preference
+securities
(description)
Changes during
quarter
(a) Increases
through issues
(b) Decreases
through returns
of capital, buybacks,
redemptions
+Ordinary
securities
Changes during
quarter
(a) Increases
through issues
(b) Decreases
through returns
of capital, buybacks
+Convertible
debt securities
(description)
Changes during
quarter
(a) Increases
through issues
(b) Decreases
through
securities
matured,
converted
Options
(description and
conversion
factor)
Issued during
quarter
Exercised during
quarter
Expired during
quarter
Debentures
(totals only)
Unsecured
notes (totals
only)
Number
quoted
Issue price per security
(see note 3) (cents)
Amount paid up per
security (see note 3)
(cents)
-
-
-
-
-
-
-
-
-
-
-
-
316,962,696
316,962,696
-
-
-
-
-
-
-
-
-
-
-
-
-
-
60,150,000
-
Exercisable @ $0.025 to
$0.030
-
+ See chapter 19 for defined terms.
01/05/2013 Appendix 5B Page 5 of 6
-
-
-
-
-
-
-
-
-
-
-
-
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Compliance statement
1
This statement has been prepared under accounting policies which comply with
accounting standards as defined in the Corporations Act or other standards acceptable
to ASX (see note 5).
2
This statement does give a true and fair view of the matters disclosed.
Date: Friday, 30th October 2015
Sign here:
(Director)
Print name:
Michael Quinert
Notes
1
The quarterly report provides a basis for informing the market how the entity’s
activities have been financed for the past quarter and the effect on its cash position.
An entity wanting to disclose additional information is encouraged to do so, in a note
or notes attached to this report.
2
The “Nature of interest” (items 6.1 and 6.2) includes options in respect of interests in
mining tenements and petroleum tenements acquired, exercised or lapsed during the
reporting period. If the entity is involved in a joint venture agreement and there are
conditions precedent which will change its percentage interest in a mining tenement
or petroleum tenement, it should disclose the change of percentage interest and
conditions precedent in the list required for items 6.1 and 6.2.
3
Issued and quoted securities The issue price and amount paid up is not required in
items 7.1 and 7.3 for fully paid securities.
4
The definitions in, and provisions of, AASB 6: Exploration for and Evaluation of
Mineral Resources and AASB 107: Statement of Cash Flows apply to this report.
5
Accounting Standards ASX will accept, for example, the use of International
Financial Reporting Standards for foreign entities. If the standards used do not
address a topic, the Australian standard on that topic (if any) must be complied with.
== == == == ==
+ See chapter 19 for defined terms.
Appendix 5B Page 6 of 6
01/05/2013
Share your feedback
Discover