WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27 October 2026
westwitsmining.com | ir@westwitsmining.com page 1
Quarterly Activity Report
Reporting Period 1 July – 30 September 2026
HIGHLIGHTS
Qala Shallows Operations
o Development Rates Almost Tripled: monthly underground advance increased from 73m (July) to 183m
(August) and a record 200m (September), 456m for the quarter (Project to date: 1,150), driven by
increased face availability, improved ground and increased fleet. Development rates are expected to
continue accelerating through 2027 to support the production ramp-up.
o Surface Infrastructure 61% Complete (up from 45% at 30 June 2026): haulage road 100% complete and
handed over; pollution control dam and permanent ore handling facility at advanced stages – on track for
completion of critical surface infrastructure in Q3 2027.
o Early Gold Production: 112oz of gold recovered in the quarter (June 2026 quarter: 227oz) from on-reef
development ore toll-treated at Sibanye-Stillwater’s Ezulwini plant.
o Clear Pathway to Primary Production: historic 2 Level stoping areas, accessed via the 1 West Decline
breakthrough, are being developed for trackless equipment, with stoping scheduled to commence from
February 2027 – the transition from development ore to primary production.
o Workforce Scaling: site workforce of 507 people at 30 September 2026 (431 at 30 June 2026), building
the surface infrastructure and operating capacity required for ramp-up towards ~1,100 personnel at
steady state.
o Safety Culture: CEO Safety Day held in August with the workforce signing the Company’s Zero Harm
Pledge.
o Key project milestone schedule on track:
o Q3 2027: completion of critical surface infrastructure
o Q4 2027: commercial production
o Q1 2029: 70,000oz p.a. steady-state production rate2
o Qala Shallows Production Outlook:
o 2027: 10,000oz – 15,000oz
o 2028: 42,500oz2
o 2029: 70,000oz2
Corporate
o Second Senior Debt Drawdown – Project Fully Funded to Steady State: passed the lenders’ independent
cost-to-complete test and other conditions precedents for the second drawdown. Subsequent to period
end, a second drawdown of R236M (~A$21M) under the R875M (~A$76M) Senior Loan Facility with Absa
and Nedbank CIB was received – total drawdowns of R575M (~A$50M), with R300M (~A$26M) remaining
available under the facility.
o Cash Position: cash and cash equivalents of A$17.1M at 30 September 2026, increasing to ~A$36M at 7
October 2026 following receipt of the second drawdown.
o Investor Engagement: new corporate website and InvestorHub shareholder platform launched; CEO
presented at Africa Down Under (Perth) and the Company participated in FCR Resources Day (Hong Kong).
Engage with this announcement via Investor Hub https://westwitsmining.com/
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27 October 2026
westwitsmining.com | ir@westwitsmining.com page 2
CEO and Managing Director, Rudi Deysel:
“The September quarter was about building momentum on the three drivers of production at Qala
Shallows: underground access, surface infrastructure and funding. Our monthly development rate almost
tripled from July to a record 200 metres in September, surface infrastructure is now 61% complete, and the
project remains fully funded to steady-state production with the second senior debt drawdown received
after quarter end following the lenders’ independent cost-to-complete test.
The 2 Level stoping areas opened up by the 1 West Decline breakthrough give us a direct pathway from
development ore to primary production, with stoping scheduled from February 2027. Our milestone
schedule is clear: critical surface infrastructure in Q3 2027, commercial production in Q4 2027 and a steady-
state production rate of 70,000 ounces per annum2
in Q1 2029.
Safety remains our first priority with the CEO Safety Day providing me the opportunity to highlight the
Company wide drive to embed safe operations with the Company’s “Zero Harm Pledge” as we approach
the South African mining industry’s family season.”
IMAGE 1: AERIAL VIEW OF QALA SHALLOWS SHOWING THE DECLINE PORTAL, WORKSHOP, SITE OFFICES AND SURFACE
INFRASTRUCTURE WORKS
OPERATIONS AND PROJECT DEVELOPMENT
WITWATERSRAND BASIN PROJECT (“WBP”), GAUTENG, SOUTH AFRICA
West Wits Mining Limited (ASX: WWI; OTCQB: WMWWF) (“West Wits”, “WWI” or “the Company”) is
advancing Qala Shallows from development ore towards primary production from stoping, with the project
remaining fully funded to steady-state production of approximately 70,000oz per annum2
. The September
2026 quarter was defined by accelerating underground development, substantial progress on surface
infrastructure and the deployment of the Company’s senior debt funding.
Underground Development – Advance Rates Building Month on Month
Underground development reached 1,150m at 30 September 2026, comprising 513m of on-reef development
and 637m of waste development. Monthly advance rates increased progressively through the quarter:
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27 October 2026
westwitsmining.com | ir@westwitsmining.com page 3
TABLE 1: MONTHLY UNDERGROUND DEVELOPMENT ADVANCE – SEPTEMBER 2026 QUARTER
Month Advance (m)
July 2026 73
August 2026 183
September 2026 200
Cumulative to 30 Sep 2026 1,150
Increased face availability, ground conditions and the expanding underground fleet drove the improvement.
Following completion of support installation in the weathered zone near surface during the June quarter, the
Main Decline entered more competent ground from July 2026, requiring standard roof bolting only with
reduced shotcrete requirements, enabling higher advance rates.
Development metres are the leading indicator of future ore production. Development opens up the mining
faces and ore tonnes that feed future production; the near-tripling of monthly advance during the quarter is
building the capacity required for ~840,000t per annum of ore2
at steady state. Development rates are
expected to continue to accelerate through 2027 to support the production ramp-up.
IMAGE 2: DEVELOPMENT DRILLING AND SURVEY AT AN UNDERGROUND FACE AT QALA SHALLOWS
2 Level – The Pathway from Development Ore to Primary Production
The 1 West Decline holed into the historic 2 Level area on 21 May 2026, providing access to ore tonnes in
unmined stopes with established underground infrastructure. During the quarter, this area continued to be
developed for modern trackless equipment, including vamping and slyping operations to enable access for the
undergound equipment mine the stopes.
Gold produced during the quarter continued to be sourced via the on-reef development ore and toll-treated
at Sibanye-Stillwater’s Ezulwini plant. The Company recovered 112oz during for the reporting period (June
2026 quarter: 227oz).
Primary production from stoping is scheduled to commence from February 2027. As expected at this stage of
development, gold produced to date has come from processing ore generated by on-reef development – a by-
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27 October 2026
westwitsmining.com | ir@westwitsmining.com page 4
product of establishing the mine rather than its primary production source. Processing of on-reef development
ore will continue through 2026.
Surface Infrastructure and Power
The surface infrastructure program under the EPCM contractor reached 61% completion at 30 September
2026 (45% at 30 June 2026) and remains on track for completion of critical surface infrastructure in Q3 2027.
Key works advanced during the quarter include:
• Haulage road construction 100% complete and handed over.
• Pollution control dam and permanent ore handling facility – both key to environmental compliance –
at an advanced stage.
• Potable water infrastructure installation progressing, including connection to mains water supply.
• 2.5MW permanent backup generators commissioned in October 2026.
• Bulk power connection planned for commissioning in early 2027. On grid connection, the Company
expects a material reduction in diesel consumption, with generators transitioning to a backup role –
reducing operating costs and exposure to fuel price volatility.
West Wits continues to maintain additional on-site fuel storage capacity, high minimum stock levels and diesel
fuel supply contracts with allocations from diversified bulk fuel suppliers to mitigate risk relating to fule supply.
The Company confirms that fuel supply arrangements are sufficient to support planned mining and
development activities at Qala Shallows with no impact expected on current production plans from current
world fuel supply issues.
IMAGE 3: ACCESS ROADS AND POLLUTION CONTROL DAM UNDER CONSTRUCTION
People and Safety
The site workforce grew to 507 people at 30 September 2026, up from 431 at 30 June 2026 and more than
ten-fold from 45 at 31 May 2025. The Company remains on track towards a total labour requirement of
approximately 1,100 personnel at steady-state operations.
Following the mud rush incident at Qala Shallows on 10 June 2026, in which a colleague lost his life, the
Company again extends its deepest condolences to his family, friends and colleagues. The Department of
Mineral and Petroleum Resources (“DMPR”) completed its formal investigation, lifted all operational
restrictions and made no adverse findings against West Wits.
Ground and water management has since been a central focus underground. Head of Operations Sephela
Makete Thema (Pr Eng) represented West Wits at the Minerals Council South Africa’s Mud Rush Day of
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27 October 2026
westwitsmining.com | ir@westwitsmining.com page 5
Learning, which brought together mining companies, organised labour, regulators, researchers and technical
specialists to share practical approaches to preventing mud rush incidents.
Executive Director and Head of Corporate Affairs Tozama Kulati Siwisa and Head of Operations Sephela
Makete Thema also represented West Wits at the 2026 Mine Health and Safety Tripartite Summit. Held under
the theme “Accelerating Innovation, Inclusion and Accountability Towards the Achievement of Zero Harm”,
the Summit brought Government, employers and organised labour together to address the sector’s critical
health and safety matters and review progress towards shared milestones, with a common goal of every
mineworker returning home unharmed, every day.
The Company’s CEO Safety Day in August 2026 brought together employees, contractors, and representatives
of the National Union of Mineworkers (“NUM”), and the workforce signed the Company’s Zero Harm Pledge.
Subsequent to quarter end, an ongoing Family Season Safety Campaign is being rolled out and attended by
representatives of both the NUM and the DMPR.
IMAGE 4: CEO SAFETY DAY – WEST WITS WORKFORCE SIGNED THE ZERO HARM PLEDGE
Sustainability and Community Partnerships
West Wits continues to support local enterprise and employment alongside the development of Qala Shallows,
including local SMMEs and community vendors across catering, logistics and site services, and learnerships
and local hiring that build workforce capability within host communities.
Qala Shallows Project Outlook
On 7 October 2026, the Company released its Qala Shallows Project Update, confirming receipt of the second
senior debt drawdown and set out its key project milestones and production outlook:
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27 October 2026
westwitsmining.com | ir@westwitsmining.com page 6
TABLE 2: QALA SHALLOWS KEY PROJECT MILESTONES
Timing Milestone Significance
February 2027 Stoping commences Primary production from 2 Level
Q3 2027 Critical surface infrastructure complete Support steady-state production rates
Q4 2027 Commercial production Transition to free cashflow from operation
Q1 2029 Steady-state production rate2
70,000oz p.a. from ~840ktpa ore2
Annual recovered gold production is forecast to ramp up from 10,000oz–15,000oz in 2027 to 42,500oz in 20282
and 70,000oz in 20292
, as primary production from stoping commences from February 2027. Near-term
output reflects the project’s development stage; the progressive step-up in production is tied to the start of
stoping, completion of surface infrastructure and underground development accessing additional levels.
Mineral Resource Estimate and Growth Projects
WBP Mineral Resource Estimate — 7.24Moz @ 4.0g/t Au1
The Company’s Global JORC Mineral Resource Estimate for the WBP, announced on 2 February 2026, remains
at 7.24Moz @ 4.0g/t Au1
, hosted across the Kimberley Reef, Bird Reef and Main Reef horizons.
TABLE 3: WBP GLOBAL JORC MINERAL RESOURCE ESTIMATE AS AT 1 FEBRUARY 2026¹
Category Tonnes (M) Grade (g/t Au) Ounces Au Cut-off
Measured 14.08 4.40 1,991,000 Various
Indicated 15.55 4.04 2,020,000 Various
Measured & Indicated 29.63 4.21 4,012,000
Inferred 26.81 3.75 3,232,000
Total 56.44 4.00 7,244,000
Notes: Mineral Resources are reported in accordance with the JORC Code (2012 Edition). The MRE is reported at a blended cut-off of 2.0g/t Au
for Bird Reef and Main Reef areas and 1.24g/t Au for Kimberley Reef areas. Mineral Resources are reported as inclusive of Ore Reserves.
Project 200 Scoping Study
On 27 August 2026, West Wits advised that the Project 200 Scoping Study (“Scoping Study”) was completed
on a 35-year life-of-mine model for the WBP, incorporating Qala Shallows and the Company's broader tenure
within the Witwatersrand Basin. Inferred Mineral Resources averaged 74% across the full life-of-mine, with
certain years exceeding 90%.
The Company views the results as positive and as meeting its internal objectives, which were predominantly
to enable a decision on the merits of progressing Project 200 into the pre-feasibility stage. Following
consultation with ASX, the Company concluded that releasing the Scoping Study as completed would not meet
ASX requirements given the proportion of Inferred Mineral Resources used in the production target and the
financial information derived from it.
The Company is continuing to progress Project 200 and the development of the WBP through to the next level
of studies, including work to convert more Inferred Mineral Resources into higher-confidence categories. The
Company is reviewing the Scoping Study with the aim of increasing the proportion of Measured and Indicated
Mineral Resources in the production target, with a view to providing further disclosures to the market as
appropriate.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27 October 2026
westwitsmining.com | ir@westwitsmining.com page 7
Bird Reef Central (“BRC”) Uranium-Gold Opportunity
BRC is a standalone uranium and gold opportunity within the Company’s Witwatersrand Basin Project (“WBP”)
Mining Right area, approximately 4km north-west of the Company’s Qala Shallows operating gold mine. BRC
targets uranium and gold in closely spaced reef horizons of the Bird Reef package: the White Reef, historically
the focus for gold, and the overlying Monarch Reefs, which host the uranium mineralisation.
FIGURE 1: LOCATION OF BRC WITHIN THE WBP MINING RIGHT, RELATIVE TO QALA SHALLOWS
The BRC area has a declared JORC (2012) gold MRE of 1.38 Mt at 2.66g/t Au for 117,600oz Au3
. Approximately
65% of the contained ounces are already classified as Measured or Indicated, providing a solid base from which
Stage 2 infill drilling aims to lift confidence further.
TABLE 4: JORC (2012) MRE FOR BIRD REEF CENTRAL AT 2.0G/T Au CUT-OFF3
BRC Gold Mineral Resource Estimate
Category Tonnes (M) Grade (g/t Au) Ounces
Measured 0.04 3.73 4,500
Indicated 0.89 2.51 72,200
Inferred 0.44 2.86 40,900
Total 1.38 2.66 117,600
Notes: The MRE set at a 2.0 g/t Au cut-off. Reported in accordance the JORC Code of 2012. Number differences may occur due to
rounding errors.
During the reporting period, the Company tendered the scope for a 17-hole diamond drill program, totalling
5,750m along an approximate 4km strike. The contract adjudication occurred post period and, as announced
on 25/10/2026, is scheduled to mobilise the first drill rig and commence drilling by the end of November 2026.
The 17-hole program is planned in three stages, each with its own purpose, so that results can be reported
and acted on as each stage is completed (Table 5).
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27 October 2026
westwitsmining.com | ir@westwitsmining.com page 8
TABLE 5: STAGED DRILLING PLAN
Stage Purpose Holes / metres Indicative Timing
1. Resource
drilling
Undertake drilling and evaluation of the
uranium mineralisation with the objective of
providing sufficient data to assess whether a
maiden Uranium Mineral Resource can be
estimated.
7 holes / 2,100m From late Nov-26;
3 months
2. Infill drilling Close hole spacing of 250m by 250m to
improve the MRE confidence level, which
could underpin a feasibility study to assess a
potential standalone Uranium / Gold Project
at the BRC.
8 holes / 2,900 m From Jan-27;
3 months
3. Strike
extension
Test the Bird Reef beyond the Exploration
Target area to the east to assess an extension
of the mineralisation
2 holes / 750 m From Feb-27;
3 months
Total 17 holes / 5,750 m 6 months
The BRC Project offers shareholders potential exposure to uranium alongside gold, leveraging the Company’s
existing geological knowledge, infrastructure and Mining Right position. The Company will provide an update
to the market with results of the exploration program when available.
FINANCIAL POSITION AND FUNDING
Cash at 30 September 2026 was A$17.1M (30 June 2026: ~A$32M). Following receipt of the second senior
debt drawdown, the Company held cash of approximately A$36M at 7 October 2026.
On 1 July 2026, West Wits announced Financial Close of its R875M (~A$76M) Senior Loan Facility (“SA Senior
Loan”) with Absa Bank Limited and Nedbank CIB Limited (acting through its Nedbank Corporate and
Investment Banking division) (“Nedbank CIB”), together with the first drawdown of R339M (~A$30M) received
on 30 June 2026.
The SA Senior Loan fully funds Qala Shallows through to steady-state production of 70,000oz per annum, as
outlined in the 2025 DFS (post-tax NPV7.5 US$500M, IRR 81% at a gold price of US$2,850/oz)2
. The first
drawdown activated the deployment of senior debt into the local subsidiary, West Wits MLI (Pty) Ltd,
accelerating the EPCM surface infrastructure program, plant and equipment expansion, 2 Level development
and the Main Decline advance.
The Company completed the conditions precedent – including cost-to-complete and covenant testing – for
the second drawdown of R236M (~A$21M) which was received shortly after the reporting period. Drawdowns
now total R575M (~A$50M), leaving R300M (~A$26M) available under the facility.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27 October 2026
westwitsmining.com | ir@westwitsmining.com page 9
IMAGE 5: LENDER REPRESENTATIVES INSPECTING UNDERGROUND DEVELOPMENT AT QALA SHALLOWS, SEPTEMBER 2026
TABLE 6: PROJECT FUNDING PACKAGE AND AVAILABILITY (AS AT 7 OCTOBER 2026)
Facility Total (ZAR) Drawn (ZAR) Purpose
Senior Loan Facility R875M R575M
Project development, ramp-up &
production at Qala Shallows
Working Capital Facility R150M Undrawn
Fund working capital cycle during
production ramp up
Cost Overrun Debt Facility R90M Undrawn Contingency funding for cost overruns
Cost Overrun Equity Reserve R57M
Cash Held by
Company
Equity-funded contingency
TOTAL DEBT FACILITIES R1,115M R575M
CORPORATE ACTIVITY
Divestment of Mt Cecelia Project
As announced on 29 April 2026, West Wits agreed to divest its Mt Cecelia Project in Western Australia to
Aventine Resources Limited (“Aventine”) for $2.0 million in Aventine equity, a 1% Net Smelter Royalty and up
to $1.0 million in deferred milestone consideration. The divestment remains subject to completion of
conditions precedent, including Aventine’s ASX listing.
Investor Engagement
West Wits continued to broaden awareness of its production growth story among institutional and retail
investors during the quarter:
• Africa Down Under, Perth (September 2026): CEO and Managing Director Rudi Deysel presented an
update on progress at Qala Shallows to investors and industry stakeholders.
• FCR Resources Day, Hong Kong (September 2026): the Company met with investors as part of its Hong
Kong roadshow.
• New corporate website and Investor Hub: launched in September 2026, giving shareholders real-time
announcement alerts, a Q&A function to engage directly with the Board and management, on-demand
access to webinars and presentations, and centralised Company information.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27 October 2026
westwitsmining.com | ir@westwitsmining.com page 10
Subsequent to quarter end, the Company presented at the Australian Gold Conference in Sydney (13–15
October 2026). Upcoming engagement includes investor briefings in Zurich and Geneva (week of 16 November
2026) and 121 Mining Investment London (23–24 November 2026).
IMAGE 6: WEST WITS CFO, SIMON WHYTE, CHAIRMAN, MICHAEL QUINERT, AND CEO AND MANAGING DIRECTOR RUDI
DEYSEL AT AFRICA DOWN UNDER, PERTH 2026
Approved for release by the Board of West Wits Mining Limited.
For Investor Relations contact:
Jessica Fertig, Investor Relations — ir@westwitsmining.com
General:
info@westwitsmining.com
westwitsmining.com
ABOUT WEST WITS MINING LIMITED
West Wits Mining Limited (ASX: WWI) (OTCQB: WMWWF) is focused on the exploration, development and production
of high-value precious and base metals for the benefit of shareholders, communities and environments in which it
operates. Witwatersrand Basin Project, located in the proven gold region of Central Rand Goldfield of South Africa, hosts
a 7.24Moz JORC Mineral Resource at 4.0g/t Au1
. The Witwatersrand Basin is a largely underground geological formation
which surfaces in the Witwatersrand. It is the world’s most prolific gold basin, having produced over 1.5 billion ounces
(over 40,000 metric tons), representing about 22% of all the gold accounted for above the surface.
WEST WITS MINING LIMITED | ASX: WWI | OTCQB: WMWWF ASX Announcement and Media Release | 27 October 2026
westwitsmining.com | ir@westwitsmining.com page 11
1. The original report was “2.2Moz Increase to WBP Global Resource Estimate to 7.24Moz” which was issued with consent of the Competent
Person, Mr Hermanus Berhardus Swart. The report was released to the ASX on 02 February 2026 and can be found on the Company’s website
(https://westwitsmining.com/). Comprising 14.08MT at 4.40g/t for 1.99Moz Measured, 15.55MT at 4.04g/t for 2.02Moz Indicated and 26.81MT
at 3.75g/t for 3.23Moz Inferred. The Company is not aware of any new information or data that materially effects the information included in
the relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The form and
context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
2. The original report was “Updates to Qala Shallows DFS provide improved results for Witwatersrand Basin Project” , which was issued with the
consent of the Competent Person, Mr Andrew Pooley. The report was released to the ASX on 27 July 2023 and is available on the Company’s
website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially affects the information included
in the relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The form and
context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement. The
DFS and any production target under the DFS contain inferred mineral resources. The directors confirm that it is reasonable to include these inferred
mineral resources in the well-understood and researched structure of the Witwatersrand Basin and the views provided to WWI by independent
geological expert consultants, given the project’s location and geology.
3. The original report was “Updated Mineral Resource Estimate for the Soweto Cluster” which was issued with consent of competent persons Mr
Hermanus Berhardus Swart, it was released to the ASX on 22 January 2016 and can be found on the Company’s website
(https://westwitsmining.com/). Comprising 0.04MT at 3.73g/t for 4.5koz Measured, 0.89MT at 2.51g/t for 72.2koz Indicated and 0.44MT at
2.86g/t for 40.9koz Inferred. The Company is not aware of any new information or data that materially effects the information included in the
relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters
underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The form and context in
which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
SUMMARY OF EXPENDITURE
Summary of expenditure on substantive exploration, development and production activities during the
quarter ended 30 September 2026:
• Approximately $10.5M for Qala Shallows surface infrastructure, underground mine development,
operations and maintenance.
• Approximately $1.2M for two permanent diesel generators
Related Party Payments
• $241k for director fees, salaries and related costs paid to Messrs Quinert, Deysel, Grigor and Middleton
(to 1 September 2026).
• $41k to QR Lawyers Pty Ltd & Brickwick Pty Ltd, related entities of Mr Quinert, for office rent, company
secretarial and legal services.
INTERESTS IN MINING TENEMENTS
Tenements Location
Held at end of
Quarter
Acquired during
Quarter
Disposed during
Quarter
Mining Right – GP
30/5/1/2/2/10073 MR (WBP)
Witwatersrand Basin, West
Rand, South Africa
74%* - -
Prospecting Right – (GP
30/5/1/1/2/10730PR) (WBP)
Witwatersrand Basin, West
Rand, South Africa
74%* - -
Prospecting Right – (GP
30/5/1/1/2/10839PR) (WBP)
Witwatersrand Basin, West
Rand, South Africa
74%* - -
Exploration License – EL
45/5045 (Mt Cecelia)
Pilbara region, Western
Australia
100% - -
* Minority positions are held by local parties in compliance with South African legislation in relation to foreign ownership and mineral and
production rights.
Rule 4.7B
ASX Listing Rules Appendix 4C (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 4C
Quarterly cash flow report for entities
subject to Listing Rule 4.7B
Name of entity
WEST WITS MINING LIMITED (ASX: WWI)
ABN Quarter ended (“current quarter”)
89 124 894 060 30 September 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
1. Cash flows from operating activities
485 485
1.1 Receipts from customers
1.2 Payments for
- -
(a) research and development
(b) product manufacturing and operating
costs
(743) (743)
(c) advertising and marketing (26) (26)
(d) leased assets - -
(e) staff costs (396) (396)
(f) administration and corporate costs (1,538) (1,538)
1.3 Dividends received (see note 3) - -
1.4 Interest received 259 259
1.5 Interest and other costs of finance paid (4) (4)
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(1,963) (1,963)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) businesses - -
(c) property, plant and equipment (1,243) (1,243)
(d) investments - -
(e) intellectual property - -
Appendix 4C
Quarterly cash flow report for entities subject to Listing Rule 4.7B
ASX Listing Rules Appendix 4C (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
(f) other non-current assets (Mine
Development)
(10,520) (10,520)
2.2 Proceeds from disposal of:
- -
(a) entities
(b) businesses - -
(c) property, plant and equipment - -
(d) investments - -
(e) intellectual property - -
(f) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - -
2.6 Net cash from / (used in) investing
activities
(11,763) (11,763)
3. Cash flows from financing activities
- -
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of
equity securities or convertible debt
securities
- -
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
(1,462) (1,462)
3.8 Dividends paid - -
3.9 Other (provide details if material) (22) (22)
3.10 Net cash from / (used in) financing
activities
(1,484) (1,484)
4. Net increase / (decrease) in cash and
cash equivalents for the period
32,145 32,145
4.1 Cash and cash equivalents at beginning of
period
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(1,963) (1,963)
Appendix 4C
Quarterly cash flow report for entities subject to Listing Rule 4.7B
ASX Listing Rules Appendix 4C (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
4.3 Net cash