WWI Investor Presentation - RIU Resources Round-Up
Released
Released
Announcement PDF
ASX Announcement and Media Release
Tuesday, 7 May 2024
West Wits Mining Presentation
RIU Sydney Resources Round-Up Australia
West Wits Mining Limited (ASX: WWI) (OTCQB: WMWWF) is pleased to announce its participation at
the RIU Sydney Resources Round-up to be held at the Hyatt Regency Hotel in Darling Harbour, Sydney,
on 7-9 May 2024.
Central to West Wits’ participation is its flagship project, Qala Shallows, a pivotal component of the
4.28Moz Gold2 Witwatersrand Basin Project (“WBP”). Positioned strategically within South Africa's
Central Rand Goldfield, near Soweto in Gauteng Province, Qala Shallows is poised to be a
transformative force, creating over 1,000 job opportunities in its initial phase.
Qala Shallows’ Definitive Feasibility Study1 reveals a projected gold production of 924,000 ounces at
an All-In-Sustaining-Cost of US$977/oz over its 17.7 Life-of-Mine, with an annual steady-state
production of 70,000 ounces, highlighting the project's substantial potential and long-term
sustainability.
Attached is a copy of the Corporate Presentation that will be shared with attendees at the event.
Approved for release by the joint Company Secretary.
For further information contact our Investor Relations:
Keith Middleton
keith@middletoncorporate.com.au
General
info@westwitsmining.com
westwitsmining.com
linkedin.com/company/west-wits-mining
ABOUT WEST WITS MINING LIMITED
West Wits Mining Limited (ASX: WWI) (OTCQB: WMWWF) is focused on the exploration, development and
production of high value precious and base metals for the benefit of shareholders, communities and
environments in which it operates. Witwatersrand Basin Project, located in the proven gold region of Central
Rand Goldfield of South Africa boasts, a 4.28Moz gold project at 4.58g/t2. The Witwatersrand Basin is a largely
underground geological formation which surfaces in the Witwatersrand. It holds the world's largest
known gold reserves and has produced over 1.5 billion ounces (over 40,000 metric tons), which represents about
22% of all the gold accounted for above the surface. In Western Australia, WWI is exploring for gold and copper
at the Mt Cecilia Project in a district that supports several world-class projects such as Woodie Woodie
manganese mine, Nifty copper and Telfer gold/copper/silver mines.
1.
The original report was “Updates to DFS Provide Improved Results for WBP” which was issued with consent of Competent
Persons Mr. Andrew Pooley. The report was released to the ASX on 26 July 2023 and can be found on the Company’s
website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially
effects the information included in the relevant market announcement and, in the case of Mineral Resources or Ore
Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed. The form and context in which the Competent
Person’s findings are presented have not been materially modified.
page i
2.
The original report was “WBP’s Global JORC Mineral Resource Expands by 724,000oz to 4.28MOZ at 4.58 g/t Gold” which
was issued with consent of the Competent Person, Mrs Cecilia Hattingh. The report was released to the ASX on 3
December 2021 and can be found on the Company’s website (https://westwitsmining.com/). Comprising 8.8MT at
4.60g/t for 1.449Moz measured, 11.3MT at 4.19g/t for 1.517Moz Indicated and 8MT at 5.10g/t for 1.309Moz inferred.
The Company is not aware of any new information or data that materially effects the information included in the relevant
market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially
changed. The form and context in which the Competent Person’s findings are presented have not been materially
modified from the original market announcement.
page ii
WEST WITS MINING
SOUTH AFRICA | NEAR TERM GOLD PRODUCER
Sydney Resources Round-Up |Corporate Presentation | May 2024
ASX:WWI | OTCQB: WMWWF
COPYRIGHT ©2024 ALL RIGHTS RESERVED
Qala Shallows, Witwatersrand Basin Project, Gauteng
Mining District, Johannesburg, South Africa
DISCLAIMER
FORWARD-LOOKING STATEMENTS
COMPETENT PERSON STATEMENTS
This presentation includes “forward-looking statements” as that term within the meaning of securities laws of
The original report was “Updates to Qala Shallows DFS provide improved results for Witwatersrand Basin
applicable jurisdictions. Forward-looking statements involve known and unknown risks, uncertainties and other
Project” which was issued with consent of the Competent Person, Mr. Jim Pooley. The report was released to
factors that are in some cases beyond West Wits Mining Limited’s control. These forward-looking statements
the ASX in July 2023 and can be found on the Company’s website (https://westwitsmining.com/). The
include, but are not limited to, all statements other than statements of historical facts contained in this
Company is not aware of any new information or data that materially effects the information included in the
presentation, including, without limitation, those regarding West Wits Mining Limited’s future expectations.
relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material
Readers can identify forward-looking statements by terminology such as “aim,” “anticipate,” “assume,”
assumptions and technical parameters underpinning the estimates in the relevant market announcement
“believe,” “continue,” “could,” “estimate,” “expect,” “forecast,” “intend,” “may,” “plan,” “potential,”
continue to apply and have not materially changed. The form and context in which the Competent Person’s
“predict,” “project,” “risk,” “should,” “will” or “would” and other similar expressions. Risks, uncertainties and
findings are presented have not been materially modified from the original market announcement.
other factors may cause West Wits Mining Limited’s actual results, performance, production or achievements
to differ materially from those expressed or implied by the forward-looking statements (and from past results,
The original report was “WBP’s Global JORC Mineral Resource Expands by 724,000oz to 4.28MOZ at 4.58 g/t
performance or achievements).
Gold” which was issued with consent of the Competent Person, Mrs Cecilia Hattingh. Comprising 8.8MT at
4.60g/t for 1.449Moz measured, 11.3MT at 4.19g/t for 1.517Moz Indicated and 8MT at 5.10g/t for 1.309Moz
These factors include, but are not limited to, the failure to complete and commission the mine facilities and
inferred. The report was released to the ASX on 3 December 2021 and can be found on the Company’s
related infrastructure in the time frame and within estimated costs currently planned; variations in global
website (https://westwitsmining.com/). The Company is not aware of any new information or data that
demand and price for gold fluctuations in exchange rates between the U.S. Dollar, South African Rand and
materially effects the information included in the relevant market announcement and, in the case of Mineral
the Australian Dollar; the failure of West Wits Mining Limited’s suppliers, service providers and partners to fulfil
Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates
their obligations under construction, supply and other agreements; unforeseen geological, physical or
in the relevant market announcement continue to apply and have not materially changed. The form and
meteorological conditions, natural disasters or cyclones; changes in the regulatory environment, industrial
context in which the Competent Person’s findings are presented have not been materially modified from the
disputes, labour shortages, political and other factors; the inability to obtain additional financing, if required,
original market announcement.
on commercially suitable terms; and global and regional economic conditions. Readers are cautioned not to
place undue reliance on forward-looking statements. The information concerning possible production in this
announcement is not intended to be a forecast. They are internally generated goals set by the board of
directors of West Wits Mining Limited. The ability of the Company to achieve any targets will be largely
determined by the Company’s ability to secure adequate funding, implement mining plans, resolve logistical
issues associated with mining and enter into any necessary off take arrangements with reputable third parties.
Although West Wits Mining Limited believes that its expectations reflected in these forward-looking statements
are reasonable, such statements involve risks and uncertainties and no assurance can be given that actual
results will be consistent with these forward-looking statements.
ASX:WWI
PAGE | 2
Why invest in West Wits
ASX:WWI
OTCQB:WMWWF
Significant gold resource in the
Witwatersrand Basin Project (WBP)
South Africa
WBP – Mineral Resource Estimate
4.28Moz Gold
(70% measured & indicated categories)1
WBP - Project 200 - significant growth
opportunity aimed to produce
200 000oz Gold per annum
Stage 1 - Qala Shallows - DFS
Post Tax IRR 53% & NPV US$255M
at US$1,850/oz gold price2
Qala Shallows – Robust DFS aimed at
70,000oz p/a steady-state production
for 9 years2
Qala Shallows – immediate production
Fully permitted: Mining Right; power;
environmental; social; water; explosives
Critical infrastructure completed
Qala Shallows – Secured cost-effective
toll treat agreement with Ezulwini Mining
Company/ Sibanye-Stillwater subsidiary
Funding - Expression of Interest for
~US$16M Debt Facility from SA
Development Finance Institution;
Due Diligence underway
Two projects in stable jurisdictions with
experienced board and management
team
ASX: WWI | OTBCQB: WMWWF
CORPORATE SNAPSHOT
Transforming into mid-tier gold producer
CAPITAL STRUCTURE (ASX:WWI)
Pre-Raise
Pro-forma2
Shares on issue
Unlisted Options
2.43B
175M
2.54B
180M
Market Capitalisation
@1.6c per share on 30/04/2024
$38.9M
$40.6M
Cash - 30/04/20241
A$600k
A$1.9M
Enterprise Value per ounce
A$8.92oz
A$9.04oz
JORC Mineral Resource Estimate1 (Gold)
includes declared Ore Reserves
Commodity Exposure
ASX:WWI
1. Approx. $350k of additional funds expected to be received via settlement of
26M Excess Provisional Placement Shares issued to SBC Global upon, or
before, expiry period (26 August 2024).
2. Pro-forma Capital Structure based on settlement of Equity Placement
announced to the ASX on 03/05/2024 for the issue of 107.7M West Wits shares
at 1.3c for $1.4M
4.28Moz
Gold, Uranium
PAGE | 4
INVESTOR FOCUSED INTERNATIONAL BOARD &
MANAGEMENT TEAM
RSA SUBSIDIARY
EXEC DIRECTOR /
HEAD OF CORP
AFFAIRS
AUSTRALIA
WWI CHAIRMAN
Michael Quinert
ASX-experienced
commercial lawyer with
extensive involvement in
assisting and advising
publicly listed mining
companies
COO / COUNTRY
MANAGER (RSA)
ASX:WWI
Tozama Kulati Siwisa
BCom with MBA with
extensive experience in
ESG management having
worked at Lonmin plc
prior to joining West Wits
Rudi Deysel
Mining Eng. with
Geophysics and MBA.
Extensive experience in
conventional narrow
tabular underground &
open cast, mining
various commodities
including Gold, PGMs,
Copper and Cobalt
EXEC MANAGER
COMMERCIAL
SOUTH AFRICA
WWI NON-EXEC
DIRECTOR
SOUTH AFRICA
WWI NON-EXEC
DIRECTOR
AUSTRALIA
WWI NON-EXEC
DIRECTOR
Hulme Scholes
One of SA’s top legal
professionals
specialising in mining
and mineral law
Jac van Heerden
Mining Engineer with
MBA and operations
and project experience
in South Africa, DRC
and Zimbabwe
Warwick Grigor
Experienced mining analyst
who founded Far East
Capital Limited, a specialist
mining company financier
and corporate adviser
Keith Middleton
Experienced Executive
of ASX listed companies
specialising in the
resources sector,
financial analysis, risk
management, major
capital works
expenditure, corp.
governance and ESG
regulations
CFO / COMPANY
SECRETARY
Simon Whyte
Chartered
Accountant with
extensive experience
in mining,
commodities and
logistics which
includes global
majors, Ernst & Young
and BP
Martin Bevenlander
Geologist with
expertise that spans
across the entire
mining cycle. Worked
in Indonesia, Papua
New Guinea, Australia,
and across Africa
HEAD OF
GEOLOGY &
EXPLORATION
PAGE | 5
WITWATERSRAND BASIN PROJECT (WBP)
GLOBAL MINERAL RESOURCE ESTIMATE (JORC 2012)1
▪
Significant global Mineral Resource Estimate of 4.28 Moz gold @ 4.58 g/t Au1
▪
3 distinct Reef horizons: Kimberley Reef; Bird Reef; Main Reef (left image)
Category
Tonnage (Mt)
Grade (g/t)
Content (oz)
Measured
8.8
4.60
1 449 000
▪
Critical infrastructure in place at Qala Shallows (Stage 1)
Indicated
11.26
4.19
1 517 000
▪
Measured & Indicated
21.06
4.38
2 967 000
New Prospecting Rights approval expected: will re-introduce a substantial
portion of previous Mineral Resource Estimate
Inferred
7.98
5.10
1 309 000
Total
29.05
4.58
4 276 000
Mining Right boundary (blue) & New Prospecting Right Applications (green / yellow)
ASX:WWI
PAGE | 6
QALA SHALLOWS – STAGE 1
ROBUST DEFINITIVE FEASIBILITY STUDY2
▪
Gold produced: 924,000oz
▪
Steady-State production: 70,000oz p/a (9 years)
▪
Ore Reserves : 4.03 million tonnes at 2.71g/t for 351,400 oz gold
▪
Life-of-Mine: 17.7 years
RAPID PRODUCTION GROWTH
ASX:WWI
▪
Critical infrastructure completed
▪
Decline & box cut rehabilitation completed
▪
Utilises existing decline shaft for immediate ore extraction, no plant required
▪
Contracts adjudicated with key suppliers (i.e. Toll Processing, Mining Contractor,
Underground Equipment, Explosives, etc.)
▪
Fully Permitted
o
Mining Right and Environmental Authorisation granted
o
7.5MVA power allocation received & primary power substation completed
o
Water Use License granted & established water supply infrastructure installed
o
Explosives License received
PAGE | 7
QALA SHALLOWS – DFS FINANCIAL MODEL & FUNDING
KEY FINANCIAL METRICS
DEFINITIVE FEASABILITY STUDY2
▪
Post-Tax Free Cashflow of US$522m over Life-of-Mine
▪
AISC cost in lowest quartile at US$977/oz
▪
Post-Tax - NPV7.5 US$255m and IRR 53%
PEAK FUNDING REQUIREMENT
▪
US$54m (DFS) with 4.1yr payback period from commencement of construction
▪
Peak funding substantially reduced at prevailing Gold Price & ZAR / US$ FX rate due to
higher revenue from production during the 3-year mine development phase
▪
At a Gold Price (US$2,150/oz), peak funding reduces to US$44M
PROJECT FUNDING INITIATIVES
▪
▪
▪
South African Development Finance Institution provided Expression of Interest and Indicative
Terms for ZAR300m (~US$16m) debt package facility. The due diligence process
commenced in Feb-24 and is progressing well
Wingfield Partners LLC (Wingfield), Expression of Interest and indicative terms for US$10M
debt facility. WWI has deferred progressing the Wingfield Letter of Interest to a binding
commitment whilst it examines other potential funding sources which may ultimately
provide more favourable terms
Company is pursuing multiple negotiations with a broad range of potential financiers and /
or investors. Possible funding mechanisms range from debt facilities, streaming / royalty
finance, pre-paid gold loans, direct investment at project level or listed company level and
combinations of one or more of the above
ASX:WWI
DFS - Financial Evaluation2
Gold Price
US$1,850/oz
Total Revenue
US$ 1.7b
Total Free Cashflow
US$ 522m
Peak Funding
US$ 54m
LOM C1 Cost
US$ 818 / oz
LOM All-In Sustaining Cost
US$ 977/oz
Steady-State All in Sustaining Cost
US$ 871 /oz
Payback
4.1 years
Pre-Tax Net Present Value (7.5%)
US$ 367m
Post-Tax Net Present Value (7.5%)
US$ 255m
Pre-Tax Internal Rate of Return
61%
Post-Tax Internal Rate of Return
53%
PAGE | 8
Bird Reef Central: Uranium & Gold Opportunity
Presence of uranium mineralisation within the Bird Reef sequence provides
significant opportunity for the BRC to become a joint gold and uranium operation
URANIUM EXPLORATION TARGET4
BRC Uranium Project has the potential to become a standalone mine with
separate infrastructure accessed through the existing Circular Shaft site
Range
Low
High
Declared JORC Gold Mineral Resource - 1.38Mt Ore at 2.66g/t for 118,000oz5
Tonnes (M)
10
22
Uranium Exploration Program
Grade (ppm) U3O8
300
550
Content (Mlb) U3O8
12
16
▪
▪
Phase 1 2008 Exploration results4 confirmed consistent uranium mineralisation
over approx. 3.3km with more than 7km of strike identified along the targeted
Bird Reef section within the WBP’s mining right area
BRC Uranium Exploration Program outlined and aimed at converting the
significant Uranium Exploration Target to a JORC compliant Mineral Resource
Estimate (MRE) within the Bird Reef Sequence of the WBP
▪
Uranium Exploration Target is confined to the western margin of the WBP’s
mining right area and remains open for the approx. 3.75km strike length
extension to the east
▪
2022 Diamond Drilling results5 highlighted by:
Notes: The potential quantity and grade are conceptual in nature. There has been insufficient exploration
and evaluation of historical information to estimate a Mineral Resource. It is uncertain if further exploration
will result in the estimation of a Mineral Resource.
URANIUM EXPLORATION PROGRAM TIMELINE
Phase 1 – 2008
Completed
30 drillholes
6,688m3
Initial Exploration Program to
confirm uranium mineralisation
Phase 2 – 2022
Completed
3 drillholes
291m5
Execution of Phase 2
exploration drilling (BRC Project)
0.96m @ 1,321ppm U & 2.30g/t Au from 85.74m)
Phase 3
Planned
10 drillholes
2,640m
Convert Exploration Target to
JORC MRE
White Reef (PH1B) - 1.20m depth @ 108ppm U & 5.45g/t Au (104.61m)
Phase 4
Planned
2 drillholes
1,600m
Target depth extension of MRE
Middle Reef (PH1B) - 1.59m depth @ 835ppm U & 1.46g/t Au (85.11m), including
Middle Reef (PH1C) - 1.26m depth @ 221ppm U & 0.38g/t Au (77m)
ASX:WWI
PAGE | 9
ENVIRONMENTAL, SOCIAL & GOVERNANCE (ESG)
ENVIRONMENTAL STEWARDSHIP & BIODIVERSITY CONSERVATION
▪
Complete underground operation: low noise and dust levels
▪
Small footprint & surface infrastructure: low rehabilitation liability & minimal impact
on surrounding environment
▪
Efficient water use model: Minimal water usage & zero effluent discharge into
local tributaries
SOCIAL POSITIVE IMPACT OF HOST COMMUNITIES
▪
Local Economic Development Programme: Community wards forum in
collaboration with City of Joburg
▪
Local procurement: Sourced from growing BEE database
▪
Social & Labour Plan: Includes Beneficiary Learnership Programme
GOVERNANCE RESPONSIBLE PRODUCTION PRACTICES
▪
Corporate Governance Framework: Complies with changing legal
& regulatory requirements
▪
Company Mine Health & Safety: Conforms to Mine Health & Safety Act 29 of 1996
▪
Mining Right & Water Use License: Granted
▪
Health & Safety: Zero harm approach
▪
Stakeholder Engagement: Transparent reporting
ASX:WWI
PAGE | 10
MT CECELIA PROJECT
Paterson Province / East Pilbara, Western Australia
Up to $10m Farm-In Agreement with Rio Tinto Exploration to earn up 80% of project.
GEOLOGY & MINERALISATION
▪
Regional geological setting is highly prospective & conducive to multiple possible styles
of precious & base metal mineralisation.
▪
Bedrock largely concealed beneath recent sedimentary cover.
▪
Geophysical MLTEM surveys completed identifying 4 top priority drill targets (SGC1-4)
defined with legitimate bedrock conductors (bottom right image)7
▪
Major Vines Fault structure runs broadly NNE-SSW through center of E45/5045 towards
Nifty Mine
SIGNIFICANT GOLD INTERCEPTS AT PRIMARY EM SGC_1 TARGET8
Maiden drilling program highlighted by:
ASX:WWI
▪
WEWI0001 - 56m @ 0.55g/t Au from 194m, including 20m @
0.93g/t Au from 194m
▪
WEWI0004 - 82m @ 0.51g/t Au from 128m, including 24m @
0.95g/t Au from 150m
PAGE | 11
Qala Shallows Box Cut
CHIEF OPERATIONS OFFICER
INVESTOR RELATIONS
SOUTH AFRICA
AUSTRALIA
Rudi Deysel
Keith Middleton
+27 (0)78 680 2864
rdeysel@westwitsmining.com
+61 438 101 102
keith@middletoncorporate.com.au
Unit 8A, Sifon Industrial Park
279 Sifon Street, Robertville
Roodepoort
1709
Level 6, 400 Collins Street
Melbourne, Victoria
Australia
3000
westwitsmining.com | info@westwitsmining.com
COPYRIGHT ©2023 ALL RIGHTS RESERVED
ASX:WWI
PAGE | 12
Appendix 1: Ore Reserve & Mineral Resource Estimate Statements
Table: WBP (JORC) Ore Reserve2
Declared ore reserve of 4.03MT at 2.71g/t for 351,424oz Gold2
Ore Reserve Notes:
1. No Inferred Mineral Resources are included in the Ore Reserves.
2. The evaluation used a gold price US$1,850 per ounce and a rate of exchange of R17.5 / US$ 1.
ORE RESERVE STATEMENT FOR QALA SHALLOWS (JORC 2012)
ORE Reserve
Category
Tonnage
(Mt)
Grade
(g/t)
Content
(kg)
Content
(oz)
Proved
0.96
2.96
2 847
91 536
Probable
3.07
2.64
8 083
259 887
Total
4.03
2.71
10 930
351 424
WBP’s Global Mineral Resource is made up of several gold bearing reefs across the mining
right area, a breakdown by reef and MRE category is detailed in Table 21.
MRE Notes:
1. Global MRE set at a 2.0g/t Au cut-off. Reported in accordance with the JORC Code of 2012.
2. Number differences may occur due to rounding errors.
3. Mineral Resources are reported as inclusive of Ore Reserves.
4. The Inferred Mineral Resources have a high degree of uncertainty, and it should not be
assumed that all or a portion thereof will be converted to Ore Reserves.
Note: errors may occur due to rounding differences
Table 2: WBP (JORC) Mineral Resource Estimate – by Reef (2g/t cut-off)1
Measured
Indicated
Inferred
Total
Reef
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Tonnes
(M)
Grade
(g/t)
Ounces
(M)
Bird – Central & West
0.04
3.73
0.00
0.89
2.51
0.07
0.44
2.86
0.04
1.38
2.66
0.12
Bird – East
2.22
4.30
0.31
2.00
4.74
0.30
0.42
4.48
0.06
4.63
4.51
0.67
K9B KRC
0.00
2.98
0.00
0.10
3.87
0.01
0.18
4.22
0.02
0.28
4.08
0.04
K9B KRE
1.93
4.37
0.27
6.21
4.14
0.83
2.35
5.51
0.42
10.50
4.49
1.52
K9A KRE
2.10
4.54
0.31
1.82
4.20
0.25
4.20
5.14
0.69
8.11
4.77
1.25
Main Reef Leader
0.72
5.81
0.14
0.15
8.34
0.04
0.09
7.54
0.02
0.96
6.36
0.20
Main
2.79
4.73
0.42
0.09
5.15
0.01
0.31
5.27
0.05
3.19
4.79
0.49
Total
9.81
4.60
1.45
11.26
4.19
1.52
7.98
5.10
1.31
29.05
4.58
4.28
ASX: WWI | OTBCQB: WMWWF
REFERENCES
1.
The original report was “WBP’s Global JORC Mineral Resource Expands by 724,000oz to 4.28MOZ at 4.58 g/t Gold” which was issued with consent of the Competent Person, Mrs Cecilia Hattingh. The report was released to
the ASX on 3 December 2021 and can be found on the Company’s website (https://westwitsmining.com/). Comprising 8.8MT at 4.60g/t for 1.449Moz measured, 11.3MT at 4.19g/t for 1.517Moz Indicated and 8MT at 5.10g/t
for 1.309Moz inferred. The Company is not aware of any new information or data that materially effects the information included in the relevant market announcement and, in the case of Mineral Resources or Ore
Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The form and context in which the
Competent Person’s findings are presented have not been materially modified from the original market announcement.
2.
The original report was “Updates to Qala Shallows DFS provide improved results for Witwatersrand Basin Project” which was issued with consent of the Competent Person, Mr. Andrew Pooley. The report was released to the
ASX on 27 July 2023 and can be found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the information included in the relevant
market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply
and have not materially changed. The form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
3.
WWI ASX Release 22/07/2008 “West Wits Completes Conceptual Target Statement”
4.
The original report was “West Wits advances exploration work on Uranium at WBP” which was issued with consent of the Competent Person, Mr Michael Robertson. The report was released to the ASX on 25 October 2021
and can be found on the Company’s website (https://westwitsmining.com/). The potential quantity and grade of the Exploration Target are conceptual in nature, there has been insufficient exploration and evaluation of
historical information to estimate a Mineral Resource. It is uncertain if further exploration will result in the estimation of a Mineral Resource. The Company is not aware of any new information or data that materially effects
the information included in the relevant market announcement. The form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
5.
The original report was “Updated Mineral Resource Estimate for the Soweto Cluster” which was issued with consent of competent persons Mr. Hermanus Berhardus Swart, it was released to the ASX on 22 January 2016 and
can be found on the Company’s website (https://westwitsmining.com/). The company is not aware of any new information or data that materially effects the information included in the relevant market announcement.
The form & context in which the Competent Persons’ findings are presented have not been materially modified.
6.
The original report was “Positive Phase 1 Uranium Drilling Results for West Wits” which was issued with consent of Competent Persons Mr. Michael Robertson. The report was released to the ASX on 6 October 2022 and can be
found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the information included in the relevant market announcement. The form
and context in which the Competent Person’s findings are presented have not been materially modified
7.
The original report was “HEM Survey Identifies Eight Targets Areas at Mt Cecelia” which was issued with consent of the Competent Person, Mr. Russell Mortimer. The report was released to the ASX on 16/12/2020 and can be
found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the information included in the relevant market announcement. The form
and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
8.
The original report was “Significant Maiden Gold Intercept at Mt Cecelia” which was issued with consent of Competent Person, Mr. Martin Bevelander. The report was released to the ASX on 18/01/2023 and can be found
on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the information included in the relevant market announcement. The form and
context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
ASX:WWI