Updates to DFS Provide Improved Results for WBP
Released
Released
Announcement PDF
ASX Announcement and Media Release
26 July 2023
Updates to Qala Shallows DFS provide improved results for
Witwatersrand Basin Project
West Wits Mining Limited (“ASX: WWI”, “OTCQB: WMWWF” “West Wits”, or “the Company”) is
pleased to announce the positive results of an updated Definitive Feasibility Study for its Qala Shallows,
part of the Witwatersrand Basin Project (“WBP”) in Johannesburg, South Africa.
HIGHLIGHTS
➢ 38% increase in Recovered Gold
o Gold Production: 924,000oz (38% increase) over 17.7-year Life-of-Mine
o Steady-State Production: ~70,000oz pa (27% increase) for 9 years
➢ All-In-Sustaining-Cost: decreasing 10.7% from US$ 1,093/oz to US$ 977/oz
➢ Project Financials:
o Free Cashflow: US$522M, increase of US$254M (95%)
o Pre-tax NPV7.5: US$367M, increase of US$187M (104%)
o Post-tax NPV7.5: US$255M, increase of US$130M (104%)
➢ Funding: US$54M (2022: US$63M) with payback period of 4.1-years (2022: 5-years)
from construction
➢ Ore Reserve: 4.03 million tonnes at 2.71g/t for 351,400 oz Gold, an increase of 61,400
oz (21%)
QALA SHALLOWS – FINANCIAL EVALUATION
Total Revenue (USD)
Total Free Cashflow (USD)
Peak Funding (USD)
LOM C1 Cost (USD/oz)
LOM All in sustaining Cost (USD/oz)
Steady-State All in Sustaining Cost (USD/oz)
Payback (years)
Pre-Tax Net Present Value 7.5 (USD)
Post-Tax Net Present Value 7.5 (USD)
Pre-Tax Internal Rate of Return (%)
Post-Tax Internal Rate of Return (%)
*
AUG-221
$ 1 170 million
$ 268 million
$ 63 million
$ 917 / oz
$ 1 093/oz
$ 962 /oz
5.0 years
$ 180m
$ 125m
38%
32%
JUN-23
$ 1 709 million
$ 552 million
$ 53 million
$ 818 / oz
$ 977/oz
$ 871 /oz
4.1 years
$ 367m
$ 255m
61%
53%
Including Inferred Resources
West Wits Chairman Michael Quinert said, “Qala Shallows’ updated DFS has delivered a strong result
and sets the scene for us to deliver a substantially larger gold project. The project's potential is evident
in the updated financial metrics. With an impressive increase of US$254 million (95%) in Free Cashflow,
the project is set to generate US$522 million. These figures emphasise the project's value and its
potential to deliver substantial returns to our shareholders. There is good reason to be excited about
the future prospects of the Witwatersrand Basin Project.”
page i
ASX Announcement and Media Release
26 July 2023
EXECUTIVE SUMMARY
In line with the Company’s commitment to excellence, it commissioned independent mining engineers
Bara Consulting (“Bara”), to undertake a comprehensive review and update of the Qala Shallows
Definitive Feasibility Study (“DFS”) released in August 20221. The updated DFS further enhances its
already promising outlook.
QALA SHALLOWS IMPROVED PRODUCTION SCHEDULE
Image 1 outlines Qala Shallows’ production profile to an execution level of accuracy for a 24-month
budgetary period. The remaining Life-of-Mine (“LOM”) is at a DFS level of accuracy, and there is an
improved confidence on costs regarding some capital and operating expenditure, most notably the
mining and equipment costs.
900
90,000
800
80,000
700
70,000
600
60,000
500
50,000
400
40,000
300
30,000
200
20,000
100
10,000
-
-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
ROM - Gold Content [oz]
Ore/Waste Tonnes [kt]
IMAGE 1: QALA SHALLOWS PRODUCTION PROFILE SHOWING THE WASTE AND ORE MINING
OVERLAID WITH THE ROM OUNCE PROFILE OVER LOM
Project Year
Ore Tonnes
Waste Tonnes
ROM Content
The updated production profile indicates waste and ore tonnes, as well as ROM gold content in ounces.
Qala Shallows has a steady-state gold production of approximately 70,000 oz per annum for
approximately twelve years.
QALA SHALLOWS UPDATED MINE SCHEDULES
The DFS models two mine schedules updated in terms of JORC 2012 requirements:
1. Base Case – LOM plan which targets total Mineral Resources (Measured, Indicated and
Inferred Mineral Resources)
2. Ore Reserve – LOM Plan which targets Measured and Indicated Mineral Resources only
QALA SHALLOWS IMPROVED PRODUCTION DATA
Table 2 shows the highlights of the production data from the updated LOM plan. There is an increase
from the 2022 DFS plan regarding total ROM tonnage, as well as the maximum production rates and
gold produced.
(Table 1 outlining Section 4 Estimation and Reporting of Ore Reserves is in Appendix A)
page ii
ASX Announcement and Media Release
26 July 2023
TABLE 2: BASE CASE - KEY PRODUCTION METRICS FOR QALA SHALLOWS
AUG-221
15.7 years
7.6 million t
699,000 pa
2.98 g/t Au
726,400 oz
92%
688,000 oz
JUN-23
17.7 years
10.2 million t
839,000 pa
3.04 g/t Au
1,005,000 oz
92%
924,000 oz
Average Annual Gold Production
43,000 oz
51,000 oz
Average Annual Steady State Gold Production (9yrs)
Max Gold Production (Year 6)
55,000 oz
60,000 oz
70,000 oz
75,000 oz
QALA SHALLOWS – PRODUCTION DATA*
Life-of-Mine (Construction to Relinquishment)
Total Production (Run of Mine Tonnes)
Max Production Rate (Tonnes)
Run-of-Mine Grade Au (Average)1
LOM Contained Au
Metallurgical Recovery Au (Overall)
Gold Produced
*
Includes Inferred Resources
The improved production data includes:
•
New survey and sampling data obtained from underground access, enabling an update of the
dip of the ore body based on actual measurements
•
Confirmation of mining blocks available for mining in the old mine area
•
Inclusion of additional Mineral Resources not previously accounted for in the LOM
•
Increase of ore production rate to approx. 65,000tpm (2022: 55,000tpm)
•
Application of a 5% ore loss through the ore flow process
QALA SHALLOWS ENHANCED FINANCIAL OUTCOME
Updated capital and operating cost estimates, along with the updated LOM plan, were used in the
updated DFS financial evaluation. Gold price and Foreign Exchange (USD / ZAR) assumptions have been
updated to more closely represent the current market trends. Primary updates include:
•
Gold Price: US$1,850/oz (2022: US$1,750/oz)
•
Exchange Rate: ZAR 17.5 to US$ 1 (2022: ZAR 15.0 to US$ 1)
•
Toll Treating rate based on executed agreement
•
New contractor rates based on firm quotes
The Base Case financial evaluation improved when compared to the 2022 DFS, which is largely driven
by increase in production volume and production rate, plus favourable movements in the Gold Price
and USD / ZAR rate.
Table 3 shows the financial evaluation of Qala Shallows, comparing the August 2022 DFS to the
updated July 2023’s figures.
page iii
ASX Announcement and Media Release
26 July 2023
TABLE 3: BASE CASE - FINANCIAL EVALUATION OUTCOME
QALA SHALLOWS – FINANCIAL EVALUATION
Total Revenue (USD)
Total Free Cashflow (USD)
Peak Funding (USD)
LOM C1 Cost (USD/oz)
LOM All in sustaining Cost (USD/oz)
Steady-State All in Sustaining Cost (USD/oz)
Payback (years)
Pre-Tax Net Present Value 7.5 (USD)
Post-Tax Net Present Value 7.5 (USD)
Pre-Tax Internal Rate of Return (%)
Post-Tax Internal Rate of Return (%)
*
AUG-221
$ 1 170 million
$ 268 million
$ 63 million
$ 917 / oz
$ 1 093/oz
$ 962 /oz
5.0 years
$ 180m
$ 125m
38%
32%
JUN-23
$ 1 709 million
$ 552 million
$ 53 million
$ 818 / oz
$ 977/oz
$ 871 /oz
4.1 years
$ 367m
$ 255m
61%
53%
Including Inferred Resources
The main highlights are:
•
AISC – 10.6% decrease to US$977/oz
•
Post Tax NPV7.5 - 104% increase in Post Tax NPV7.5 to US$255M
•
Post-Tax IRR – 63.5% increase to 53%
The waterfall chart presented in Image 2 clearly shows that the most significant improvement to the
financial evaluation is attributed to revenue obtained by 38% increase in Gold Produced and 5.7%
increase in Gold Price. Operating Costs increased due to the higher production volumes and the ZAR
unit cost increased approx. 6% from higher Processing and Transport rates. This was offset in USD
terms by the devaluation of the ZAR.
IMAGE 2: BASE CASE - WATERFALL CHART FOR NPV7.5 (ZAR'million)
page iv
ASX Announcement and Media Release
26 July 2023
QALA SHALLOWS SENSITIVITY ANALYSIS
The sensitivity analysis in Table 4 shows that at a low gold price of US$1,500/oz, the project still has
strong financial outcomes which makes this a highly robust project.
TABLE 4: BASE CASE - SENSITIVITY TO GOLD PRICE
Gold
Price
Post-Tax
Project
NPV7.5
USD'm
Post-Tax
Project
IRR
%
Operating
Margin
Peak Funding
Requirement
Payback
Period
USD/oz
Pre-Tax
Project
NPV7.5
USD'm
%
USD'm
years
1 500
1 750
1 850
2 000
2 200
219
321
367
437
531
144
223
255
302
366
34
47
53
61
72
46
53
56
59
63
68
58
54
49
43
4.9
4.3
4.1
3.8
3.6
Recent devaluation of the South African Rand compared to the United States Dollar presents further
project potential as demonstrated in Table 5, which outlines the sensitivity to exchange rate. This is
largely driven by the additional revenue realised by the project at higher ZAR/USD exchange rates, as
most project costs remain in South African Rand terms.
TABLE 5: BASE CASE- SENSITIVITY TO EXCHANGE RATE
Exchange
Rate
Pre-Tax
NPV7.5
Post-Tax
NPV7.5
Post-Tax
IRR
Operating
Margin
ZAR/USD
15.00
16.50
17.50
18.50
20.00
USD'm
287
338
367
394
429
USD'm
200
235
255
273
296
%
39
47
53
59
67
%
48
53
56
58
61
Peak
Funding
Requirement
USD'm
75
61
54
47
40
Payback
Period
years
4.7
4.3
4.1
3.9
3.7
PROJECT FUNDING OPTIONS ADVANCING
The 2023 Base Case DFS estimates peak funding of USD54m (ZAR 943M) over a three-year period, a
net decrease of US$9M. Higher OPEX and CAPEX resulting from the increased production have been
offset by revenue from increased production during the 3-year funding period and favourable
movements in the Gold Price and South African Rand.
The IDC has expressed formal interest in providing loan funds of ZAR300 million (approximately
US$15.9 million) for development capital at Qala Shallows4. The IDC is a prominent development
finance institution committed to driving economic growth and industrial development in South Africa.
This endorsement showcases the IDC's confidence in the WBP and highlights the immense potential of
Qala Shallows. The proposed funding terms align with customary conditions for loan facilities of this
nature.
Both parties are now collaborating to expedite the due diligence process and secure final approval of
terms and conditions by the IDC’s Executive Credit Committee.
page v
ASX Announcement and Media Release
26 July 2023
The IDC funding will provide the foundation for funding the development plan outlined in the Qala
Shallows DFS. Initial funds will be used to mobilise the mining contractor and acquire essential
equipment to initiate operations. This will enable the Company to establish a robust 30,000-tonne ore
stockpile and facilitating a steady delivery of 15 kilo-tonnes per month to Sibanye-Stillwater’s plant.
The Company continues to progress constructive discussions with several prospective funders to
secure the optimum funding solution for the WBP and remains confident it will be able to secure
commitments to finance the re-commencement of operations in the near-term.
ORE RESERVE
A LOM plan and budget have been generated by the mine plan update and inclusion of actual costs in
the updated financial evaluation. The outcome of this exercise is positive and an improvement to the
2022 DFS with a 61,400oz (21%) increase in Ore Reserve to 351,424oz.
The work undertaken was based on DFS level work, as well as actual on-site activities linked to the
Early Works Program5. It is therefore considered that the Ore Reserve can be updated based on the
updated mine plan. Table 6 outlines the updated Mineral Ore Reserve.
TABLE 6: ORE RESERVE STATEMENT FOR QALA SHALLOWS (JORC 2012)
Ore Reserve
Category
Grand Totals
Proved
Probable
Total
Tonnage
Grade
Content
Content
(Mt)
0.96
3.07
4.03
(g/t)
2.96
2.64
2.71
(kg)
2 847
8 083
10 930
(oz)
91 536
259 887
351 424
NEXT STEPS
The Company will now focus on:
•
Completion of the Due Diligence process by the IDC
•
Securing balance of funding for the full US$54M funding package
•
Finalising terms and pre-conditions to enable activation of the facility including
documentation and provision of security
•
Upon drawdown, initiating mining contractor mobilisation and initial equipment required
for operations
•
Building up a 30,000-tonne gold ore stockpile to enable consistent 15ktpm gold ore delivery
to Sibanye-Stillwater’s plant
•
Targeting achievement of the stockpile and delivery within five months after mining
commenced
•
Gradual mine build-up towards a steady-state production of 5,700 ounces of gold per
month
page vi
ASX Announcement and Media Release
26 July 2023
Image 4 showcases Qala Shallow’s impressive infrastructure. To date, operational activities at Qala
Shallows have successfully:
•
Completed all critical infrastructure, including substations and water infrastructure
•
Completed the decline and box cut rehabilitation
•
Completed on reef underground access
•
Delivered first ore (estimated stockpile of 3 000t) during an Early Works Program
IMAGE 4: QALA SHALLOWS PROJECT PROGRESS
page vii
ASX Announcement and Media Release
26 July 2023
BARA CONSULTING TECHNICAL SUMMARY
INTRODUCTION
West Wits holds a mining right for the WBP located approximately 15 kilometres to the west of the
Johannesburg CBD in the Gauteng Province of South Africa. The WBP is made up of three Reef mining
targets which will be developed sequentially. During September 20212, West Wits completed a DFS
and maiden Ore Reserve Statement for the Qala Shallows Project. This study was updated in August
20221 and has subsequently been updated again in 30 June 2023 for works completed and new
information obtained, including installation of infrastructure, underground survey data, contractor
agreements and market-based cost escalations.
The Company is in the process of implementing the Qala Shallows Project and initiated an Early Works
Program in 20215 which included underground rehabilitation, development and limited production,
with a detailed short-term mine plan.
Bara has previously combined the Early Works Program with the long term DFS schedule to create an
integrated LOM plan, including a financial evaluation. This work was undertaken for the 2022 DFS
update and subsequent to this, the plan has been further updated to 21st June 2023 as reported in the
sections below.
TENURE
West Wits holds a granted mining right (GP 30/5/1/2/2/10073 MR) for the WBP located approximately
15km west of the city of Johannesburg in the Gauteng Province of South Africa.
The Company executed a 99-year lease agreement with Calgro M3 in February 2022, acquiring a 16ha
footprint which provides sufficient land for the Qala Shallows site infrastructure and access to
underground development.
The land is currently zoned for mining and the Qala Shallows site is located between old mining dumps,
away from formal housing communities. The location of the infrastructure was included in the
Environmental Impact Assessment (“EIA”), as well as for the Integrated Water Use License (“WUL”).
GEOLOGY AND MINERAL RESOURCES
The geology, geotechnical and mineral resource assumptions used in the updated DFS remain
unchanged from those utilised in the 2021 DFS2.
The mineral resource shown in Table 1 is confined to the perimeter of the Mining Right and hence has
potential to be included in a mine plan, dependent on various other modifying factors.
TABLE 1: K9A & K9B REEF JORC (2012) COMPLIANT MINERAL RESOURCE2
K9A REEF JORC (2012) COMPLIANT MINERAL RESOURCE ESTIMATE2
Au
Au
sw
cw
Au
Tonnes
Resource Category
(Millions)
(MOz) (g/t) (cm) (cm) (cm.g/t)
Measured
2.1
0.31
4.54 112 108
508
Indicated
1.8
0.25
4.20 113 112
473
Measured and Indicated
3.9
0.55
4.38 112 110
492
Inferred
4.2
0.7
5.1
124
124
639
Grand Total
8.1
1.2
4.8
118
117
564
Note: Errors may occur due to rounding differences
page viii
ASX Announcement and Media Release
26 July 2023
Notes:
• Mineral Resource Estimate is inclusive of declared Ore Reserves
• Mineral Resources are reported in accordance with JORC (2012)
• Cut-off values are reported applying a gold price of US$1500/oz and ZAR 15.00/1 US$
• All Mineral Resources exclude geological structural loss
• Any discrepancies in totals are due to rounding
• CW: Channel Width
• SW: Stoping Width
The following tonnage discount factors have been applied for unknown geological losses:
• 5% for the Measured Mineral Resource Category
• 10% for the Indicated Mineral Resource Category
• 15% for the Inferred Mineral Resource Category
Cut-off Grade: 2.0 g/t
Density: 2.73 t/m³
K9B REEF JORC (2012) COMPLIANT MINERAL RESOURCE ESTIMATE2
Au
Au
sw
cw
Tonnes
Resource Category
(Millions) (MOz) (g/t) (cm) (cm)
Measured
1.9
0.27 4.37 154 153
Indicated
6.2
0.83 4.14 162 162
Measured and Indicated
8.1
1.10 4.20 160 160
Au
(cm.g/t)
672
672
672
Inferred
2.4
0.4
5.5
123
123
675
Grand Total
10.5
1.5
4.5
150
149
673
Note: Errors may occur due to rounding differences
Notes:
• Mineral Resource Estimate is inclusive of declared Ore Reserves
• Mineral Resources are reported in accordance with JORC (2012)
• Cut-off values are reported applying a gold price of US$1500/oz and ZAR 15.00/1 US$
• All Mineral Resources exclude geological structural loss
• Any discrepancies in totals are due to rounding
• CW: Channel width
• SW: Stoping width
The following tonnage discount factors have been applied for unknown geological losses:
• 5% for the Measured Mineral Resource Category
• 10% for the Indicated Mineral Resource Category
• 15% for the Inferred Mineral Resource Category
Cut-off Grade: 2.0 g/t
Density: 2.73 t/m³
page ix
ASX Announcement and Media Release
26 July 2023
MINE PLAN UPDATE
The integrated LOM plan created for the DFS update in August 2022 has been further updated for the
following:
• Confirmation of mining blocks immediately available for mining in the old mine area by access,
survey and sampling
• Change to the dip of the orebody based on actual survey measurements
• Inclusion of additional Mineral Resources previously not accounted for in the LOM plan
Figure 1 shows a production profile of the 2022 plan compared to the 2023 update.
900
4.5
800
4.0
700
3.5
600
3.0
500
2.5
400
2.0
300
1.5
200
1.0
100
0.5
-
ROM Grade [g/t]
Ore Tonnes [kt]
FIGURE 1: 2023 UPDATE VS 2022 LOM PLAN
0.0
1
2
3
4
5
6
7
8
9
10 11 12 13 14 15 16 17 18
Project Year
Ore Tonnes - Jun-23
Ore Tonnes - Aug-22
ROM Grade - Jun-23
ROM Grade - Aug-22
The 2023 mine plan update shows an improvement in production rate, as well as a longer LOM due to
an increase in the mining inventory.
The updated LOM schedule and inventory produced are shown in the figures and tabulations below.
It is specifically noted that in undertaking the update to the mine plan, the mining method and mining
productivities used were left unchanged from those used in the 2021 DFS1 as well as the DFS update
completed in 2022. The only difference between the mining plans relates to mining sequence and
timing.
The conventional breast mining in an underhand configuration is the optimal method for the Qala
Shallows deposit.
The stopes will be accessed by strike drives developed on the K9B Reef horizon and both K9A and K9B
stopes will be accessed from this infrastructure. The strike drives will connect to a decline system
developed from the existing Qala Adit box cut, which will be located centrally in the mining area and
in the footwall of the K9B Reef.
Most of the mining will take place in a large unmined block of ground to the east of the property. There
will however also be limited mining of pillar remnants on the western side of the mining area. All
mining in the western areas will take place above the flooded historical workings and a water pillar will
be left between the eastern workings and the flooded areas to minimise pumping requirements.
Figure 2 shows a plan of a typical stope block.
page x
ASX Announcement and Media Release
26 July 2023
FIGURE 2: PLAN OF STOPE BLOCK
Mining in the stope blocks will use standard conventional mining techniques widely used in South
Africa with the deployment of hand-held drills mounted on jack legs with cleaning using a scraper and
winch combination. Support will also be installed manually with a combination of rock bolts and
timber poles.
Development of the strike drives and decline will be with mechanised methods including drill rigs, LHDs
and ADTs deployed for drilling, face cleaning and hauling of blasted rock to the tips respectively.
To estimate the quality and quantity the Run-of-Mine (“ROM”) material that will be mined and
delivered to surface, various modifying factors will be applied to the in-situ Mineral Resource. These
modifications must consider anything that will impact the grade of the material and/or the tonnage of
material delivered to surface. In the case of Qala Shallows, the following modifying factors will be
included:
•
Estimation of any dilution that will be incurred in the mining process whether planned or
unplanned and adjustment of the grade and tonnage of the mined material accordingly
•
Estimation of any gold loss that may be incurred during the mining process (reduction in
grade)
•
Estimation of pay limit grades to ensure that only payable material is mined and delivered to
surface
•
Exclusion of any pillars that are required to be left in-situ for ground stabilisation purposes
•
Exclusion of any material that is not practical for economic or technical reasons
•
Application of a 5% ore tonnage loss due to inefficiencies in the mining process
Figure 3 shows the updated Qala Shallows production profile indicating waste and ore tonnes, as well
as recovered gold production in ounces. The project has a steady-state gold production of
approximately 70,000 oz per annum for approximately 9 years.
page xi
ASX Announcement and Media Release
26 July 2023
FIGURE 3: QALA SHALLOWS PRODUCTION PROFILE
Figure 4 outlines additional detail of the first 60 months of the LOM schedule and the build-up period
to full production after 3 years.
FIGURE 4: QALA SHALLOWS PRODUCTION BUILD UP FIRST 60 MONTHS
Based on the mine layout and the modifying factors discussed above a mine development and
production schedule was generated by calculating estimated mining productivities by excavation and
sequencing the layout in a logical order. All mine layouts and scheduling were undertaken in the
Deswik suite of mine design and scheduling software.
Key production schedule points are listed in Table 2.
page xii
ASX Announcement and Media Release
26 July 2023
TABLE 2: SCHEDULE KEY POINTS
SCHEDULE KEY POINTS
First Gold production
First Stope production
4 months
5 months
Measured and Indicated Resources
Sustainable full production
Full production sustained
Life-of-Mine
52,000t pm
3.3 years
10.4 years
All Mineral Resources
Sustainable full production
Full production sustained
Life-of-Mine
62,000t pm
12 years
17.7 years
Table 3 outlines production data highlights from the updated 2023 LOM plan. The table shows an
improvement from the 2022 DFS plan in regard to total ROM tonnage, as well as the maximum
production rates and gold produced as described above.
TABLE 3: UPDATED DFS PRODUCTION DATA (INCLUSIVE OF INFERRED RESOURCES)
Item
Life-of-Mine (Construction to Relinquishment)
Total Production (Run-of-Mine)
Max Production Rate (Tonnes)
Run-of-Mine Grade Au (Average)
LOM Contained Au
Metallurgical Recovery Au (Overall)
Gold Produced
Average Annual Gold Production
Average Annual Steady State Gold Production (9 years)
Max Gold Production (Year 6)
Outcome
17.7 years
10.2 million
839,000 pa
3.04 g/t Au
1,005,000 oz
92%
924,000 oz
51,000 oz
70,000 oz
75,000 oz
1 Including Inferred Resources
Table 4 shows the production data profile for Measured and Indicated. The corresponding results from
the 2022 DFS are also stated with the variance between the two plans.
TABLE 4: RUN OF MINE INVENTORY (MEASURED AND INDICATED)
Resource category
(Updated – June 2023)
Measured
Indicated
Inferred
Totals
Tonnes (t)
Resource category
(August 2022)
Measured
Tonnes (t)
1 008 000
3 492 000
4 500 000
880 000
Grade (g/t)
2.93
2.62
2.69
Grade (g/t)
3.00
Au Content
(kg)
2 949
9 135
12 084
Au Content
(oz)
95 000
294 000
389 000
Au Content
(kg)
2 636
Au Content
(oz)
85 000
page xiii
ASX Announcement and Media Release
26 July 2023
Indicated
Inferred
Totals
2 741 000
3 621 000
Resource category
(Variance)
Measured
Indicated
Inferred
Totals
Tonnes (t)
128 000
751 000
879 000
2.69
2.77
7 385
10 022
237 000
322 000
Grade (g/t)
Au Content
(kg)
313
1 750
2 062
Au Content
(oz)
10 000
57 000
67 000
-0.07
-0.07
-0.08
It is specifically noted that the above inventory includes the Measured and Indicated Mineral
Resources only, Inferred Resources are excluded. However, the Inferred Mineral Resources are largely
located in areas that will be accessed by the primary development to access and mine the Measured
and Indicated Mineral Resources. Relatively limited additional development will be required to access
and mine the Inferred Mineral Resources in these areas and because of this, mine layouts and mining
inventories have also been developed for the Inferred Mineral Resources.
Table 5 outlines the mining inventory, including all mineral resource categories (Measured, Indicated
and Inferred) and accounting for all modifying factors as described above.
TABLE 5: RUN OF MINE INVENTORY (MEASURED, INDICATED AND INFERRED)
Resource category
(Updated 2023)
Measured
Indicated
Inferred
Totals
Tonnes (t)
Resource category
(DFS Update 2022)
Measured
Indicated
Inferred
Totals
Tonnes (t)
Resource category
(Variance)
Measured
Indicated
Inferred
Totals
Tonnes (t)
1 008 000
3 492 000
5 778 000
10 278 000
880 000
2 741 000
3 970 000
7 591 000
128 000
751 000
1 808 000
2 687 000
Grade (g/t)
2.93
2.62
3.32
3.04
Grade (g/t)
3.00
2.69
3.18
2.99
Grade (g/t)
-0.07
-0.07
0.14
0.05
Au Content
(kg)
2 949
9 135
19 156
31 240
Au Content
(oz)
95 000
294 000
616 000
1 004 000
Au Content
(kg)
2 636
7 385
12 640
22 661
Au Content
(oz)
85 000
237 000
406 000
729 000
Au Content
(kg)
313
1 750
6 516
8 579
Au Content
(oz)
10 000
57 000
210 000
275 000
Note that in both tables, including and excluding Inferred Mineral Resources, there is an increase in
tonnages and gold produced over the LOM. The LOM grade has only very minor variation between the
two plans.
Figures 5 and 6 show production profiles for the Measured and Indicated and All Mineral Resources
respectively, as well as the relevant waste tonnages and grade.
page xiv
ASX Announcement and Media Release
26 July 2023
FIGURE 5: PRODUCTION PROFILE (MEASURED & INDICATED RESOURCES)
FIGURE 6: PRODUCTION PROFILE (ALL MINERAL RESOURCES)
Figure 7 displays the ore production and associated grade by Mineral Resource category. It is clearly
seen that the majority of early production is from the Measured and Indicated categories.
page xv
ASX Announcement and Media Release
26 July 2023
800
5.00
4.50
4.00
3.50
3.00
2.50
2.00
1.50
1.00
0.50
-
Ore Tonnes [ktpa]
700
600
500
400
300
200
100
1
2
3
4
5
6
7
8
9
ROM Grade [g/t]
FIGURE 7: LOM SCHEDULE SHOWING PROPORTION OF PRODUCTION FROM MEASURED,
INDICATED AND INFERRED MINERAL RESOURCES
10 11 12 13 14 15 16 17 18 19
Year
Ore Tonnes - Measured
Ore Tonnes - Indicated
Ore Tonnes - Inferred
Ore Tonnes - Proven & Probable
ROM Grade - Measured
ROM Grade - Indicated
ROM Grade - Inferred
ROM Grade - Proven & Probable
The production schedule contains a portion of Inferred Mineral Resources. There is a low level of geological confidence
associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the
determination of Indicated Mineral Resources or that the Production Target itself will be realised.
The requirements for TMM equipment were validated against the updated production plan. An
additional one 30-tonne truck is required for rock transportation in the decline to surface and an
additional one 20-tonne truck is required for rock transportation on level. The total number of trucks
increased from 10 to 12. The requirements in terms of other TMM equipment remained the same.
The ventilation requirement for the new mining plan was evaluated and the ventilation design
modified. The increased fleet size required an increase of the size of the primary intake ventilation
raise, which increased from 3.0m x 3.0m to 4.0m x 4.0m. The size of other intake or return airways did
not increase.
Additional conventional mining equipment is required to achieve the increased production rate and as
such, the number of equipped half levels was increased from 5 to 6. The additional half level equipment
comprises all conventional equipment such as winches, rock drills, and ancillaries required to achieve
the increased steady state production rate.
While the size of the dewatering, service water and compressed air underground services were
deemed to be of suitable capacity for the increased production requirement, the size of the main
electrical reticulation cables was increased for the increased underground loads brought on by
equipping the additional half level.
The total estimated labour requirement increased from 916 to 1065 people including provisions for
leave and absenteeism. The surface infrastructure design was validated and confirmed to be
appropriate in size with respect to the increased labour complement.
page xvi
ASX Announcement and Media Release
26 July 2023
ORE PROCESSING
The Reefs to be processed during the life of the project are the two Kimberley Reefs, K9A and K9B. The
Kimberley Reef is a free milling ore containing minor quantities of sulphides, mainly pyrite. Gold
dissolution is generally of the order of 94% to 95%. Kimberley Reef ore has been processed in several
metallurgical plants on the Witwatersrand in the past. A 92% metallurgical recovery has been allowed
for in the project evaluation.
The Kimberley Reef ore produced at Qala Shallows will be treated at an existing nearby plant on a toll
treatment basis. A toll treatment agreement has been signed with the Ezulwini Proc