ASX Announcement and Media Release
Friday, 26 June 2026
NEBARI LOAN FACILITY REPAID — FINANCIAL CLOSE OF ZAR
875M SA SENIOR LOAN FACILITY IMMINENT
HIGHLIGHTS
➢ Nebari Loan Facility repaid in full to release all obligations and security, as part of
satisfying the final condition precedents for financial close of the ZAR 875M (~USD 53M)
senior loan facility with Absa Bank and Nedbank CIB (“SA Senior Loan”).
➢ Financial close and first drawdown of the SA Senior Loan expected imminently.
➢ SA Senior Loan provided by Absa Bank and Nedbank CIB — two of South Africa’s leading
mining finance institutions — is a strong institutional endorsement of West Wits and the
Qala Shallows Project.
➢ Nebari’s loan facility, secured in H2 2025, enabled the operational ramp-up and gave West
Wits the funding optionality to progress full project development — the Company
acknowledges Nebari as a nimble and pivotal funding partner in the development of Qala
Shallows.
➢ The SA Senior Loan fully funds Qala Shallows towards the steady-state production of
~70,000oz Au per annum (DFS NPV7.5 USD 500M, 81% IRR at USD 2,850/oz)2.
West Wits Managing Director and CEO, Rudi Deysel, said:
“Repaying the Nebari Facility and clearing the path to financial close of the SA Senior Loan is a
significant milestone for West Wits and our shareholders. Nebari played a genuinely pivotal role in our
development — their willingness to move quickly and pragmatically in H2 2025 gave us the operational
momentum and funding optionality that made this outcome possible, and we are grateful for their
partnership. With financial close of the SA Senior Loan now imminent, our focus is entirely on executing
the final steps to drawdown and accelerate the Qala Shallows ramp-up toward steady-state
production.”
REPAYMENT OF NEBARI LOAN FACILITY
West Wits Mining Limited (ASX: WWI) (OTCQB: WMWWF) (“West Wits” or the “Company”)
is pleased to announce it has repaid the Nebari loan facility (the “Nebari Facility”) in full, being
the USD 12.5M (Tranche 1 Loan Facility Amount) advanced by Nebari Natural Resources Credit
Fund II LP (“Nebari”) and drawn down in November 2025.
Repayment of the Nebari Facility enables the release of all associated obligations and security
as part of satisfying the condition precedents for financial close of the ZAR 875 million (approx.
USD 53M) SA Senior Loan Facility with Absa Bank Limited (“Absa Bank”) and Nedbank Limited
Page | ii
(acting through its Nedbank Corporate and Investment Banking division) (“Nedbank CIB”). The
Company is in the final stages of documentation and expects to achieve financial close and
first drawdown imminently.
West Wits wishes to formally recognise the important role played by Nebari throughout the
development of the Qala Shallows Project. Drawdown of the USD 12.5 million Tranche 1 in
November 2025 — as part of a scalable USD 35 million funding package — provided critical
capital at a pivotal stage, directly enabling the ramp-up of underground operations, the
purchase of critical plant and equipment, and the continued ore delivery to Sibanye-
Stillwater’s Ezulwini processing plant.
SA SENIOR LOAN FACILITY — COMPLETING THE FUNDING STRUCTURE
The ZAR 875 million (~USD 53 million) SA Senior Loan is a syndicated project finance facility
arranged with Absa Bank Limited and Nedbank CIB, two of South Africa’s largest and most
experienced mining finance institutions. The execution of definitive agreements for this
facility as announced on 19 June 2026, with the facility first being announced on 21 May 2026,
represents a strong institutional endorsement of the Qala Shallows Project’s technical
credentials and commercial viability.
PATH TO PRODUCTION
The Qala Shallows Project represents Stage 1 of West Wits’ Witwatersrand Basin Project
(WBP), which hosts a Global JORC Mineral Resource Estimate of 7.24Moz @ 4.0g/t Au1 within
one of the world’s most prolific and proven gold districts. West Wits achieved first gold
production from Qala Shallows in October 2025 and completed its inaugural gold pour at
Sibanye-Stillwater’s Ezulwini processing plant on 17 March 2026. The Company is now in its
production ramp-up phase, with underground development advancing.
The SA Senior Loan completes the funding structure required to advance Qala Shallows to
steady-state production. The updated DFS (July 2025) outlines a 16.8-year mine life producing
a total of 944,000oz Au, with steady-state output of approximately 70,000oz per annum at an
AISC of USD 1,181/oz2. At a gold price of USD 2,850/oz, the project delivers a post-tax NPV7.5
of USD 500 million and an IRR of 81% with an 8-month payback from end of the peak funding
period.²
Key near-term milestones include:
➢ Financial close and first drawdown of the ZAR 875M SA Senior Loan (expected imminently)
➢ Continued underground development to unlock additional stoping and mining areas
➢ Progressive increase in ore delivery rates to the Ezulwini processing plant
➢ Grid power connection (targeted Q4 2026) to improve cost efficiency
➢ Advancement of the Project 200 Scoping Study, targeting an aspirational production
profile of ~200,000oz per annum
Page | iii
Approved for release by the Managing Director and CEO, Rudi Deysel.
For further information contact:
Jessica Fertig, Investor Relations
IR@westwitsmining.com
General info@westwitsmining.com
www.westwitsmining.com
ABOUT WEST WITS MINING LIMITED
West Wits Mining Limited (ASX: WWI) (OTCQB: WMWWF) is focused on the exploration,
development and production of high-value precious and base metals for the benefit of
shareholders, communities and environments in which it operates. Witwatersrand Basin
Project, located in the proven gold region of Central Rand Goldfield of South Africa, boasts a
7.24Moz gold project at 4.0g/t1. The Witwatersrand Basin is a largely underground geological
formation which surfaces in the Witwatersrand. It holds the world's largest known gold
reserves and has produced over 1.5 billion ounces (over 40,000 metric tons), representing
about 22% of all the gold accounted for above the surface.
1. The original report was “2.2Moz Increase to WBP Global Resource Estimate to 7.24Moz ” which was issued with consent
of the Competent Person, Mr Hermanus Berhardus Swart. The report was released to the ASX on 02 February 2026 and
can be found on the Company’s website (https://westwitsmining.com/). Comprising 14.08MT at 4.40g/t for 1.99Moz
Measured, 15.55MT at 4.04g/t for 2.02Moz Indicated and 26.81MT at 3.75g/t for 3.23Moz Inferred. The Company is not
aware of any new information or data that materially effects the information included in the relevant market
announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially
changed. The form and context in which the Competent Person’s findings are presented have not been materially
modified from the original market announcement.
2. The original report was “Updates to DFS provide Improved Results for WBP” which was issued with consent of the
Competent Person, Mr. Andrew Pooley. The report was released to the ASX on 23 July 2025 and can be found on the
Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that
materially effects the information included in the relevant market announcement and, in the case of Mineral Resources
or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed. The form and context in which the Competent
Person’s findings are presented have not been materially modified from the original market announcement. The DFS and
any production target under the DFS contain inferred mineral resources. The directors confirm that it is reasonable to
include these inferred mineral resources in the well-understood and researched structure of the Witwatersrand Basin and
the views provided to West Wits by independent geological expert consultants, given the project’s location and geology.