August 2023
Michael Quinert : Chairman
COPYRIGHT ©2023 ALL RIGHTS RESERVED
Qala Shallows, Witwatersrand Basin Project,
Gauteng Mining District, Johannesburg
South Africa
ASX:WWI | OTCQB: WMWWF
DISCLAIMER
This presentation may contain certain forward-looking statements that have been based on current expectations about future acts, events and circumstances. These forward-looking statements are, however,
subject to risks, uncertainties and assumptions that could cause those acts, events and circumstances to differ materially from the expectations described in such forward-looking statements.
These factors include, among other things, commercial and other risks associated with estimation of resources, the meeting of objectives and other investment considerations, as well as other matters not yet
known to West Wits Mining or not currently considered material by the company. West Wits Mining accepts no responsibility to update any person regarding any error or omission or change in the information in
this presentation or any other information made available to a person or any obligation to furnish the person with further information.
Forward-Looking Statements
This presentation includes “forward-looking statements” as that term within the meaning of securities laws of applicable jurisdictions. Forward-looking statements involve known and unknown risks,
uncertainties and other factors that are in some cases beyond West Wits Mining Limited’s control. These forward-looking statements include, but are not limited to, all statements other than statements of
historical facts contained in this presentation, including, without limitation, those regarding West Wits Mining Limited’s future expectations. Readers can identify forward-looking statements by terminology such
as “aim,” “anticipate,” “assume,” “believe,” “continue,” “could,” “estimate,” “expect,” “forecast,” “intend,” “may,” “plan,” “potential,” “predict,” “project,” “risk,” “should,” “will” or “would” and other similar
expressions. Risks, uncertainties and other factors may cause West Wits Mining Limited’s actual results, performance, production or achievements to differ materially from those expressed or implied by the
forward-looking statements (and from past results, performance or achievements).
These factors include, but are not limited to, the failure to complete and commission the mine facilities and related infrastructure in the time frame and within estimated costs currently planned; variations in
global demand and price for gold and silver; fluctuations in exchange rates between the U.S. Dollar, South African Rand and the Australian Dollar; the failure of West Wits Mining Limited’s suppliers, service
providers and partners to fulfil their obligations under construction, supply and other agreements; unforeseen geological, physical or meteorological conditions, natural disasters or cyclones; changes in the
regulatory environment, industrial disputes, labour shortages, political and other factors; the inability to obtain additional financing, if required, on commercially suitable terms; and global and regional economic
conditions. Readers are cautioned not to place undue reliance on forward-looking statements. The information concerning possible production in this announcement is not intended to be a forecast. They are
internally generated goals set by the board of directors of West Wits Mining Limited. The ability of the Company to achieve any targets will be largely determined by the Company’s ability to secure adequate
funding, implement mining plans, resolve logistical issues associated with mining and enter into any necessary off take arrangements with reputable third parties. Although West Wits Mining Limited believes that
its expectations reflected in these forward-looking statements are reasonable, such statements involve risks and uncertainties and no assurance can be given that actual results will be consistent with these
forward-looking statements.
Competent Person Statements
The original report was “Updates to Qala Shallows DFS provide improved results for Witwatersrand Basin Project” which was issued with consent of the Competent Person, Mr. Andrew Pooley. The report was
released to the ASX in July 2023 and can be found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the information
included in the relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed. The form and context in which the Competent Person’s findings are presented have not been materially modified from the original market
announcement.
The original report was “WBP’s Global JORC Mineral Resource Expands by 724,000oz to 4.28MOZ at 4.58 g/t Gold” which was issued with consent of the Competent Person, Mrs Cecilia Hattingh. The report was
released to the ASX on 3 December 2021 and can be found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the
information included in the relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the
relevant market announcement continue to apply and have not materially changed. The form and context in which the Competent Person’s findings are presented have not been materially modified from the
original market announcement.
ASX:WWI
PAGE |
2
CORPORATE SNAPSHOT
§
ASX-listed minerals exploration & mining company focused on gold / strategic metals
§
Management team experienced in building exploration & mining companies
§
Internationally-based and investor-focused board
§
Two projects in stable jurisdictions
§
Revenue opportunity of USD 2.6 billion2
CAPITAL STRUCTURE (ASX:WWI)
Shares on issue
2.321B
Unlisted Options
137M
Market Capitalisation
@1.8c per share on 31/07/2023
$41.7M
Cash : 30/06/2023
A$1.36M
Enterprise Value per ounce
A$10.71/oz
JORC Mineral Resource Estimate3 (Gold)
includes declared Ore Reserves
4.28Moz
Commodity Exposure
Gold, Uranium
ASX:WWI
PAGE |
3
SHARE PRICE & VOLUMES
SHAREHOLDER BREAKOWN
ASX: WWI
https://www2.asx.com.au/markets/company/wwi
5%
38%
48%
9%
BOARD & MANAGEMENT
TOP 20 SHAREHOLDERS
TOP 21-50 SHAREHOLDERS
RETAIL
TOP 10 SHAREHOLDERS
Wingfield Durban Deep LP
9.03%
Citicorp Nominees
5.31%
BNP Paribas Nominees
2.82%
Supernova Fund
2.54%
BNP Paribas Nominees
2.42%
BNP Paribas Nominees
2.37%
DRD Gold Limited
2.14%
Realstar Finance
1.92%
Mr Ronald Werner Neugebauer & Miss Tess
Caitlin Neugebauer
1.91%
Kastin
1.87%
TOTAL
32.33%
ASX:WWI
PAGE |
4
INVESTOR-FOCUSED INTERNATIONAL BOARD
Australia
WWI Chairman
South Africa
MLI WWI Executive
Director/Head of
Corporate Affairs
South Africa
WWI Non-Executive
Director
USA
WWI Non-Executive
Director
South Africa
WWI Non-Executive
Director
Australia
WWI Non-Executive
Director
Michael Quinert
ASX-experienced
commercial lawyer
with extensive
involvement in
assisting and
advising publicly
listed mining
companies
Tozama Kulati
Siwisa
BCom with MBA with
extensive experience
in ESG management
having worked at
Lonmin plc prior to
joining West Wits
Hulme Scholes
One of SA’s top legal
professionals
specialising in
mining and mineral
law
Peter O’Malley
US-based investment
finance executive
with wide-ranging
experience advising
on
M&A, debt/equity
transactions and
capital optimisation
strategies in multiple
jurisdictions
Jac van Heerden
Mining Engineer with
MBA and operations
and project
experience in South
Africa, DRC and
Zimbabwe
Warwick Grigor
Experienced mining
analyst who founded
Far East Capital
Limited, a specialist
mining company
financier and
corporate adviser
ASX:WWI
PAGE |
5
EXPERIENCED MANAGEMENT TEAM
ASX:WWI
Chief Operations
Officer/Country Manager
(RSA)
Executive Manager
Commercial
Chief Financial
Officer/Company Secretary
Head of Geology and
Exploration
Rudi Deysel
Mining Engineer with
Geophysics and MBA and
extensive production
experience in conventional
narrow tabular underground,
as well as open cast, mining
various commodities
including Gold, PGMs, Copper
and Cobalt
Keith Middleton
Experienced Executive of ASX
listed companies specialising
in the Australian and
international resources
sector; highly skilled in
financial analysis, risk
management, major capital
works expenditure, corporate
governance and ESG
regulations
Simon Whyte
Chartered Accountant with
extensive experience in
mining, commodities and
logistics which includes
global majors, Ernst & Young
and BP, prior to joining West
Wits
Martin Bevenlander
Geologist with expertise
that spans across the
entire mining cycle, from
grassroots exploration,
project design to
exploration project
management. Worked in
Indonesia, Papua New
Guinea, Australia, and
across Africa
PAGE |
6
WEST WITS MINING LIMITED : COMPANY OVERVIEW
West Wits Mining is a dual-listed : ASX (WWI) & OTCQB (WMWWF) exploration and development company with a focus on two premier regions:
§
Witwatersrand (South Africa)
§
Eastern Pilbara (Western Australia)
West Wits is undertaking a strategic transformation to position itself as a mid-tier gold producer.
The Witwatersrand Supergroup consists of the lower West Rand Group, and the Central Rand Group, in which the majority of the gold bearing
conglomerates is located.
Our flagship Witwatersrand Basin Project (WBP), is located in the Central Rand Goldfield, which historically produced over 247 million ounces.
The WBP presents a revenue opportunity of USD 2.6 billion.
The Central Rand Group contains the Kimberley Reefs which are the target reefs for mining at Qala Shallows.
In the Paterson Province, Western Australia, a maiden drilling program at West Wits' 100% owned Mt Cecelia Project was completed in December
2022, hitting significant gold intercepts.
Targeting gold, nickel and copper, the exploration program is managed by Rio Tinto (RIO) under a A$10M Farm-In/JV Agreement for RIO to earn up to
80% interest in the project.
ASX:WWI
PAGE |
7
WEST WITS MINING LIMITED : PROJECT SUMMARY
The South African Witwatersrand Basin Project, is a largely underground geological formation which surfaces in the Witwatersrand.
It holds the world's largest known gold reserves and has produced over 1.5 billion ounces (over 40,000 metric tons)
The Witwatersrand Basin Project is an ambitious undertaking involving the development of three mining reefs:
1. Kimberly Reef
2. Bird Reef
3. Main Reef
Our flagship project within this development is Qala Shallows, situated on the Kimberly Reef.
Our recently released and updated Definitive Feasibility Study for Qala Shallows outlines a gold production of 924,000 ounces over an 18-year Life-of-Mine, with a steady-state
production of around 70,000 ounces per year.
The updated financial metrics truly underscore the value and profitability of the Qala Shallows Project.
We're anticipating an impressive Project NPV of US$255 million, leading to a total free-cash flow generation of US$522 million.
Significantly we have received a formal letter of interest for debt funding amounting to nearly US$16 million from the Industrial Development Corporation of South Africa (IDC).
The IDC is a prominent development finance institution dedicated to driving economic growth and industrial development in South Africa.
With the formal expression of interest and terms from the IDC, we're poised for exciting progress at Qala Shallows.
We'll proceed to complete the due diligence process with the IDC, secure funding, mobilise the mining contractor and equipment to the site, and begin building up to mine to
around 5,700 ounces of gold per month.
ASX:WWI
PAGE |
8
WEST WITS MINING LIMITED : MINING TARGETS
West Wits Mining (West Wits) holds a mining right, (GP 30/5/1/2/2/10073 MR) granted in July 2021, for the Witwatersrand Basin Project (WBP) located approximately 15 km to
the west of the city of Johannesburg in the Gauteng Province of South Africa.
There are a significant number of old mine workings in the area, the (WBP) is focused on two of these existing but closed mining sites located on the Rand Leases Gold Mine
(RL) and the Durban Roodepoort Deep Gold Mine (DRD).
There are a number of historically economic reef horizons in these areas which include
§
§
§
Kimberley Reefs (K9A and K9B)
The Bird Reef (BR)
Main Reef (MR)
§ Main Reef Leader (MRL)
The four existing sites identified are listed below together with the reef horizons to be found at each site.
1) Qala Project Site (RL)
§
§
This site is made up of the Qala Incline Shaft
The site has been divided into discrete mining areas being Qala Shallows and Qala Deeps
§ This project site hosts: K9A Reef and K9B Reef
2) No. 11 Shaft area - Bird Reef (RL)
§ Bird Reef horizon to be accessed from Qala Shallows underground infrastructure
3) No. 6 and 7 Shafts (RL) hosting: Main Reef and Main Reef Leader opportunities
4) Circular Shaft (DRD) hosting: Bird Reef – Uranium Exploration Target
ASX:WWI
PAGE |
9
WITWATERSRAND BASIN PROJECT (WBP)
Mineral Resource Estimate
WBP MINERAL RESOURCE ESTIMATE (JORC 2012)
§
§
§
Significant global Mineral Resources of 4.28 Moz gold
resource @ 4.58 g/t Au
3 distinct Reef horizons: Kimberley Reef; Bird Reef;
Main Reef
Prospecting Right approval expected: will re-introduce
a substantial portion of previous Mineral Resource
WBP MINERAL RESOURCE (JORC 2012)2
Category
Tonnage (Mt)
Grade (g/t)
Content (oz)
Measured
8.8
4.60
1 449 000
Indicated
11.26
4.19
1 517 000
Measured & Indicated
21.06
4.38
2 967 000
Inferred
7.98
5.10
1 309 000
Total
29.05
4.48
4 276 000
ASX:WWI
Location of Mineral Resource Estimate within the Mining Right
PAGE |
10
WITWATERSRAND BASIN PROJECT (WBP)
Qala Shallows Ore Reserve
QALA SHALLOWS ORE RESERVE
The updated DFS released to market (July 2023)
Reserve base increased by 21% (increase of 61,400 oz)
Grand total of 4.03 million tonnes at 2.71g/t for
351,400 oz gold
This reserve as a standalone asset is economically
viable
§
§
§
§
ORE RESERVE STATEMENT FOR QALA SHALLOWS AT 30 JUNE 2023 (JORC 2012)1
Reef Type
K9A
FORWARD LOOKING WORKPLAN
§
§
§
§
Funding to be used in the mobilisation of key
resources to initiate mining operations
Will enable a robust 30,000-tonne ore stockpile
to facilitate a steady delivery of 15 kilo tonnes per
month to Sibanye-Stillwater’s plant
Targeting achievement of the stockpile & delivery
within 5 months, from start of production
Gradual mine build-up towards a steady-state
production of 5,700 ounces of gold per month
K9B
Grand Totals
Ore Reserve
Category
Tonnage
(Mt)
Grade
(g/t)
Content
(kg)
Content
(oz)
Proved
0.48
3.20
1 550
49 825
Probable
0.50
2.41
1 209
38 871
Total K9A
0.99
2.80
2 759
88 695
Proved
0.48
2.71
1 297
41 711
Probable
2.56
2.68
6 874
221 017
Total K9B
3.04
2.69
8 172
262 728
Proved
0.96
2.96
2 847
91 536
2.64
8 083
259 887
2.71
10 930
351 424
Probable
Total
ASX:WWI
3.07
4.03
PAGE |
11
QALA SHALLOWS
Fast-tracked Monetisation
US$1.7B REVENUE OPPORTUNITY
§
§
§
§
ASX:WWI
Estimated peak funding of US$54m (ZAR 943M) over a
three-year period
All-in-Sustaining Cost (AISC) of Life-of-Mine (LOM):
US$977/0z
Higher OPEX and CAPEX resulting from increased
production have been offset by revenue from increased
production during the 3-year funding period and favourable
movements in the Gold Price and South African Rand
South African Industrial Development expressed formal
interest in providing loan funds of ZAR300 million
(~US$15.9 million) for development capital
Qala Shallows Financial Evaluation 1
AUG-22
JUL-23
Total Revenue (USD)
$ 1 170 million
$ 1 709 million
Total Free Cashflow (USD)
$ 268 million
$ 552 million
Peak Funding (USD)
$ 63 million
$ 53 million
LOM C1 Cost (USD/oz)
$ 917 / oz
$ 818 / oz
LOM All-In Sustaining Cost (USD/oz)
$ 1 093/oz
$ 977/oz
Steady-State All in Sustaining Cost (USD/oz)
$ 962 /oz
$ 871 /oz
Payback (years)
5.0 years
4.1 years
Pre-Tax Net Present Value 7.5 (USD)
$ 180m
$ 367m
Post-Tax Net Present Value 7.5 (USD)
$ 125m
$ 255m
Pre-Tax Internal Rate of Return (%)
38%
61%
Post-Tax Internal Rate of Return (%)
32%
53%
PAGE |
12
QALA SHALLOWS –DFS on KIMBERLY REEF
ROBUST DEFINITIVE FEASIBILITY STUDY
§
Gold produced: 924,000oz
§
Steady-State production: 70,000oz p/a (9 years)
§
Ore Reserves : 4.03 million tonnes at 2.71g/t for
351,4000 oz gold
§
Life-of-Mine: 17.7 years
RAPID PRODUCTION GROWTH
§
Critical infrastructure completed
§
Decline & box cut rehabilitation completed
§
Mining blocks available by access
§
Advanced infrastructure set up for rapid nearterm production ramp-up
“We’ve got plenty of gold and even at 70,000 ounces a
year, we are only scratching the surface of what this ore
body can deliver.”
Michael Quinert, Chairman
ASX:WWI
Underground workings
Underground
production plan
PAGE |
13
THE VALUE PROPOSITION
Qala Shallows Annual Production Schedule
§
Qala Shallows robust DFS earmarked to produce 924,000oz1
§
Advanced understanding of geology & project economics
§
Qala Shallows steady-state production of 70,000oz p/a1
§
ESG baseline testing & environmental authority
§
Already produced ore stockpile suitable for nearby plant with toll
treatment agreement (Sibanye-Stillwater)
§
Mine permitting & social license
§
Surface & underground infrastructure in place for rapid production growth
§
Metallurgy program completed & delivered processing flowsheet
ASX:WWI
PAGE |
14
WBP WORK PROGRAM
Q1 2023
Q2 2023
Q3 2023
Q4 2023
Q1 2024
Q2 2024
Witwatersrand Basin Project
Short-term and med-term production
plan completion
Water Use Licence approved by Department of
Water Affairs
Explosive Permits approvals from
South African Police Services
Accurate reconciliation between historical
mined-out areas and future production
planning, with underground survey data
7.5 MVA Power allocation from City Power
Johannesburg
LOM updated with new data
Potable water allocation from Johannesburg
Water
DFS updated based on updated LOM
Water pipeline completed & connection
commissioned
Electrical cable trenching
ASX:WWI
PAGE |
15
MT CECELIA PROJECT
GREENFIELDS GOLD PROJECT
Paterson East/ Pilbara Province
Western Australia
Mt Cecelia Project, Pilbara Province,
Western Australia
ASX:WWI | OTCQB: WMWWF
MT CECELIA PROJECT
Key Milestones
KEY MILESTONES
§
§
§
§
§
§
§
§
ASX:WWI
2018: Desktop study – re-interpretation of the regional geology and
structure
2020: Completed heliborne electromagnetic survey - identified 8
priority EM targets5
August 2021: Completed ground geophysical MLTEM surveys: top 4
priority drill targets (SGC1-4) defined with legitimate bedrock
conductors
December 2021: Earn-in & JV agreement with Rio Tinto Exploration
up to $10M & up to 80% interest (RTX wholly owned subsidiary of
Rio Tinto Limited
March 2023: Assay results from completed maiden drilling program
on SGC_1 target comprised of 4 Reverse Circulation holes @
~1,036m
May 2023: Downhole Electromagnetic (DHEM) survey @ SGC_1
across 4 holes to guide diamond drill testing of target using existing
heritage cleared areas & commencement of 2023 Exploration
Program to enhance understanding of anomalies
July 2023: RTX completed DHEM survey
Ongoing : Results and target evaluation
PAGE |
17
MT CECELIA WORK PROGRAM
Q4 2022
Q1 2023
Q2 2023
Q3 2023
Q4 2023
Mt Cecelia Project
Maiden Drilling Programme & results at
target SGC_1
DHEM surveys at target SGC_1
Diamond drilling to test interpreted
conductors at SGC_1
Further drill-testing at SGC_1also
considering targets SGC_2 to 8
ASX:WWI
PAGE |
18
QALA SHALLOWS BOX CUT
CHIEF OPERATIONS OFFICER
INVESTOR RELATIONS
Rudi Deysel
Keith Middleton
+27 (0)78 680 2864
rdeysel@westwitsmining.com
+61 438 101 102
keith@middletoncorporate.com.au
South Africa
Unit 8A, Sifon Industrial Park
285 Sifon Street, Robertville
Roodepoort
1709
Australia
Level 6, 400 Collins Street
Melbourne, Victoria
Australia
3000
westwitsmining.com | info@westwitsmining.com
ASX:WWI
PAGE |
19
REFERENCES
1.
The original report was “Updates to Qala Shallows DFS provide improved results for Witwatersrand Basin Project” which was issued with consent of the Competent Person, Mr. Andrew Pooley. The report
was released to the ASX in July 2023 and can be found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the
information included in the relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the
relevant market announcement continue to apply and have not materially changed. The form and context in which the Competent Person’s findings are presented have not been materially modified from
the original market announcement.
2.
The original report was “WBP’s Global JORC Mineral Resource Expands by 724,000oz to 4.28MOZ at 4.58 g/t Gold” which was issued with consent of the Competent Person, Mrs Cecilia Hattingh. The report
was released to the ASX on 3 December 2021 and can be found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects
the information included in the relevant market announcement and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in
the relevant market announcement continue to apply and have not materially changed. The form and context in which the Competent Person’s findings are presented have not been materially modified
from the original market announcement.
The original report was “West Wits advances exploration work on Uranium at WBP” which was issued with consent of the Competent Person, Mr Michael Robertson. The report was released to the ASX on 25
October 2021 and can be found on the Company’s website (https://westwitsmining.com/). The potential quantity and grade of the Exploration Target are conceptual in nature, there has been insufficient
exploration and evaluation of historical information to estimate a Mineral Resource. It is uncertain if further exploration will result in the estimation of a Mineral Resource. The Company is not aware of any
new information or data that materially effects the information included in the relevant market announcement. The form and context in which the Competent Person’s findings are presented have not been
materially modified from the original market announcement.
The original report was “Positive Phase 1 Uranium Drilling Results for West Wits” which was issued with consent of Competent Persons Mr. Michael Robertson. The report was released to the ASX on 6
October 2022 and can be found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the information included in the
relevant market announcement. The form and context in which the Competent Person’s findings are presented have not been materially modified
The original report was “HEM Survey Identifies Eight Targets Areas at Mt Cecelia” which was issued with consent of the Competent Person, Mr. Russell Mortimer. The report was released to the ASX on
16/12/2020 and can be found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the information included in the
relevant market announcement. The form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
The original report was “Significant Maiden Gold Intercept at Mt Cecelia” which was issued with consent of Competent Person, Mr. Martin Bevenlander. The report was released to the ASX on 18/01/2023 and
can be found on the Company’s website (https://westwitsmining.com/). The Company is not aware of any new information or data that materially effects the information included in the relevant market
announcement. The form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
The original report was “Mt Cecelia Project DHEM Survey Results” which was issued with consent of the Competent Person, Mr Martin Bevenlander, who is a Member of SACNAS Reg. # 400158/07 – The South
African Council of Natural Scientific Professions and fairly represents this information. Mr Bevelander has sufficient experience relevant to the style of mineralisation and type of deposit under
consideration, and to the activities undertaken, to qualify as a Competent Person as defined in the 2012 Edition of the Joint Ore Reserves Committee (JORC) Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves. Mr Bevenlander is a WWI employee and consents to the inclusion in the report of the matters based on his information in the form and context in which it
appears.
3.
4.
5.
6.
7.
ASX:WWI
PAGE | 20
Share your feedback
Discover