Annual Report to shareholders
Released
Released
Announcement PDF
Annual Report 2026
FOR THE YEAR ENDED 30 JUNE 2026
West Wits Mining Limited | ABN 8912489060
West Wits Mining Limited
Contents
30 June 2026
1
Corporate directory 2
Chairman's Letter 3
Review of Operations 4
ORE reserve and MRE statement 14
Directors' report 18
Auditor's independence declaration 38
Statement of profit or loss and other comprehensive income 39
Statement of financial position 40
Statement of changes in equity 41
Statement of cash flows 43
Notes to the financial statements 44
Consolidated entity disclosure statement 73
Directors' declaration 74
Independent auditor's report to the members of West Wits Mining Limited 75
Shareholder information 82
West Wits Mining Limited
Corporate directory
30 June 2026
2
Directors Mr Michael Quinert, Executive Chairman
Mr Rudi Deysel, Managing Director and Chief Executive Officer
Mr Jac van Heerden, Non-Executive Director
Mr Warwick Grigor, Non-Executive Director
Mr Keith Middleton, Non-Executive Director
Joint Company Secretaries Mr Simon Whyte
Mr Paul Godfrey
Registered office and Level 6, 400 Collins Street
Principal place of business Melbourne VIC 3000
Australia
Share register Automic Pty Ltd
Level 5 126 Phillip Street
Sydney NSW 2000
+61 2 9698 5414
Auditor William Buck
Level 20, 181 William Street
Melbourne VIC 3000
Solicitors QR Lawyers
Level 6, 400 Collins Street
Melbourne VIC 3000
Bankers National Australia Bank
Level 2, 330 Collins Street
Melbourne VIC 3000
Stock exchange listing West Wits Mining Limited shares are listed on the Australian Securities Exchange
(ASX code: WWI)
Website https://westwitsmining.com/
West Wits Mining Limited
Chairman's Letter
30 June 2026
3
Dear Fellow Shareholders,
For the better part of a half a century, the Central Rand was spoken of in the past tense; the goldfield that built Johannesburg
and then, so conventional wisdom held, surrendered everything it had. When we set out to prove otherwise, a measure of
scepticism came with the territory.
This was the year that scepticism began to look misplaced.
On 17 March 2026, West Wits poured its first gold at Qala Shallows. After years working on the geology, permitting and
feasibility studies, we watched ore from beneath the West Rand become metal, the plainest possible proof that the ounces
we have long carried in our resource statements are real and mineable. By 30 June we had produced 227 ounces and will
keep adding to that total from here. These are early ounces, and we hold no illusions about the ramp-up still in front of us. But
every mine that has ever reached scale began precisely here: with a first pour and a decision to keep going.
The wider industry appears to share our conviction. In December we officially opened Qala Shallows, recognised as the first
new underground gold mine developed in South Africa in more than fifteen years. The occasion drew the Honourable Gwede
Mantashe, Minister of Mineral and Petroleum Resources; the Australian High Commissioner, Her Excellency Ms Tegan Brink
and the Chief Executive of the Minerals Council South Africa, Mr Mzila Mthenjane, to a marquee west of Johannesburg. That
is not a room a written-off project can fill.
Behind the ceremony lay a year of unglamorous progress. We grew the Witwatersrand Basin Project’s Mineral Resource base
to 7.24 million ounces Au, a 2.2-million-ounce increase that lengthens the potential runway ahead of us. An updated definitive
feasibility study lifted the project’s post-tax net present value to US$500 million and its internal rate of return to 81%, with free
cash flow up by almost ninety per cent, the economics improving precisely as we moved to prove them. And in late May, our
1 West decline broke through into a historically developed mining horizon, handing us access to established stoping areas
and saving roughly a year of development we would otherwise have had to carve from scratch. Good fortune played its part;
disciplined planning made us ready to use it.
None of this would matter if we could not fund it. In the final quarter of the year we closed a ZAR1.115 billion project finance
package with Absa and Nedbank CIB, two of South Africa’s foremost mining financiers. Debt of that scale, from lenders of
that standing, is not extended on faith; it is extended on technical merit. Alongside roughly A$51.4 million raised over the year
from institutional investors and anchored by Tribeca Investment Partners, it means Qala Shallows is funded through to steady-
state production. We also lifted our interest in the project to 74% and simplified our capital structure, so that as much of the
value we create as possible accrues to you, our shareholders.
I cannot write about this year without pausing on its hardest moment. In June, a mud-rush incident at Qala Shallows took the
life of a contractor’s employee. No milestone in this letter weighs against that loss, and on behalf of the Board I extend our
deepest sympathies to his family and colleagues. We notified the authorities, paused the affected operations and cooperated
fully with the investigation, which concluded with no adverse findings against the Company and all restrictions lifted. We take
no comfort in that outcome beyond the obligation it reinforces: everyone who goes underground at Qala Shallows must come
home. That commitment sits above every target in this report.
A word on the people carrying the work. In July, Rudi Deysel was appointed Managing Director, recognising the leadership
that took Qala Shallows from concept to operating mine. Our workforce grew steadily toward its steady-state complement of
around 1,100 and our community and skills programmes deepened alongside it, the surest sign that a mine is becoming part
of the place it operates.
We enter the new year with our ambition intact and, if anything, extended. Qala Shallows is Stage 1: a mine designed to
produce roughly 70,000 ounces Gold a year. Through our Project 200 study we are testing a credible path toward something
far larger and we do so with gold trading well above the prices our feasibility work assumed. The task now is execution, turning
a first pour into a steady, safe and profitable operation, and a single mine into the foundation of a far bigger business.
To our shareholders: thank you for your patience and your belief through the years when this was a story told largely on paper.
This year, it began to be told in gold. On behalf of the Board, I look forward to writing the next chapter with you.
Yours sincerely,
Michael Quinert
Executive Chairman
West Wits Mining Limited
Review of Operations
30 June 2026
4
The Journey to First Gold
For much of the past century, the Central Rand Goldfield — the district on which Johannesburg's gold industry was founded
— was widely considered mined out. West Wits took a different view. Backed by rigorous geological work and a disciplined
development plan, the Company set out to prove that economic gold remained within reach at Qala Shallows.
Image 1 records that transformation. At its centre is the box cut, the surface excavation from which the underground decline
descends. First carved in 2021 and progressively developed, collared and shotcrete, it became the fixed point around which
the mine took shape year on year, even through a pause in development while project funding was secured. Throughout that
period the project continued to draw senior industry visitors, including the Minerals Council South Africa.
With financing in place, Qala Shallows was officially opened in December 2025 — the first new underground gold mine
developed in South Africa in over 15 years — and poured its first gold in March 2026, within five years of ground first being
broken. What began as a deposit on paper is today an operating mine.
IMAGE 1: THE TRANSFORMATION OF QALA SHALLOWS GOLD MINE, 2018–2026
Review of Operations
Financial Year Ended 30 June 2026
West Wits Mining Limited (ASX: WWI; OTCQB: WMWWF) (“West Wits” or “the Company”) is an emerging South African gold
producer focused on the Witwatersrand Basin Project ("WBP") in South Africa's Central Rand Goldfield. The WBP hosts a
7.24Moz JORC Mineral Resource at 4.0g/t gold. During FY2025-26, West Wits began its transition to becoming a gold
producer, pouring first gold at its Qala Shallows underground mine in March 2026 under a toll-treatment agreement with
Sibanye-Stillwater's Ezulwini Plant whilst progressing underground mine development. With its full project finance package
now in place, the Company is ramping up toward a steady-state target of approximately 70,000oz of gold per annum which is
scheduled for the 2028/29 financial reporting period.
West Wits Mining Limited
Review of Operations
30 June 2026
5
HIGHLIGHTS
Qala Shallows Operations
➢ First Gold Production Achieved: Qala Shallows delivered its maiden gold pour in March 2026, with
7.05kg (227oz) of gold produced from on-reef development ore by 30 June 2026 — marking West
Wits’ transitioning from developer to near-term gold producer.
➢ 1 West Decline Breakthrough: access gained to historically pre-developed, higher-grade stoping
areas at Qala Shallows, requiring only minor modifications to accommodate modern trackless mining
vehicles and accelerating the path to the DFS-modelled steady-state target of approximately 70,000oz
per annum1.
➢ Resource Base Expanded to 7.24Moz: a 2.2Moz increase to the Witwatersrand Basin Project’s
Global JORC Mineral Resource Estimate, driven by a new depth-extension Prospecting Right and a
lower cut-off grade, underpinning a longer potential mine life and future production growth.
➢ Underground Development: 544m of underground development achieved during the year, including
375m on-reef and 168m waste development.
Corporate
➢ Full Project Finance Package Completed: a ZAR1.115 billion (~A$97 million) financing package
comprising a ZAR875 million Senior Loan Facility, a ZAR150 million Working Capital Facility and a
ZAR90 million Cost Overrun Debt Facility was secured with Absa Bank and Nedbank Corporate and
Investment Banking (“Nedbank”), materially de-risking the path to steady-state production.
➢ Capital Raised to Fund the Ramp-Up: approximately A$51.4 million raised across two institutional
placements during the year (A$17.7 million in September 2025 and A$33.74 million in January 2026),
together with debt facilities, fully funding Qala Shallows through to steady-state production.
➢ Portfolio Rationalisation: a binding agreement to divest the non-core Mt Cecelia Project in Western
Australia for equity, a royalty and milestone consideration, allowing management and capital to focus
exclusively on Qala Shallows and the broader WBP growth pathway.
➢ Capital Consolidation: issued capital consolidated on a 10-for-1 basis, reducing shares on issue to
434,647,512 ordinary shares and simplifying the capital structure ahead of the institutional finance
close.
West Wits Mining Limited
Review of Operations
30 June 2026
6
OPERATIONS AND PROJECT DEVELOPMENT
SOUTH AFRICA
WITWATERSRAND BASIN PROJECT (“WBP”), GAUTENG, SOUTH AFRICA
The WBP is West Wits’ flagship asset, located in the Central Rand Goldfield, one of the world’s most prolific gold-producing
regions. The Project comprises the Qala Shallows mine together with a series of adjacent growth targets — the Main Reef
Package, Bird Reef East, Bird Reef Central and Qala Deeps — held under a Mining Right and two Prospecting Rights.
During the year, West Wits increased its interest in the Project from 66.6% to 74% through the US$5.09 million buy-back of a
minority shareholder’s 10% interest in West Wits Mining SA (Pty) Ltd, completed in August 2025. Management characterised
the transaction as value-accretive in light of the upgraded project economics confirmed by the updated DFS, strengthening
the Company’s long-term exposure to project cash flows.
QALA SHALLOWS GOLD PROJECT
Qala Shallows is the first stage of the WBP and, on its official opening in December 2025, was recognised as the first new
underground gold mine to be developed in South Africa in over 15 years. The Project transitioned during the year from
mobilisation to underground development and first gold production — the central operational narrative of FY2025-26.
IMAGE 2: AERIAL VIEW OF QALA SHALLOWS, WEST OF JOHANNESBURG, GAUTENG
Development and Production Ramp-Up
The year opened with the completion of a three-month mobilisation programme, positioning Qala Shallows for underground
works. Ore transfers to Sibanye-Stillwater’s Ezulwini Plant, under a toll-treatment agreement, began soon after, with ore
stockpiled on a dedicated pad ahead of processing. First underground ore was delivered to surface in October 2025, supported
by the completion of an engineered box-cut haul road, water management systems and safety infrastructure including
proximity detection, fire suppression and underground communications systems.
Underground development continued through the second half of the year, with the commencement of main decline
development and the first production blast completed in the December 2025 quarter. Qala Shallows achieved its inaugural
gold pour at the Ezulwini Plant on 17 March 2026, delivering 2.54kg of gold in that month — a milestone that management
described as marking West Wits’ transitioning to a near-term gold producer. Underground development advanced with
continued delivery development ore to Ezulwini; the Company reported 4.6kg (148oz) of gold produced in the June 2026
quarter, taking cumulative production to 7.05kg (227oz) by 30 June 2026.
West Wits Mining Limited
Review of Operations
30 June 2026
7
IMAGE 3: 1 WEST DECLINE BREAKTHROUGH ACHIEVED AT QALA SHALLOWS
A significant operational milestone was achieved at the end of May 2026, when the 1 West Decline broke through into the
historically pre-developed 2 Level mining horizon. This gave Qala Shallows access to established, unmined stoping areas
requiring only minor modification for modern trackless mining vehicles — work that management estimated would otherwise
have taken approximately one additional year to develop from scratch. By shortening the path to higher-grade ore, the
breakthrough is expected to improve mine grades and cash generation during the ramp-up phase and to accelerate progress
toward the DFS-modelled steady-state production profile of approximately 70,000oz per annum.
IMAGE 4: QALA SHALLOWS UNDERGROUND DEVELOPMENT WITH EXISTING WESTERN STOPING AREAS NOW
ACCESSIBLE FOLLOWING 2 LEVEL BREAKTHROUGH VIA 1 WEST (1W) DECLINE
By year-end, total underground development reached 544 metres (375 metres on-reef and 168 metres waste), comprising 63
metres on the Main Decline, 53 metres on the 1 East Decline and 132 metres on the 1 West Decline. Development through
the shallow, weathered zone near surface on the Main Decline required additional support work during the year; that ground
was left behind shortly after year-end, allowing for standard roof bolting and shotcreting for improved advance rates going
forward.
West Wits Mining Limited
Review of Operations
30 June 2026
8
Underground fleet capacity was expanded progressively across the year, including the delivery and commissioning of the first
Load-Haul-Dump unit and double-boom drill rig in the first quarter, and further additions to the fleet including a new 10-tonne
LHD unit and a third jumbo drill rig in the final quarter. Surface infrastructure also advanced materially: a new Main Store
warehouse facility, storm water management system were completed, pollution control dam excavations and haulage road
construction reached approximately 90% completion, and a new tarred access road improving site logistics and accessibility.
Overall surface infrastructure works were 45% complete at year-end.
IMAGE 5: OPERATIONAL INFRASTRUCTURE UPGRADES AND UNDERGROUND FLEET
EXPANSION ACTIVITIES AT QALA SHALLOWS
Mineral Resource Estimate Growth
On 2 February 2026, West Wits announced a 2.2Moz increase to the WBP’s Global JORC Mineral Resource Estimate, taking
the total to 7.24Moz at 4.0g/t gold. The increase was driven by the grant of Prospecting Right PR10839 in December 2025,
which provided a depth extension to the Kimberley Reef ore body contributing approximately 1.2Moz at 4.38g/t, together with
a reduction in the cut-off grade applied to the Kimberley Reef area from 2.0g/t to 1.24g/t, reflecting materially higher prevailing
gold prices and adding a further approximately 1Moz.
JORC 2012 compliant Mineral Resource Estimate as at 30 June 2026
Category Tonnes (M) Grade (g/t Au) Ounces
Measured 14.08 4.40 1,991,000
Indicated 15.55 4.04 2,020,000
Measured & Indicated 29.63 4.21 4,012,000
Inferred 26.81 3.75 3,232,000
Total 56.44 4.00 7,244,000
Note: discrepancies in totals are due to rounding.
Mineral Resources are reported in accordance with the JORC Code (2012 Edition) and are inclusive of Ore Reserves. With
4.0Moz (55%) classified as Measured and Indicated, the update strengthened the Mineral Resource base and provides the
geological foundation for the longer-term growth pathway being assessed under the Project 200 Scoping Study.
West Wits Mining Limited
Review of Operations
30 June 2026
9
Project 200 Scoping Study and BRC Uranium-Gold Opportunity
During the year, West Wits commenced a scoping study — Project 200 — assessing a pathway to scale WBP production
toward an aspirational target of approximately 200,000oz per annum, compared with the current Stage 1 DFS target of
approximately 70,000oz per annum. The study, being undertaken by Bara Consulting, was initially targeted for completion in
June 2026; its scope was subsequently expanded to assess multiple development and processing pathways — including a
standalone processing plant, third-party toll-processing partnerships, and the integration of additional WBP ore sources.
The Scoping Study was completed in August 2026 on the basis of a 35-year life-of-mine model for the Witwatersrand Basin
Project. The Scoping Study considers the broader tenure of the Company within the Witwatersrand Basin and incorporates
Qala Shallows, which is currently in development. Under the Scoping Study, the proportion of Inferred Mineral Resources
arising across the full 35-year life-of-mine of the Project was an aggregate of 74%, with certain years within the mine plan
contained in the Scoping Study including proportions of Inferred Mineral Resources exceeding 90%.
The Company views the results of the Scoping Study as positive and as meeting its internal objectives which were
predominantly to enable a decision on the merits of progressing Project 200 into the pre-feasibility stage. It had intended to
release full details of the Scoping Study. However, following consultation with the ASX the Company concluded that releasing
the Scoping Study as completed would not meet ASX requirements given the proportion of Inferred Mineral Resources used
in the production target and the financial information derived from same.
The Company intends to continue to progress Project 200 and the development of the WBP through to the next level of
studies. As part of that process, the Company will also seek to complete additional work, including to convert more Inferred
Mineral Resources into higher confidence categories of Mineral Resources
The Company also continued to assess its Bird Reef Central target, located within the WBP Mining Right, for its potential as
a standalone uranium-gold project.
Surface Infrastructure and Energy Security
Reliable power supply was a recurring operational focus during the year. In response to rising risks in energy security and the
need for continuity during ramp-up, the Company implemented a multi-layered diesel fuel strategy, securing access to
approximately 163,000 litres of diesel by the March 2026 quarter — providing roughly 3.5 to 4 months of coverage under
planned consumption. This measure ensured no disruption to production during the year. Connection to grid power, which is
expected to materially reduce diesel consumption and associated costs once complete, was targeted for the fourth quarter of
calendar 2026 as at March 2026; by year-end, this had been revised to an estimated connection date of early 2027 with
sufficient diesel power generation capacity to meet requirements.
Future Focus
West Wits enters FY2026-27 with underground development and ore delivery continuing to ramp up toward steady-state
production, and with several outcomes pending: advances Project 200 Scoping Study initiatives including conversion of
Inferred Mineral Resources to higher confidence categories and further studies; progress toward a maiden Uranium Mineral
Resource Estimate at Bird Reef Central; and connection to grid power, now targeted for early 2027.
AUSTRALIA
MT CECELIA PROJECT (E45/5045), PATERSON PROVINCE
West Wits 100% owned Mt Cecelia Project in Western Australia’s Paterson Province was subject to a farm-in arrangement
under which Rio Tinto Exploration Pty Ltd (“RTX”) could earn up to an 80% interest by spending A$10 million on exploration.
RTX’s Stage 1 farm-in rights lapsed in December 2025, having spent approximately A$1.5 million against the required A$4
million threshold for 51% ownership. Following the lapse, the Company assessed options to either progress a Company-led
exploration programme or introduce a third party to advance the Project, noting strong regional interest supported by the
prevailing gold price.
On 29 April 2026, West Wits announced a binding agreement to divest Mt Cecelia by selling 100% of Northern Reserves Pty
Ltd, the Project’s holding entity, to Aventine Resources Limited (“Aventine”), a gold-copper explorer focused on the Paterson
Province. Consideration comprises A$2.0 million in Aventine equity (currently equating to 10,000,000 Aventine fully paid
ordinary shares at the IPO price), a 1% Net Smelter Royalty over future production (with a right for Aventine to buy back half
the royalty for a further A$2.0 million), and deferred consideration of up to A$1.0 million payable if a JORC Inferred or greater
Mineral Resource Estimate of at least 500,000oz gold at a 0.5g/t cut-off is declared within five years of completion.
The transaction would remove all further capital obligations at Mt Cecelia while retaining meaningful exposure to its exploration
upside, freeing management attention and capital to focus on the Qala Shallows ramp-up and the Project 200 growth strategy.
As at 30 June 2026, completion remained conditional on Aventine’s proposed ASX listing and capital raising, and customary
regulatory approvals.
West Wits Mining Limited
Review of Operations
30 June 2026
10
ENVIRONMENTAL, SOCIAL AND GOVERNANCE (“ESG”)
Safety
The Company reports with regret that a mud rush incident occurred at Qala Shallows on 10 June 2026, resulting in the fatality
of a contractor’s employee. West Wits extended its condolences to the worker’s family, friends and colleagues, formally notified
the South African Department of Mineral and Petroleum Resources (“DMPR”) in accordance with regulatory protocols, and
paused affected underground operations while the Department conducted its investigation. The investigation was completed,
with all operational restrictions subsequently lifted and no adverse findings made against West Wits. The pause in operations
required to support the investigation contributed, alongside development through weathered ground on the Main Decline, to
delays in underground development during the year.
Social & Labour
West Wits’ underground and surface labour contingent grew over the course of the year to 431 personnel at 30 June 2026
(64 on the Company’s Owners Team and 367 Contractors), on a trajectory toward an anticipated steady-state workforce of
approximately 1,100. In May 2026, the Company strengthened its operational leadership with the appointment of Sephela
Makete Thema as Head of Operations, bringing prior senior operating experience from Sibanye-Stillwater and Fraser
Alexander.
The Company continued its community and workforce development programmes throughout the year, including a Portable
Skills Programme (launched October 2025) and an Internship Programme (commenced February and March 2026) spanning
environmental studies, rock engineering, geology, chemical engineering, finance, mine planning, mine ventilation and mine
survey disciplines. West Wits also launched a Food Vendor Project during the year, providing fitted facilities and infrastructure
to local food and beverage enterprises operating on-site, and facilitated a Terms of Reference workshop establishing a formal
governance framework with the Local Economic Development Forum representing the nine wards covered by the Company’s
Social and Labour Plan.
IMAGE 6: MEMBERS OF THE LOCAL ECONOMIC DEVELOPMENT (LED) FORUM DURING THE TERMS OF
REFERENCE WORKSHOP
West Wits Mining Limited
Review of Operations
30 June 2026
11
CORPORATE
Project Finance and Capital Structure
Financing activity underpinned the year’s operational progress. In September 2025, West Wits completed a A$17.7 million
equity placement and executed definitive agreements for a US$12.5 million first tranche of a scalable US$35 million debt
facility with Nebari Natural Resources Credit Fund II LP (“Nebari”), which was drawn in November 2025. This bridge funding
enabled the ramp-up of underground operations, equipment purchases and continued ore delivery to Ezulwini ahead of the
completion of longer-term project finance.
In January 2026, the Company completed a further A$33.74 million institutional placement, anchored by a A$10 million
strategic investment from Tribeca Investment Partners, which management stated fully funded Qala Shallows through to
steady-state production and provided capital to advance Project 200 and the BRC uranium-gold target.
The year’s most significant financing milestone came in the June 2026 quarter, when West Wits completed its full project
finance package with Absa Bank Limited and Nedbank Corporate and Investment Banking:
Facility Amount (ZAR) Purpose Rate Lender(s)
Senior Loan Facility 875,000,000 Project development,
ramp-up & production at
Qala Shallows
ZARONIA-
linked
Absa /
Nedbank CIB
Working Capital Facility
(WCF)
150,000,000 Fund production working
capital cycle via invoice
drawdowns
Prime-
linked
Absa /
Nedbank CIB
Cost Overrun Debt Facility
(CODF)
90,000,000 Contingency funding for
cost overruns after Senior
Facility drawdown
ZARONIA-
linked
Absa /
Nedbank CIB
TOTAL PACKAGE 1,115,000,000
Completion of this package, from two of South Africa’s leading mining finance institutions, represented an institutional
endorsement of Qala Shallows’ technical credentials and commercial viability. As a condition of financial close, the US$12.5
million Nebari bridge facility was fully repaid on 26 June 2026, transitioning the Company from bridge funding to a lower-cost,
longer-tenure institutional finance structure purpose-built for a producing mine. The Company also put in place a hedging
structure protecting 50% of planned gold sales through construction (Ore Reserves only) via a put option programme at a
ZAR 57,750/oz (USD 3,500/oz @ ZAR/USD 16.5) strike price, preserving upside exposure to gold prices, which has traded
at levels above the DFS’s US$2,850/oz base case assumption since Q1 2025.
At 30 June 2026, the Company held A$32.1 million of cash.
Capital Consolidation
Following shareholder approval at a general meeting held 8 April 2026, West Wits consolidated its issued capital on a 10-for-
1 basis. Updated holding statements were dispatched on 16 April 2026. Management characterised the consolidation as
simplifying the Company’s capital structure ahead of continued institutional engagement. The post-consolidation capital
structure was as follows:
Class of Security Pre-Consolidation Post-Consolidation
WWI (Ordinary Shares) 4,346,465,221 434,647,512
WWIO (Listed Options) 302,551,631 30,255,205
WWIAC (Unlisted Options) 386,963,596 38,696,376
WWIAD (Performance Rights) 2,500,000 250,000
WWIAG (Warrants) 166,933,764 16,693,377
West Wits Mining Limited
Review of Operations
30 June 2026
12
West Wits maintained an active investor engagement programme throughout the year, presenting at conferences and
roadshows across Australia, Asia, Europe and South Africa, including Diggers & Dealers, Africa Downunder, the Munich
Mining Conference, the Noosa Mining Conference, Mining Indaba, the 121 Mining Investment Conference, the RIU Explorers
Conference and RIU Sydney Resources Round-up, the Gold Coast Gold Conference, the ASX Midcaps Conference, Junior
Indaba, and investor summits in Hong Kong. The Company’s Annual General Meeting was held on 20 November 2025.
Official Opening Event at Qala Shallows
West Wits officially opened the Qala Shallows Underground Mine on 5 December 2025. The event was addressed by the
Honourable Gwede Mantashe, Minister of Mineral and Petroleum Resources; Her Excellency Ms Tegan Brink, Australian
High Commissioner and Mr Mzila Mthenjane, CEO of the Minerals Council South Africa, alongside the West Wits executive
team, and drew community stakeholders, investors and media, underscoring the project's significance to the South African
gold sector.
IMAGE 7: THE OFFICIAL OPENING OF QALA SHALLOWS, ATTENDED BY THE HONOURABLE GWEDE MANTASHE,
MINISTER OF MINERAL AND PETROLEUM RESOURCES; AUSTRALIAN HIGH COMMISSIONER HER EXCELLENCY
MS TEGAN BRINK; MINERALS COUNCIL SOUTH AFRICA CEO MR MZILA MTHENJANE AND THE WEST WITS
EXECUTIVE TEAM, WITH A COMMISSIONED RENDERING OF THE QALA SHALLOWS MINE
West Wits Mining Limited
Review of Operations
30 June 2026
13
Awards and Recognition
West Wits Mli (Pty) Ltd Executive Director and Head of Corporate Affairs, Tozama Kulati Siwisa, received the “Most Visionary
Architect of Sustainable Mining and Social Transformation 2026” award at The Global Icons of Impact 2026, in recognition of
her leadership in integrating social impact into West Wits’ growth strategy.